HSHQEC11R00007 Amendment 0002.pdf
PDF 61 KB Posted
- Attached to
- Protective Security Officer Services
- Solicitation number
- HSHQEC-11-R-00007
About this file
Amendment 02
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 6_Price Element Breakdown.xlsm | XLSM spreadsheet | |
| EXHIBIT 1A_Supervisory Post Exhibit Multiple Sites.xls | XLS spreadsheet | |
| Attachment 3- Past Project Form.doc | DOC document | |
| Seniority List.pdf | ||
| Exhibit 11 Monthly Status Report.doc | DOC document | |
| Attachment 4- Past Performance Questionaire.doc | DOC document | |
| HSHQEC11R00007 Amendment 0001.pdf | ||
| HSHQEC-11-R-00007.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NSN 7540-01-152-8070 STANDARD FROM 30 (REV. 10-83)
1. CONTRACT ID CODE PAGE OF PAGES
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1 4
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
0002 August 18, 2011
6. ISSUED BY CODE GI000 7. ADMINISTERED BY (If other than Item 6)
US Department of Homeland Security Federal Protective Service Office of Procurement Operations 701 Market Street, Suite 4200 Philadelphia, PA 19106 Attn: D.Abraham, (215) 521-2292, Debby.Abraham@dhs.gov
8. NAME AND ADD
RESS OF CONTRACTOR (No., street, county, State, and ZIP Code)
( ) 9A. AMENDMENT OF SOLICITATION NO.
HSHQEC-11-R-00007
9B. DATED (SEE ITEM 11)
August 11, 2011
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers Is extended, X is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; of (c) By separate letter of telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
() A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b)
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, Is required to sign this document and return copies to the issuing office.
14. DECRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
See Page 2
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type of print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or Print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
PREVIOUS EDITION UNUSABLE Prescribed by GSA
FAR (48 DFR) 53.243
mailto:Debby.Abraham@dhs.gov
A. Section: CONTINUITY OF CRITICAL CONTRACTOR DELIVERABLES (SERVICES IN THE EVENT OF AN EMERGENCY (October 2009) (tailored)- Pages 30, section 1b- COOP Plan is not required to be addressed within the Management Approach technical evaluation factor.
B. Evaluation Criteria, Section 2 Management Approach, pg. 42, Staffing and COOP are not required to be addressed as part of the technical proposal.
C. The correct page limitation for technical proposals is 12 pages. Section 1 D. on page 41 under Technical Proposal is deleted in its entirety and replaced with the following:
D. Where contractor teaming arrangements (as defined at FAR Subpart 9.6) are proposed, a narrative shall be submitted as part of the proposal which clearly details the roles, responsibilities, and distribution of effort (by type and percentage) between the parties in performance of the Government’s requirement.
This information should be provided by the managing partner of the joint venture or the prime contractor as a one (1) page supplement to its Past Project Forms (Attachment 3 of the SSP) and will not count against the 12-page size limitation on the proposal.
D. The following clauses are hereby deleted in its entirety:
HSAR 3009-108-7005 on page 27 FAR 52.209-2 on page 61
E. Page 19, FAR 52.222-100- NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL
LABOR RELATIONS ACT (DEVIATION 10-03) (JUN 2010) is replaced with the following: FAR
52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS
ACT) (Dec 2010)
F. Page 46: The Government’s estimated Other Direct Costs (ODCs) (inclusive of applicable indirect burden(s)) shall be used for the purpose of evaluating the price proposal. Therefore, offerors shall use these estimates in preparing their price proposal. For applicable Indirect Burden rates (i.e. G&A and Material Handling), separately identify such indirect rates for the proposed Base and four option years in the chart below. Since this is a commercial contract, note that these rates are fixed throughout the life of the contract and not subject to adjustment. Additionally, please identify your accounting practices for applying the proposed indirect rates to the ODCs (i.e whether G&A applies to all costs or all non-material/subcontractor costs).
The following sentence: “For applicable Indirect Burden rates (i.e. G&A and Material Handling), separately identify such indirect rates for the proposed Base and four option years in the chart below.”
Is replaced with the following:
“For applicable Indirect Burden rates (i.e. G&A and Material Handling), separately identify such indirect rates for the proposed ordering period in the chart below.”
G. The following questions and answers are provided for informational purposes only:
1. Section 14.4.11 of the PWS states that the PSO must qualify with the weapon used on post and that there will be “no sharing” of weapons. As any successful bidder would be providing weapons that are not currently on post will the incumbent officers be required to re-qualify with their new duty weapon or will their qualification status be “grandfathered”?
Answer: Incumbent officers will be required to re-qualify with their new duty weapon.
2. Section 14.4.11 of the PWS states that the PSO must qualify with the weapon used on post and that there will be “no sharing” of weapons. Does this apply to all current qualified PSO who are currently working on FPS contracts or does it only qualify to new hires and any semi-annual qualifications?
Answer: Applies to all PSOs, both current officers and new hires, working under this effort. Relief officers and supervisors will also require individually assigned weapons.
3. Page 42 of the exhibits include a shotgun qualification course. Are there any post on this contract that require shotgun qualification?
Answer: No posts require shotguns.
4. Section 6.6.1.8 of the PWS states “PSOs shall wear complete duty uniform for firearms training and qualification, to include issued body armor, duty belt and equipment.” Currently FPS personnel do not allow PSO candidates to wear a uniform during qualifications as they are not yet FPS qualified PSOs. Does this requirement only apply to refresher and semi-annual re-qualifications?
Answer: Yes.
5. Section 5.3.1.13 of the PWS states “Contractors shall use local, state, or Federal law enforcement sources to obtain readable fingerprints…” We have provided contractor provided, readable prints for years at no cost to the government. Are contractors allowed to continue providing prints or are we required to use government sources building in any applicable costs?
Answer: The solicitation is clear on its face.
6. Amendment 1 references an Exhibit 4I but 4I is not in the RFP. Can you please provide a copy of Exhibit 4I for costing purposes?
Answer: There is no Exhibit 4I. Please disregard the reference to this exhibit in Amendment 01.
7. Exhibit 7 Medical Questionnaire and Physical Abilities Test is a different medical form than what is currently used on other local FPS contracts. Will FPS qualified PSOs who currently work on other contracts be allowed to work on this contract with their currently approved SF78 medical exams?
Answer: No
8. Are the incumbent PSOs grandfathered regarding the medical exam and PAT as described in Exhibit 7?
Answer: No
9. Item 14.4.8 states that Exhibit 8C shows the number of contingency rounds to be stored but Exhibit 8C does not show the number of rounds. How many rounds are to be stored as contingency rounds?
Answer: 15 rounds per post
10. RFP Page 39 indicates 12 pages for proposal submission. RFP Page 41 refers to a 20-page size limitation. Please clarify proposal page limit.
Answer: The correct page limitation for technical proposals is 12 pages. See paragraph C of this amendment.
11. Please clarify the security clearance requirements for the Contractor, Project Mgr., PSO's, etc.
Answer: Please refer to the post exhibit and Statement of Work.
12. Which weapons platform are the incumbent personnel at each individual site currently on?
Answer: This was addressed in Amendment 01, paragraph K.
13. Does/Do the current contract/s require incumbent contractors to provide individually assigned weapons to the personnel?
Answer: No
14. It is our understanding that the contract awardee should have documents pertaining to the basic FPS training and firearms training for each officer working under the contract. In the absence of such documents, the contractor will be required to retrain the officers who are missing these documents.
a. Do the incumbent contractors have the above stated documents for each incumbent personnel?
Answer: To the best of FPS’ knowledge, yes.
b. Will the incumbent contractors be required to provide these documents to the awardee?
Answer: See Amendment 01, Paragraph N
15. Are all incumbent personnel current on Baton and OC spray as required under the subject RFP?
Answer: The current contracts require batons, but not OC spray (see Amendment 01, paragraph K). To the best of FPS’ knowledge, incumbent security officers are current with baton training (see Amendment 01, paragraph N).
16. Is there a site visit scheduled?
Answer: See Amendment 01, Paragraph O