P4599471Spc.pdf
PDF 2 MB Posted
- Solicitation number
- HSCGG1-13-B-PRV258
About this file
Project Specifications for HSCGG1-13-B-PRV258
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid_Abstract_Results.pdf | ||
| Amendment_0003_Chgs_Wages.pdf | ||
| Amendment_0002_questions_and_concerns.pdf | ||
| Amend_0001.pdf | ||
| IFB_HSCGG1-13-B-PRV258.pdf | ||
| P4599471Dwg.pdf | ||
| Wage_Rate_July2013.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
SHORE INFRASTRUCTURE LOGISTICS CENTER
SPECIFICATION
FOR
ELECTRICAL DISTRIBUTION UPGRADE
AT
USCG STATION FIRE ISLAND, NEW YORK
WORK ORDER No. 4599471
PROJECT ENGINEER BRANCH CHIEF
TECHNICAL DIRECTOR, by direction
COMMANDING OFFICER
UNITED STATES COAST GUARD
CIVIL ENGINEERING UNIT PROVIDENCE
300 METRO CENTER BLVD
WARWICK, RHODE ISLAND 02886
USCG STATION FIRE ISLAND ELECTRICAL DISTRIBUTION UPGRADE
TABLE OF CONTENTS Page 1
TABLE OF CONTENTS
SPEC SECTION PART PAGE TITLE
01 11 00 1 1 SUMMARY OF WORK
01 11 00 1.1 1 WORK COVERED BY CONTRACT DOCUMENTS
01 11 00 1.2 2 OPTIONAL BID ITEM 001
01 11 00 1.3 2 ADDITIONAL REQUIREMENTS
01 11 00 1.4 3 EXISTING WORK
01 11 00 1.5 3 LOCATION OF UNDERGROUND FACILITIES
01 11 00 1.6 4 DRAWINGS
01 11 00 1.7 4 SUPERVISION
01 11 00 1.8 4 PRECONSTRUCTION CONFERENCE
01 11 00 1.9 5 INSPECTION
01 11 00 1.10 5 EXISTING CONDITIONS
01 11 00 2 8 PRODUCTS
01 11 00 3 8 EXECUTION
01 14 00 1 1 WORK RESTRICTIONS
01 14 00 1.1 1 CONTRACTOR ACCESS AND USE OF PREMISES
01 14 00 1.2 1 SECURITY REQUIREMENTS
01 14 00 2 2 PRODUCTS (Not Used) 01 14 00 3 2 EXECUTION (Not Used)
01 32 00 1 1 CONSTRUCTION SCHEDULE/
SCHEDULE OF VALUES
01 32 00 1.1 1 SUBMITTALS
01 32 00 1.2 1 CONSTRUCTION SCHEDULE
01 32 00 1.3 2 UPDATED SCHEDULES
01 32 00 2 2 PRODUCTS (Not Used)
01 32 00 3 2 EXECUTION
01 32 00 3.1 2 PROGRESS UPDATES
01 33 00 1 SUBMITTAL PROCEDURES
01 33 00 1.1 1 DEFINTIONS
01 33 00 1.2 3 SUBMITTALS
01 33 00 1.3 3 USE OF SUBMITTAL REGISTER
01 33 00 1.4 3 PROCEDURES FOR SUBMITTALS
01 33 00 1.5 5 FORMAT OF SUBMITTALS
01 33 00 1.6 7 QUANTITY OF SUBMITTALS
01 33 00 2 7 PRODUCTS (Not Used) 01 33 00 3 7 EXECUTION (Not Used)
01 35 29 1 SAFETY & OCCUPATIONAL HEALTH
REQUIREMENTS
01 35 29 1.1 1 REFERENCES
01 35 29 1.2 1 SUBMITTALS
01 35 29 1.3 2 QUALITY ASSURANCE
TABLE OF CONTENTS Page 2
01 35 29 1.4 2 ACCIDENT PREVENTION PLAN (APP)
01 35 29 2 3 PRODUCTS (Not Used)
01 35 29 3 3 EXECUTION
01 35 29 3.1 3 CONSTRUCTION
01 35 29 3.2 3 PERSONNEL PROTECTION
01 35 29 3.3 3 EXCAVATIONS
01 35 29 3.4 4 ELECTRICAL
01 35 29 3.5 4 HOUSEKEEPING
01 50 00 1 TEMPORARY FACILITIES AND CONTROLS
01 50 00 1.1 1 REFERENCES
01 50 00 1.2 1 SUBMITTALS
01 50 00 1.3 1 TRAFFIC CONTROL & CONSTRUCTION SITE
PLAN
01 50 00 1.4 2 TEMPORARY UTILITIES
01 50 00 1.5 2 WEATHER PROTECTION
01 50 00 1.6 2 STATION OPERATION EFFECTS ON
CONTRACTOR OPERATIONS
01 50 00 1.7 2 STORAGE AREAS
01 50 00 1.8 3 TEMPORARY SANITARY FACILITIES
01 50 00 1.9 3 TEMPORARY BUILDINGS & EQUIPMENT
01 50 00 2 3 PRODUCTS (Not Used)
01 50 00 3 3 EXECUTION
01 50 00 3.1 3 TEMPORARY PHYSICAL CONTROLS
01 50 00 3.2 4 TEMPORARY WIRING
01 57 19 1 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 19 1.1 1 REFERENCES
01 57 19 1.2 1 DEFINITIONS
01 57 19 1.3 2 SUBMITTALS
01 57 19 1.4 3 DIRT AND DUST CONTROL PLAN
01 57 19 1.5 3 ENVIRONMENTAL PROTECTION
REQUIREMENTS
01 57 19 1.6 3 UNFORESEEN HAZARDOUS MATERIAL
01 57 19 2 4 PRODUCTS (Not Used)
01 57 19 3 4 EXECUTION
01 57 19 3.1 4 PROTECTION OF NATURAL RESOURCES
01 57 19 3.2 5 HISTORICAL AND ARCHAEOLOGICAL
RESOURCES
01 57 19 3.3 5 CONTROL AND DISPOSAL OF SOLID WASTE
01 57 19 3.4 5 PETROLEUM PRODUCTS
01 57 19 3.5 5 RELEASES/SPILLS OF OIL AND HAZARDOUS
SUBSTANCES
01 57 19 3.6 6 DUST CONTROL
01 57 19 3.7 6 NOISE
TABLE OF CONTENTS Page 3
01 77 00 1 CLOSEOUT PROCEDURES
01 77 00 1.1 1 SUBMITTALS
01 77 00 1.2 1 PROJECT RECORD DOCUMENTS
01 77 00 1.3 1 EQUIPMENT/PRODUCT WARRANTIES
01 77 00 2 1 PRODUCTS (Not Used) 01 77 00 3 1 EXECUTION (Not Used)
26 12 19 1 1 SINGLE-PHASE PAD-MOUNTED TRANSFORMERS
(OPTIONAL BID ITEM 001)
26 12 19 1.1 1 REFERENCES
26 12 19 1.2 2 DEFINTIONS
26 12 19 1.3 2 SUBMITTALS
26 12 19 1.4 3 QUALITY ASSURANCE
26 12 19 1.5 4 WARRANTY
26 12 19 2 4 PRODUCTS
26 12 19 2.1 4 SINGLE-PHASE PAD-MOUNTED TRANSFORMERS
26 12 19 2.2 6 CORROSION PROTECTION
26 12 19 2.3 6 WARNING SIGNS
26 12 19 3 6 EXECUTION
26 12 19 3.1 6 INSTALLATION
26 12 19 3.2 6 GROUNDING
26 12 19 3.3 7 TRANSFORMER GROUNDING
26 12 19 3.4 7 INSTALLATION OF EQUIPMENT AND
ASSEMBLIES
26 12 19 3.5 7 FOUNDATION FOR EQUIPMENT AND
ASSEMBLIES
26 12 19 3.6 7 FIELD QUALITY CONTROL
31 00 00 1 1 EARTHWORK
31 00 00 1.1 1 REFERENCES
31 00 00 1.2 2 DEFINITIONS
31 00 00 1.3 3 MEASUREMENT
31 00 00 1.4 4 SUBMITTALS
31 00 00 1.5 4 CLASSIFICATION OF EXCAVATION
31 00 00 2 4 PRODUCTS
31 00 00 2.1 4 BURIED WARNING AND IDENTIFICATION TAPE
31 00 00 3 4 EXECUTION
31 00 00 3.1 4 STRIPPING OF SOIL
31 00 00 3.2 5 GENERAL EXCAVATION
31 00 00 3.3 5 BURIED TAPE AND DETECTION WIRE
31 00 00 3.4 5 BACKFILLING AND COMPACTION
31 00 00 3.5 6 PLACING TOPSOIL
TABLE OF CONTENTS Page 4
33 71 02 1 UNDERGROUND ELECTRICAL DISTRIBUTION
33 71 02 1 1 GENERAL
33 71 02 1.1 1 REFERENCES
33 71 02 1.2 3 DEFINITIONS
33 71 02 1.3 3 SUBMITTALS
33 71 02 1.4 4 QUALITY ASSURANCE
33 71 02 2 5 PRODUCTS
33 71 02 2.1 5 CONDUITS, DUCTS, AND FITTTINGS
33 71 02 2.2 6 MEDIUM VOLTAGE CABLE
33 71 02 2.3 6 MEDIUM VOLTAGE CABLE TERMINATIONS
33 71 02 2.4 7 MEDIUM VOLTAGE CABLE JOINTS
33 71 02 2.5 7 TAPE
33 71 02 2.6 7 GROUNDING AND BONDING
33 71 02 2.7 7 PRE-CAST HANDHOLES
33 71 02 2.8 8 CABLE TAGS IN HANDHOLES
33 71 02 2.9 8 SOURCE QUALITY CONTROL
33 71 02 3 8 EXECUTION
33 71 02 3.1 8 INSTALLATION
33 71 02 3.2 8 CABLE INSPECTION
33 71 02 3.3 8 CABLE INSTALLATION PLAN AND PROCEDURE
33 71 02 3.4 9 PRE-CAST HANDHOLES
33 71 02 3.5 9 DIRECT BURIAL CABLE SYSTEM
33 71 02 3.6 10 UNDERGROUND CONDUIT AND DUCT SYSTEMS
33 71 02 3.7 10 CABLE PULLING
33 71 02 3.8 10 CABLES IN HANDHOLES
33 71 02 3.9 10 MEDIUM VOLTAGE CABLE TERMINATIONS
33 71 02 3.10 10 MEDIUM VOLTAGE CABLE JOINTS
33 71 02 3.11 10 CABLE END CAPS
33 71 02 3.12 11 GROUNDING SYSTEMS
33 71 02 3.13 11 EXCAVATING, BACKFILLING, AND
COMPACTING
33 71 02 3.14 11 FIELD QUALITY CONTROL
--End Table of Contents--
PSN: 4599471
SECTION 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
a. New 15 KV Direct Burial Cable
(1) The work includes the installation of three (3) 15 KV, direct burial EPR cables with HDPE conduit approximately 5000 feet along the Robert Moses Causeway (RMC) from a Long Island Power Authority (LIPA) electrical substation to the US Coast Guard Station Fire Island and incidental related work.
(2) The operating voltage is 4160 VAC.
(3) Currently there are three (3) existing direct burial 15KV cables that are operational and feeding the US Coast Guard Station Fire Island facility. The new cables will be direct buried in a different location and away from the existing cables.
(4) The existing cables shall remain operational during the installation of the new direct burial cables. Once the rough-in of the new cables are completed, a power outage and cut-over from the old feeders to the new service cables will be granted.
(5) The Contractor shall abandon in place the existing underground cables with the exception of cutting them back below grade and away from the existing terminal cabinets.
(6) Enclosure (A) depicts the LIPA sub-station and associated feeders to the USCG and State Park Service.
(7) This is a primary metered electrical service with no other customers fed from this distribution.
(8) Contractor shall coordinate all work with the Long Island Power Authority (LIPA) prior to commencing field work and shall assume all costs associated with LIPA’s involvement in the project.
Prior to ordering of materials, a joint site visit between the General Contractor, Electrical Contractor, cable splicer and a LIPA representative to field verify all existing conditions to include identifying any specific requirements of the Long Island Power Authority.
b. Roadwork
(1) Contractor shall provide a qualified English speaking roadway foreman and safety observer who is on site during all phases of the roadwork. No roadwork shall take place without this person located at the site of the roadwork and excavation. This person shall wear a bright colored safety vest with the following identification:
SECTION 01 11 00 Page 2
Roadwork Foreman Safety Officer
(2) This Roadwork Foreman/Safety Officer shall not be engaged in any construction work, but fully focused on the workers and public safety in relation to assuring that the construction site is clearly marked, personnel and equipment remain within the marked construction site and that normal traffic flow is uninterrupted.
(3) All workers shall wear reflective safety vests and hardhats.
(4) Refer to Specification Section 01 50 00 TEMPORARY FACILITIES AND
CONTROLS.
1.2 OPTIONAL BID ITEM 001
a. Replace three (3) Distribution Transformers for CG Housing
(1) Contractor shall replace three, pad mounted, dry-type distribution transformers providing electrical service to several US Coast Guard housing units.
(2) Each transformer is 167 KVA, 2400V-120/240V, single-phase, anchored to an existing concrete foundation.
(3) Refer to Specification Section 26 12 19 (SINGLE-PHASE PAD MOUNTED
TRANSFORMERS).
1.3 ADDITIONAL REQUIREMENTS
1.3.1 Mandatory Site Visit
a. Upon Notice to Proceed, the Contractor, their sub-Contractors, and representative from LIPA (coordinated by the Contractor) shall make a mandatory site visit to fully inspect the existing conditions which shall include accessing load break cabinet, housing transformers, and LIPA substation equipment. At this time field verify all requirements of the new installation to include materials.
b. Upon completion of the mandatory site visit, the Contractor shall submit a letter to the Contracting Office indicating that the site visit was completed, all existing conditions and equipment was field verified, and indentify all attendees at this visit to include full name, company they work for and their occupation.
1.3.1.1 Optional Bid Item 001
a. During the mandatory site visit, the Contractor shall field verify voltages and configurations i.e. delta vs. wye. Contractor shall obtain the complete nameplate data off each transformer. Measure each transformer pad and location of conduits to assure the new transformers will align with the existing conditions.
b. Contractor shall fully inspect the existing feeders between the CG owned load break cabinet and each transformer as well as between each transformer and the housing load centers. Contractor will not be
SECTION 01 11 00 Page 3 authorized a commercial power outage for this site visit and shall wear the appropriate Personal Protective Equipment (PPE) for the inspection.
1.3.1.2 Discrepancies
a. If any deficiencies and/or discrepancies are noted during this site visit, the Contractor shall notify the Contracting Officer in writing as to the discrepancy or conflict and request direction from the Contracting Officer as to what action should be taken.
1.3.2 Temporary Power
a. Contractor shall provide a standby generator to power thirteen (13) housing units during any commercial power loss in excess of two hours.
b. Contractor shall be responsible for all fuel, maintenance, and repairs associated with the use of standby generators as well as providing and making up any cords and terminations to connect the housing unit(s).
c. Contractor shall submit a temporary power plan detailing the proposed power outage schedule to include a written narrative detailing how the housing unit(s) will be connected to the temporary power source.
Contractor shall be responsible for sizing the generator based on their temporary power plan.
d. Contractor shall assure that commercial power is restored by close of business each day.
1.3.3 Location
The work shall be located between US Coast Guard Station Fire Island, 1 Rescue Road, Babylon, NY and the LIPA Substation along the Robert Moses Causeway. The exact location will be shown by the Contracting Officer.
1.4 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.5 LOCATION OF UNDERGROUND FACILITIES
Obtain digging permits prior to start of excavation. Scan the construction site with electromagnetic or sonic equipment, and mark the surface of the ground where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated or specified to be removed but indicated or discovered during scanning in locations to be traversed by the new cables to be installed. Verify elevations before installing new work closer than
SECTION 01 11 00 Page 4 nearest manhole or other structure at which an adjustment in grade can be made.
1.5.1 Notification Prior to Excavation
Notify the Contracting Officer at least 48 hours prior to starting excavation work. For this location, contact the local utility or Dig Safe 48 hours prior to excavating. Contractor is responsible for marking all utilities not marked by the utility or Dig Safe. Be aware there may be other cables and/or utilities buried in this area.
1.6 DRAWINGS
1.6.1 Drawing Number P4599471
This drawing depicts work to be performed along the Robert Moses Causeway to the USCG Station Fire Island.
1.6.2 Reference Drawings
Drawings stamped “Reference Drawing” are for reference purposes only and not intended to show work to be performed.
1.6.2.1 REFERENCE Drawing Number: 03-4452 (Sheet 3 of 4)
This drawing depicts the Site Plan for the CG Housing electrical distribution system to include the 167 KVA transformers to be replaced under Optional Bid Item 001.
1.6.2.2 REFERENCE Drawing Number: 03-4452 (Sheet 3A of 4)
This drawing depicts the Site Plan for the existing area electrical distribution system. Contractor shall take note of the utility owned cables in the area. This drawing may be helpful to Dig-Safe in marking underground utilities.
1.7 SUPERVISION
Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, if a Quality Control (QC) representative is required on the contract, then that individual shall also have fluent English communication skills.
1.8 PRECONSTRUCTION CONFERENCE
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule prices, shop drawings, and other submittals, scheduling programming, and prosecution of the work. Major subcontractors who will engage in the work shall also attend.
SECTION 01 11 00 Page 5
1.9 INSPECTION
The Contractor shall keep the Contracting Officer or duly appointed representative fully informed of contract operations and plans so that a representative may arrange to be present at various times that work is being performed.
1.9.1 Contractor’s Daily Log
The Contractor shall be complete the USCG Daily Log form at the end of each working day and deliver it to the Government Inspector. The Government Inspector will attest to its accuracy by initialing the form and forwarding that form to CEU Providence. The form will be provided to the Contractor by the Contracting Officer’s Representative.
1.10 EXISTING CONDITIONS
1.10.1 Load Break Cabinet
The load bank cabinet is located on the CG property and within a fenced area as shown in photo below. The new direct burial cables will terminate to this cabinet. Also included in this load break cabinet are the feeders to each housing distribution transformer.
US COAST GUARD STATION FIRE ISLAND
LOAD BREAK/INTERRUPTING SWITCH ENCLOSURE WITHIN FENCED AREA
SECTION 01 11 00 Page 6
1.10.2 Long Island Power Authority (LIPA) Substation
LIPA has a substation off an access road along the Robert Moses Causeway.
The Contractor shall coordinate with LIPA in regards to how to best enter their equipment with the new cables.
ENTRANCE TO LIPA SUBSTATION
ACCESS ROAD OFF ROBERT MOSES CAUSEWAY
LIPA SWITCH CABINET FOR US COAST GUARD
LIPA SUBSTATION
SECTION 01 11 00 Page 7
1.10.3 Robert Moses Causeway (RMC)
Contractor shall install new direct burial cable just off the RMC in the relatively flat grassy area off the asphalt.
VIEW OF FUTURE CABLE RUN ALONG THE ROBERT MOSES CAUSEWAY
LOOKING TOWARDS THE US COAST GUARD STATION
1.10.4 US Coast Guard Housing
The Contractor shall replace three (3) 167KVA pad mounted, dry type distribution transformers located behind the CG Housing.
VIEW OF CG HOUSING (BACKYARDS) & TYPICAL 167.5 KVA HOUSING TRANSFORMERS TO BE
REPLACED
SECTION 01 11 00 Page 8
PART 2 PRODUCTS
All materials shall be UL Listed for the use of the equipment.
PART 3 EXECUTION
3.1 Contractor shall rough-in new direct burial cable prior to de-energizing the electrical service. Upon de-energizing to make the final cut-over to the new cable, the Contractor shall have 8 working hours to complete. Contractor shall not depart from the job until the Station property is fully operational on commercial power.
3.2 OPTIONAL BID ITEM 001
Contractor shall replace one housing transformer at a time. Contractor shall isolate one transformer at a time from the existing load bank cabinet. The Contractor shall have one 8 hour workday to complete a transformer replacement. By the close of business each day, the Contractor shall assure all commercial power has been restored prior to departing from the site.
--End of Section--
SECTION 01 14 00 Page 1
SECTION 01 14 00
WORK RESTRICTIONS
1.1 CONTRACTOR ACCESS AND USE OF PREMISES
1.1.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Do not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification.
1.1.2 Roadwork
Contractor shall not block or hinder local traffic.
1.1.3 Working Hours
Regular working hours shall consist of an 8 1/2 hour period established by the Contracting Officer Monday through Friday, excluding Government holidays.
1.1.4 Occupied and Existing Buildings
The Contractor shall be working around existing buildings and houses which are occupied. Do not enter any buildings or housing units without a USCG escort.
1.1.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours."
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
1.2 SECURITY REQUIREMENTS
1.2.1 Areas Not Covered by Contract
The Contractor will not be permitted to enter buildings or areas not covered by the work included in this contract, except by prior approval of the Contracting Officer, Commanding Officer, or Officer-in-Charge of the facility.
SECTION 01 14 00 Page 2
1.2.2 Parking
Parking is prohibited on any piers and waterfront areas. Contractor shall be assigned a parking area for Contractor’s and their sub-Contractors. This shall be shown during the Pre-Construction Meeting on site. Do not park on or block the marked fire lanes at any time.
Not used.
SECTION 01 32 00 Page 1
SECTION 01 32 00
CONSTRUCTION SCHEDULE/SCHEDULE OF VALUES
1.1 SUBMITTALS
Submit the following in accordance with Section 01 33 00, "Submittal Procedures."
SD-01 Preconstruction Submittals
Construction Schedule
Schedule of Values
1.2 CONSTRUCTION SCHEDULE
At the Pre-Construction Conference, submit a Construction Schedule and Schedule of Values in accordance with FAR Clause 52.236.15. The Schedule of Values shall be based on the actual breakdown of the bid price. The cost of insurance shall not be listed as a separate item but included as part of each item of work. The actual cost of bonds may be paid as the first progress payment when a receipt from the bonding company is presented to the Contracting Officer. For contracts under $25,000, a Schedule of Values is not required. In addition, keep the Government Inspector informed daily of the expected delivery dates for major pieces of equipment and materials.
The Construction Schedule shall clearly indicate the start and completion dates of major work components. The Schedule of Values shall clearly indicate unit value of all major work components.
The Construction Schedule shall incorporate at a minimum the following activities:
a. Mobilization
b. Demobilization
c. Pre-Construction Submittals
d. Work Activities
e. In-Progress Submittals
f. Final Government Inspection
g. Close-Out Submittals; i.e. Warranties, Operation and Maintenance Manuals, Posted Instructions
h. As-Built Drawings
i. Factors which Constitute Potential Interruptions to Station Operations
SECTION 01 32 00 Page 2
Pre-Construction Submittals are those activities which encompass the obtaining, submission, review and approval of submittals necessary prior to the start of the related site work. Contractor shall annotate all such activities into the progress schedule with their forecasted time periods.
These activity periods shall not be exclusive of the contract performance period. No site work shall commence until the respective submittals have been approved.
The value of all major work components within the project shall be identified on the Schedule of Values on a unit quantity and unit cost basis, e.g. number of squares and cost per square of roofing, number of lineal feet and cost per lineal foot of conduit, number of panels and cost per panel etc. Lump sum items shall only be paid for when 100% complete. Do not include mobilization and demobilization line items on the Schedule of Values.
The Construction Schedule and Schedule of Values as approved by the Government is not a substitute for quantities conveyed by the specification and drawings and those required for a complete job. Omissions and errors on the Construction Schedule and Schedule of Values are the responsibility of the Contractor.
Payments will not be made until the schedule of prices has been submitted to and approved by the Contracting Officer.
1.3 UPDATED SCHEDULES
Update the construction schedule and equipment delivery schedule at monthly intervals or when schedule has been revised. Reflect any changes occurring since the last update. Submit copies of the purchase orders and confirmation of the delivery dates as directed.
3.1 PROGRESS UPDATES
3.1.1 General
A revised Construction Schedule/Schedule of Values shall be issued by the Contractor on a monthly basis. In addition, any revisions to the Construction Schedule/Schedule of Values such as modifications or delays shall be reflected by Contractor submission of an updated Construction Schedule/Schedule of Values.
3.1.2 Modifications
When a modification is issued by the Government, record the modification as the last activity of the Construction Schedule and Schedule of Values and include the value of the modification. Adjust the Schedule of Values to reflect the inclusion of the modification. Revise the Construction Schedule portion of the form to annotate the progress change. Enter all modifications in this manner in sequential order.
PSN: 4599741
SECTION 01 33 00 Page 1
SECTION 01 33 00
SUBMITTAL PROCEDURES
1.1 DEFINITIONS
1.1.1 Submittal
Shop drawings, product data, samples, and administrative submittals presented for review and approval. Contract Clauses "FAR 52.236-5, Material and Workmanship," paragraph (b) and "FAR 52.236-21, Specifications and Drawings for Construction," paragraphs (d), (e), and (f) apply to all "submittals."
1.1.2 Types of Submittals
All submittals are classified as indicated in paragraph "Submittal Descriptions (SD)". Submittals also are grouped as follows:
a. Shop drawings: As used in this section, drawings, schedules, diagrams, and other data prepared specifically for this contract, by contractor or through contractor by way of subcontractor, manufacturer, supplier, distributor, or other lower tier contractor, to illustrate portion of work.
b. Product data: Preprinted material such as illustrations, standard schedules, performance charts, instructions, brochures, diagrams, manufacturer's descriptive literature, catalog data, and other data to illustrate portion of work, but not prepared exclusively for this contract.
c. Administrative submittals: Data presented for reviews and approval to ensure that administrative requirements of project are adequately met but not to ensure directly that work is in accordance with design concept and in compliance with contract documents.
1.1.3 Submittal Descriptions (SD)
Submittal register Schedule of values Accident Prevention Plan Traffic Control & Construction Site Plan Dust and Dirt Control Plan Severe Weather Plan Quality control plan
SECTION 01 33 00 Page 2
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the contractor for integrating the product or system into the project.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials or equipment for some portion of the work.
SD-05 Design Data
Calculations, mix designs, analyses or other data pertaining to a part of work.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)
Final acceptance test and operational test procedure
SD-07 Certificates
Statements signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
SD-08 Manufacturer's Instructions
Preprinted material describing installation of a product, system or material, including special notices and Material Safety Data sheets concerning impedances, hazards and safety precautions.
SD-10 Operation and Maintenance Data
Data intended to be incorporated in operations and maintenance manuals.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
As-built drawings
Special warranties
SECTION 01 33 00 Page 3
1.1.4 Approving Authority
Contracting Officer
1.1.5 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce construction and materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.2 SUBMITTALS
Submit the following in accordance with the requirements of this section.
Submittal register
1.3 USE OF SUBMITTAL REGISTER
Prepare and maintain submittal register, as the work progresses. Do not change data in columns (a), (b), (c), and (d) as delivered by government.
1.3.1 Submittal Register
Submit submittal register. Verify that all submittals required for project are listed and add missing submittals. Complete the following on the register:
Column (e) Contractor Submit Date: Scheduled date for approving authority to receive submittals.
1.4 PROCEDURES FOR SUBMITTALS
1.4.1 Reviewing, Certifying, Approving Authority
Government organization shall be responsible for reviewing and certifying that submittals are in compliance with contract requirements. Approving authority on submittals is the Project Manager unless otherwise specified for specific submittal.
1.4.2 Constraints
a. Submittals listed or specified in this contract shall conform to provisions of this section, unless explicitly stated otherwise.
b. Submittals shall be complete for each definable feature of work;
components of definable feature interrelated as a system shall be submitted at same time.
c. When acceptability of a submittal is dependent on conditions, items, or materials included in separate subsequent submittals, submittal will be returned without review.
SECTION 01 33 00 Page 4
d. Approval of a separate material, product, or component does not imply approval of assembly in which item functions.
1.4.3 Scheduling
a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential requirements to resubmit.
b. Except as specified otherwise, allow review period, beginning with receipt by approving authority, that includes at least 10 working days. Period of review for each re-submittal is the same as for initial submittal.
1.4.4 Variations
Variations from contract requirements require Government approval pursuant to contract Clause entitled "FAR 52.236-21, Specifications and Drawings for Construction" and will be considered where advantageous to government.
1.4.4.1 Proposing Variations
When proposing variation, deliver written request to the contracting officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to government. If lower cost is a benefit, also include an estimate of the cost saving. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.
1.4.4.2 Review Schedule Is Modified
In addition to normal submittal review period, a period of 5 working days will be allowed for consideration by the Government of submittals with variations.
1.4.5 Contractor's Responsibilities
a. Determine and verify field measurements, materials, field construction criteria; review each submittal; and check and coordinate each submittal with requirements of the work and contract documents.
b. Transmit submittals to Contracting Officer in accordance with schedule on approved Submittal Register, and to prevent delays in the work, delays to government, or delays to separate contractors.
c. Advise contracting officer of variation, as required by paragraph entitled "Variations."
d. Correct and resubmit submittal as directed by approving authority.
When resubmitting disapproved transmittals or transmittals noted for resubmittal, the contractor shall provide copy of that previously submitted transmittal including all reviewer comments for use by approving authority. Direct specific attention in writing or on resubmitted submittal, to revisions not requested by approving authority on previous submissions.
SECTION 01 33 00 Page 5
e. Furnish additional copies of submittal when requested by contracting officer, to a limit of 10 copies per submittal.
f. Complete work which must be accomplished as basis of a submittal in time to allow submittal to occur as scheduled.
g. Ensure no work has begun until submittals for that work have been returned as "approved," except to the extent that a portion of work must be accomplished as basis of submittal.
1.4.6 Government Responsibilities
a. Note date on which submittal was received from contractor on each Contract Item Approval Request Form.
b. Review each submittal; and check and coordinate each submittal with requirements of work and contract documents.
c. Review submittals for conformance with project design concepts and compliance with contract documents.
d. Ensure that material is clearly legible.
e. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
f. Identify returned submittals with one of the actions defined in paragraph entitled "Actions Possible" and with markings appropriate for action indicated.
1.4.7 Actions Possible
Submittals will be returned with one of the following notations:
a. Submittals marked "approved" "approved as submitted" authorize contractor to proceed with work covered.
b. Submittals marked "approved" "see below" authorize contractor to proceed with work as noted provided contractor takes no exception to the notations.
c. Submittals marked "disapproved" indicate submittal is incomplete or does not comply with design concept or requirements of the contract documents and shall be resubmitted with appropriate changes. No work shall proceed for this item until re-submittal is approved.
1.5 FORMAT OF SUBMITTALS
1.5.1 Transmittal Form
Transmit each submittal electronically, unless otherwise noted in the submittal register and/or where electronic submission is not feasible (i.e.
samples), to office of approving authority. The maximum file size that may be emailed is 10 MB; anything larger must be submitted hard copy or on a CD.
Transmit submittals with transmittal form prescribed by contracting officer
SECTION 01 33 00 Page 6 and standard for project. The transmittal form shall identify contractor, indicate date of submittal, and include information prescribed by transmittal form and required in paragraph entitled "Identifying Submittals." Process transmittal forms to record actions regarding sample panels and sample installations. Note: Submittals requiring hard copy submission shall be provided with carbon copy transmittal form provided by the government.
1.5.2 Identifying Submittals
Identify submittals, except sample panel and sample installation, with the following information on each separate component of each submittal and transmittal form. The maximum file size for electronic submittals shall be no larger than 10 MB. Identify each copy of each submittal identically, with the following:
a. Project title and location.
b. Construction contract number.
c. Section number of the specification section by which submittal is required.
d. Submittal description (SD) number of each component of submittal.
e. When a resubmission, alphabetic suffix on submittal description, for example, SD-10A, to indicate resubmission.
f. Name, address, and telephone number of subcontractor, supplier, manufacturer and any other second tier contractor associated with submittal.
g. Product identification and location in project.
1.5.3 Format for Product Data
a. Present product data submittals for each section. Include table of contents, listing page and catalog item numbers for product data.
b. Indicate, by prominent notation, each product which is being submitted; indicate specification section number and paragraph number to which it pertains.
c. Supplement product data with material prepared for project to satisfy submittal requirements for which product data does not exist. Identify this material as developed specifically for project.
1.5.4 Format for Shop Drawings
a. Shop drawings shall not be less than 8 1/2 by 11 inches nor more than 30 by 42 inches.
b. Present 8 1/2 by 11 inches sized shop drawings as part of the submittals required by section. Present larger drawings in sets.
SECTION 01 33 00 Page 7
c. Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to information required in paragraph entitled "Identifying Submittals."
d. Dimension drawings, except diagrams and schematic drawings; prepare drawings demonstrating interface with other trades to scale. Shop drawing dimensions shall be the same unit of measure as indicated on the contract drawings. Identify materials and products for work shown.
1.5.5 Format of Administrative Submittals
a. When submittal includes a document which is to be used in project or become part of project record, other than as a submittal, do not apply contractor's approval stamp to document, but to a separate sheet accompanying document.
1.6 QUANTITY OF SUBMITTALS
1.6.1 Number of Copies of Product Data
a. When hard copy submission is required, submit four copies of submittals of product data.
1.6.2 Number of Copies of Shop Drawings
Submit shop drawings in compliance with quantity requirements specified for product data.
1.6.3 Number of Copies of Administrative Submittals
a. Unless otherwise specified, submit administrative submittals compliance with quantity requirements specified for product data.
SECTION 01 35 29 Page 1
SECTION 01 35 29
SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS
1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
ANSI A10.32 (2004) Personal Fall Protection - Safety
Requirements for Construction and Demolition Operations
ANSI A10.34 (2005) Protection of the Public on or
Adjacent to Construction Sites
CODE OF FEDERAL REGULATIONS (CFR)
29 CFR 1910 Occupational Safety and Health Standards
29 CFR 1919 Gear Certification
29 CFR 1926 Safety and Health Regulations for
Construction
29 CFR 1926.500 Fall Protection
CORPS OF ENGINEERS (COE)
EM 385-1-1 (2003) Safety -- Safety and Health
Requirements
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 241 (2004) Safeguarding Construction, Alteration, and Demolition Operations
NFPA 70 (2011) National Electrical Code
NFPA 70E (2012) Electrical Safety in the Workplace
1.2 SUBMITTALS
Accident Prevention Plan (APP)
SECTION 01 35 29 Page 2
1.3 QUALITY ASSURANCE
1.3.1 Meetings
The Safety Officer shall attend the pre-construction conference.
1.3.1.1 Daily Safety Meetings
Hold daily at the project site. Attach minutes showing contract title, signatures of attendees and a list of topics discussed to the QC Contractor Quality Control daily report.
1.3.1.2 New Employee Indoctrination
New employees will be informed of specific site hazards before they begin work. Documentation of this orientation shall be kept on file at the project site.
1.3.2 Certifications
1.3.2.1 Accident Prevention Plan (APP)
Submit the APP at least 15 calendar days prior to start of work at the job site, following Appendix A of EM-385-1-1. Make the APP site specific.
1.4 ACCIDENT PREVENTION PLAN (APP)
Prepare the APP in accordance with EM-385-1-1 Table 1-1.
1.4.1 Contents of the Accident Prevention Plan
a. Name and safety related qualifications of safety officer (including training and any certifications).
b. Qualifications of competent and of qualified persons.
c. Identity of the individual who will complete exposure data (hours worked); accident investigations, reports and logs; and immediate notification of accidents to include subcontractors.
d. Emergency response plan. Conform to EM-385-1-1, paragraph 01.E and include a map denoting the route to the nearest emergency care facility with emergency phone numbers. Contractor may be required to demonstrate emergency response.
e. Training Records and Requirements. List of mandatory training and certifications which are applicable to this project (e.g. explosive actuated tools, confined space entry, fall protection, crane operation, vehicle operator, forklift operators, personal protective equipment); list of requirements for periodic retraining/certification; outline requirements for supervisory and employee safety meetings.
f. Severe Weather Plan. Procedures of ceasing on-site operations during lightning or upon reaching maximum allowed wind velocities.
SECTION 01 35 29 Page 3
2 PRODUCTS
Not Used.
3 EXECUTION
3.1 CONSTRUCTION
Comply with EM-385-1-1, NFPA 241, the accident prevention plan, the activity hazard analysis and other related submittals and activity fire and safety regulations.
3.1.1 Unforeseen Hazardous Material
If material, not indicated, that may be hazardous to human health upon disturbance during construction operations is encountered, stop that portion of work and notify the Contracting Officer immediately. Within 14 calendar days the Government will determine if the material is hazardous. If material is not hazardous or poses no danger, the Government will direct the Contractor to proceed without change. If material is hazardous and handling of the material is necessary to accomplish the work, the Government will issue a modification pursuant to "FAR 52.243-4, Changes" and "FAR 52.236-2, Differing Site Conditions."
3.2 PERSONNEL PROTECTION
3.2.1 Hazardous Noise
Provide hazardous noise signs, and hearing protection, wherever equipment and work procedures produce sound-pressure levels greater than 85 dBA steady state or 140 dBA impulse, regardless of the duration of the exposure.
3.2.2 Fall Protection
Personal fall arrest systems are required when working from an articulating or extendible boom, scissor lifts, swing stages, or suspended platform.
Fall protection must comply with ANSI A10.32.
3.3 EXCAVATIONS
The competent person for excavation performed as a result of contract work shall be on-site when work is being performed in excavation, and shall inspect excavations prior to entry by workers. The competent person must evaluate for all hazards, including atmospheric, that may be associated with the work, and shall have the resources necessary to correct hazards promptly. Prior to digging the appropriate digging permit must be obtained.
All underground utilities in the work area must be positively identified by a utility locating service and coordinated with the Long Island Power Authority (LIPA). The Contractor must physically verify underground utility locations by hand digging using wood or fiberglass handled tools when any adjacent construction work is expected to come within three feet of the underground system. If construction is parallel to an existing utility the utility shall be exposed by hand digging every 100 feet if parallel within 5 feet of the excavation. Trench and shoring systems must be identified in the accepted safety plan. Extreme care must be used when excavating near direct burial electric underground cables. Trenching machines with digging chain
SECTION 01 35 29 Page 4 drives shall be operated only when the spotters/laborers are in plain view of the operator. Operator and spotters/laborers shall be provided training on the hazards of the digging chain drives with emphasis on the distance that needs to be maintained when the digging chain is operating.
Documentation of the training shall be kept on file in the project site office or trailer.
3.4 ELECTRICAL
3.4.1 Conduct of Electrical Work
Cable intended to be cut must be positively identified and de-energized prior to performing each cut. Positive cable identification must be made prior to submitting any outage request for electrical systems. Arrangements are to be coordinated with LIPA for identification. The Contracting Officer will not accept an outage request until the Contractor satisfactorily documents that the circuits have been clearly identified. Perform all high voltage cutting remotely. When racking in or live switching of circuit breakers, no additional person other than the switch operator will be allowed in the space during the actual operation. Plan so that work near energized parts is minimized to the fullest extent possible. Use of electrical outages clear of any energized electrical sources is the preferred method. When working in energized substations, only qualified electrical workers shall be permitted to enter. When work requires Contractor to work near energized circuits as defined by the NFPA 70, high voltage personnel must use personal protective equipment that includes, as a minimum, electrical hard hat, safety shoes, insulating gloves with leather protective sleeves, fire retarding shirts, coveralls, face shields, and safety glasses. Insulating blankets, hearing protection, and switching suits may be required, depending on the specific job and as delineated in the Contractor APP.
3.4.2 Portable Extension Cords
Portable extension cords shall be sized in accordance with manufacturer ratings for the tool to be powered.
3.5 HOUSEKEEPING
3.5.1 Clean-up
All debris in work areas shall be cleaned up daily or more frequently as necessary. Construction debris may be temporarily located in an approved location; however garbage accumulation must be removed each day.
3.8.2 Dust Control
In addition to the dust control measures required elsewhere in the contract documents dry cutting of brick or masonry shall be prohibited. Wet cutting must address control of water run off.
SECTION 01 50 00 Page 1
SECTION 01 50 00
TEMPORARY FACILITIES AND CONTROLS
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the
FEDERAL HIGHWAY ADMINISTRATION (FHWA)
FHWA MUTCD (1988) Manual on Uniform Traffic Control
Devices
NFPA 241 (1996) Safeguarding Construction, Alteration, and Demolition Operations
1.2 SUBMITTALS
Traffic control plan
Construction site plan
1.3 TRAFFIC CONTROL & CONSTRUCTION SITE PLAN
During the pre-construction meeting, submit and discuss a Contractor generated site plan showing the locations of equipment and temporary facilities (including layouts and details, equipment and material storage area (onsite). Show locations of safety and construction fences, site trailers, construction boundaries and markings, temporary sanitary facilities, and worker parking areas.
During the pre-construction meeting the Contractor shall discuss with the US Coast Guard’s Construction Project Manager and Contracting Officer the plan to control traffic and protect workers and the public from the Construction Activities. The Contractor shall have the assigned Roadwork Foreman & Safety Officer present at the pre-construction meeting.
Refer to Section 01 11 00 Part 1.1.1.b (Roadwork) for requirements on Roadwork Foreman requirements.
SECTION 01 50 00 Page 2
1.4 TEMPORARY UTILITIES
1.4.1 Contractor Utilities
The Contractor shall provide his own utilities.
1.5 WEATHER PROTECTION
Take necessary precautions and ensure that immediate action is taken to seal off ground and equipment openings when rain or other detrimental weather is imminent, and at the end of each workday. Ensure that excavated areas are backfilled and compacted to protect the underground materials as well as prevent injury to the public.
1.5.1 Site Storm Protection
When a warning of gale force winds is issued, take precautions to minimize danger to persons, and protect the work and nearby Government property.
Precautions shall include, but are not limited to, closing openings;
removing loose materials, tools and equipment from exposed locations and other temporary work. Close openings in the work when storms of lesser intensity pose a threat to the work or any nearby Government property.
Completely fill any earth that has been excavated prior to leaving the site as to prevent public injury.
1.6 STATION OPERATION EFFECTS ON CONTRACTOR OPERATIONS
1.6.1 Interruption of Vehicular Traffic
If during the performance of work, it becomes necessary to modify vehicular traffic patterns at any locations and provide a Traffic Control Plan detailing the proposed controls to traffic movement for approval by NY DOT.
The plan shall be in accordance with State and local regulations and the FHWA MUTCD, Part VI. Make all notifications and obtain any permits required for modification to traffic movements outside Station's jurisdiction.
Provide cones, signs, barricades, lights, or other traffic control devices and personnel required to control traffic in accordance with NY DOT.
1.7 STORAGE AREAS
Contractor shall be responsible for security of his property. The Contract Clause entitled "FAR 52.236-10, Operations and Storage Areas" and the following apply:
1.7.1 Storage Size and Location
The open site available on base for storage shall be within 1,000 feet of the front gate to the base and determined at the Pre-Construction meeting on site.
1.7.2 Storage in Existing Buildings
The Contractor shall be working around existing buildings; the storage of material will not be allowed in the buildings.
SECTION 01 50 00 Page 3
1.8 TEMPORARY SANITARY FACILITIES
Provide temporary sewer and sanitation facilities that are self-contained units with both urinals and stool capabilities. Ventilate the units to control odors and fumes and empty and clean them at least once a week or more often if required by the Contracting Officer. The doors shall be self-closing. Locate the facility out of the public view.
1.9 TEMPORARY BUILDINGS & EQUIPMENT
Temporary facilities (including trailers) shall be in like new condition and located on Government property. Contractor shall locate these facilities on base as indicated during the Pre-Construction meeting. Contractor shall be responsible for the security of the stored property.
Upon completion of work each day the Contractor shall place all Contractor and Sub-Contractor property such as materials, equipment and tools on US Coast Guard property. Do not leave any equipment materials, equipment or tools on public property at the end of each workday.
1.9.1 Maintenance of Temporary Facilities
Suitably paint and maintain the temporary facilities. Failure to do so will be sufficient reason to require their removal.
1.9.2 Trailers or Storage Buildings
Trailers or storage buildings will be permitted, where space is available, subject to the approval of the Contracting Officer. The trailers or buildings shall be in good condition, free from visible damage rust and deterioration, and meet all applicable safety requirements. Trailers shall be roadworthy and comply with all appropriate state and local vehicle requirements. Failure to maintain storage trailers or buildings to these standards shall result in the removal of non-complying units at the Contractor's expense. A sign not smaller than 24 by 24 inches shall be conspicuously placed on the trailer depicting the company name, business phone number, and emergency phone number. Trailers shall be anchored to resist high winds and must meet applicable state of local standards for anchoring mobile trailers.
Not Used.
3.1 TEMPORARY PHYSICAL CONTROLS
3.1.1 Access Controls
3.1.1.1 Temporary Barricades
Contractor shall provide for barricading around all work areas to prevent public access.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .