Attachment 5 CGC AXE(WLIC 75310) USCG 68B BARGE (68020) SPECIFICATION
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| CGC_AXE_Attachment_1_-_SCHEDULE_OF_SUPPLIES__AMENDMENT_3.docx | DOCX document | |
| CGC_AXE_AMENDMENT_3_OF_SOLICITATION.docx | DOCX document | |
| CGC_AXE_Attachment_1_-_SCHEDULE_OF_SUPPLIES__AMENDMENT_2.docx | DOCX document | |
| CGC_AXE_AMENDMENT_2_OF_SOLICITATION.docx | DOCX document | |
| CGC_AXE_Attachment_1_-_SCHEDULE_OF_SUPPLIES__AMENDMENT_1.docx | DOCX document | |
| CGC_AXE_-_CG_68B_BARGE_SPEC_REV-1_18_FEB_2016.pdf | ||
| CGC_AXE_AMENDMENT_1_OF_SOLICITATION.docx | DOCX document | |
| CGC_AXE_Attachment_1_-_SCHEDULE_OF_SUPPLIES.docx | DOCX document | |
| CGC_AXE_FY-16_DD_-_SOLICITATION.docx | DOCX document | |
| CGC_AXE_Attachment_2_-_GOVERNMENT_PROPERTY_REPORT.docx | DOCX document | |
| CGC_AXE_Attachement_4_-_PAST_PERFORMANCE_INFORMATION_FORM.docx | DOCX document | |
| CGC_AXE_Attachement_3_-_Request_for_Clarification.docx | DOCX document |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC AXE (WLIC 75310)
USCG 68B BARGE (68020)
SPECIFICATION FOR DRYDOCK REPAIRS
FY2016
Developed By:
LCDR Amy M. Lockwood
(Rev-0, 04 December 2015)
USCGC AXE (WLIC-75D) DRYDOCK AVAILABILITY FY2016
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record .......................................................................................................................................... iv Consolidated List of References .................................................................................................................... v Consolidated List of Government-furnished Property .................................................................................. x Consolidated List of Critical Inspection Items ............................................................................................. xi Principal Characteristics - Tender .............................................................................................................. xii Principal Characteristics - Barge ............................................................................................................... xiii General Requirements WORK ITEM 1: Hull Plating (U/W Body), Inspect- Tender WORK ITEM 2: Hull Plating (U/W Body), Inspect - Barge WORK ITEM 3: Hull Plating (U/W Body), Ultrasonic Testing - Tender WORK ITEM 4: Hull Plating (U/W Body), Ultrasonic Testing - Barge WORK ITEM 5: Hull and Structural Plating (General) -10.2-Pound Steel, Repair - Tender WORK ITEM 6: Hull and Structural Plating (General) -10.2-Pound Steel, Repair - Barge WORK ITEM 7: Hull and Structural Plating (General) - 12.75-Pound Steel Plate, Repair - Tender WORK ITEM 8: Hull and Structural Plating (General) - 12.75-Pound Steel Plate, Repair - Barge WORK ITEM 9: Hull and Structural Plating (General) - 15.3-Pound Steel Plate, Repair - Tender WORK ITEM 10: Hull and Structural Plating (General) - 15.3-Pound Steel Plate, Repair - Barge WORK ITEM 11: Hull and Structural Plating (General) - 20.5-Pound Steel Plate, Repair - Tender WORK ITEM 12: Hull and Structural Plating (General) - 20.5-Pound Steel Plate, Repair - Barge WORK ITEM 13: Hull and Structural Plating (General) - 7.5-Pound (3/16") Steel Plate, Repair - Tender39 WORK ITEM 14: Hull and Structural Plating (General) - 7.5-Pound (3/16") Steel Plate, Repair - Barge 41 WORK ITEM 15: Hull and Structural Plating (General) – 7.65-Pound Steel Plate, Repair - Tender WORK ITEM 16: Hull and Structural Plating (General) – 7.65-Pound Steel Plate, Repair - Barge WORK ITEM 17: Hull and Structural Plating (General) - Cracked Steel Welds, Repairs - Tender WORK ITEM 18: Hull and Structural Plating (General) - Cracked Steel Welds, Repairs - Barge WORK ITEM 19: Propulsion Shaft Rope Guards, Inspect and Repair WORK ITEM 20: Tanks (MP Fuel Stowage and Overflow), Clean and Inspect - Tender WORK ITEM 21: Voids (Non-Accessible), Leak Test - Tender WORK ITEM 22: Voids (Non-Accessible), Leak Test WORK ITEM 23: Voids (Non-Accessible), Internal Surfaces, Preserve WORK ITEM 24: Voids (Non-Accessible), Internal Surfaces, Preserve WORK ITEM 25: Propulsion Shafting, Remove, Inspect, and Reinstall WORK ITEM 26: Propulsion Shafting, Optical Or Laser Alignment Check WORK ITEM 27: Propulsion Shaft Seals, Mechanical & Inflatable, Overhaul and Renew WORK ITEM 28: Propulsion Shaft Bearings (External), Check Clearances WORK ITEM 29: Propellers, Remove, Inspect, and Reinstall WORK ITEM 30: Keel Coolers, Clean, Inspect and Hydro WORK ITEM 31: Fathometer Transducer, Renew – Tender WORK ITEM 32: Fathometer Transducer, Renew – Barge WORK ITEM 33: Vent Ducts (Galley and Pantry Room All), Commercial Cleaning WORK ITEM 34: Rudder Assembly; Remove, Inspect and Reinstall WORK ITEM 35: Rudder Stock Bearings Clearances, Check WORK ITEM 36: Spud Wells, Inspect - Barge WORK ITEM 37: Spuds, Overhaul - Barge WORK ITEM 38: Decks – Exterior (Buoy or Construction Deck), Preserve 100% WORK ITEM 39: U/W Body, Preserve (100%) WORK ITEM 40: U/W Body, Preserve (100%) WORK ITEM 41: U/W Body, Preserve (Partial - Condition A) - Tender iii (Rev-0)
WORK ITEM 42: U/W Body, Preserve (Partial - Condition A) - Barge WORK ITEM 43: U/W Body, Preserve (Partial - Condition B) - Tender WORK ITEM 44: U/W Body, Preserve (Partial - Condition B) - Barge WORK ITEM 45: U/W Body, Preserve (Partial - Condition C) WORK ITEM 46: U/W Body, Preserve (Partial - Condition C) WORK ITEM 47: Stern Tube Interior Surfaces, Preserve 100% WORK ITEM 48: Cathodic Protection / Zinc Anodes, Renew - Tender WORK ITEM 49: Cathodic Protection / Zinc Anodes, Renew - Barge WORK ITEM 50: Drydock WORK ITEM 51: Drydock WORK ITEM 52: Temporary Services, Provide - Tender WORK ITEM 53: Sea Trial Performance, Support, Provide WORK ITEM 54: Tanks (MP Fuel Service), Clean and Inspect - Barge WORK ITEM 55: Deck Gear, Shrink Wrap WORK ITEM 56: Boat Davit Winch, Shrink Wrap WORK ITEM 57: Buoy and Cargo Handling Crane, Shrink Wrap WORK ITEM 58: Machinery Exhaust Stack Insulation, Renew WORK ITEM 59: Decks - Exterior, Preserve (“Non-Skid Broadcast Grit” System) WORK ITEM 60: Deck Plating, Renew WORK ITEM 61: Plating, Bulwark, Repair WORK ITEM 62: Structural Repair, Lazarette WORK ITEM 63: Aft Rake Structural Repair, Barge iv (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
v (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.
All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – as follows:
MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm
Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp
Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws::
www.gpoaccess.gov
The Government is aware of the following internet web links where contractors may procure commercial specifications:
American Welding Society (AWS): http://www.awspubs.com/index.php
ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/
NFPA: http://www.nfpa.org
SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace
COAST GUARD DRAWINGS
Coast Guard 68B CGB 2602-001, Rev -, Spud Well & Stern Log
Coast Guard Drawing 68 CGB 0700-003, Rev-, 68FT Steel Barge Docking Block Arrangement (“A” and “B” Class)
Coast Guard Drawing 68 CGB 1101-003, Rev C, 68FT Steel Barge Lines, Plating, and Deck & Bottom Framing Plans (CGB 68018-68020)
Coast Guard Drawing 68 CGB-1101-001, Rev -, Structural Sections and Details
Coast Guard Drawing 68B CGB 0103-8, Rev 1, General Arrangement Plan and Outboard Profile
Coast Guard Drawing 68B CGB 2901-004, Rev -, Curves of Form
Coast Guard Drawing 68B CGB-103-003, Rev A, Inboard Profile
Coast Guard Drawing 68B CGB-1103-001, Rev C, Lines, Plating & Dk & Bottom Framing Plans
Coast Guard Drawing 68B CGB-1111-002, Rev -, Profiles & Transverse Trusses
Coast Guard Drawing 68-CGB 1112-2, Rev -, Transducer Wet Wall & Blister Installation
Coast Guard Drawing 75 WAGL 0103-2, Rev 1, Outboard Profile and Inboard Profile
Coast Guard Drawing 75 WAGL 0103-4, Rev A, Booklet of General Plans
Coast Guard Drawing 75 WAGL 0700-004, Rev -, Docking Plan
Coast Guard Drawing 75 WAGL 633-001, Rev A, Cathodic Protection
Coast Guard Drawing 75 WLIC 111-002, Rev -, Grid Cooler Recess (AXE)
Coast Guard Drawing 75 WLIC 536-001, Rev -, Diagram Jacket Water System (AXE) vi (Rev-0)
Coast Guard Drawing 75 WLIC 536-002, Rev A, Main Engine & Generator Jacket Water System Arrangement & Details (AXE)
Coast Guard Drawing 75 WLIC-116-001, Rev B, Main Deck Framing Plan
Coast Guard Drawing 75D WAGL 0500-003, Rev -, Lines and Offsets
Coast Guard Drawing 75D WAGL 0700-004, Rev -, 75FT “D” Class Towboat Docking Block Arrangement
Coast Guard Drawing 75D WAGL 103-7, Rev C-, Outboard Profile and Inboard Profile (75306-75307)
Coast Guard Drawing 75D WAGL 1101-001, Rev C, Shell Expansion (75306)
Coast Guard Drawing 75D WAGL 1103-002, Rev -, Framing Plan
Coast Guard Drawing 75D WAGL 1103-003, Rev A, Frames 4, 12, 16, 21, 31, & 36
Coast Guard Drawing 75D WAGL 1105-007, Rev -, Miscellaneous Bulkheads and Frames
Coast Guard Drawing 75D WAGL 2200-001, Rev A, Rudder Stock and Fittings (75306-75307)
Coast Guard Drawing 75D WAGL 2200-002, Rev A, Steering Gear Arrangement (75306-75307)
Coast Guard Drawing 75D WAGL 2901-001, Rev A, Curves of Form
Coast Guard Drawing 75D WAGL 700-004, Rev -, 75FT “D” Class Towboat Docking Block Arrangement
Coast Guard Drawing 75D-WAGL 2200-14, Rev B, Steering System Arrangement for Jastram S2-16-2-
Coast Guard Drawing 75D-WAGL 2200-15, Rev B, Flanking Steering System Arrangement for Jastrum S2-16-2-35
Coast Guard Drawing 75D-WAGL 2200-16, Rev C, Rudder Post Installation for Jastrum S2-16-2-35 Steering System
Coast Guard Drawing 75D-WAGL 4301-3, Rev C, Shafting Installation to Suit If 1312 MDE
Coast Guard Drawing 75D-WAGL 1101-03, Rev -, Shell Expansion (75309-75310)
Coast Guard Drawing 75D-WAGL 1604-009, Rev A, Bulwark Ext Handrail & Grabrail Layout (75309- 75310)
Coast Guard Drawing 75D-WAGL 1604-010, Rev A, Bulwark Ext Handrail & Grabrail Dets (75309- 75310)
Coast Guard Drawing 75D-WAGL 4301-3, Rev -, Shafting Installation to Suit If 1312 MDE
Coast Guard Drawing 75-WAGL 2200-11, Rev D, Flanking Rudder Stock and Fittings for Jastram S2- 16-2-35 Steering System
Coast Guard Drawing 75-WAGL 4301-5, Rev E, Shafting Machining Details to Suit If 1312 MDE
Coast Guard Drawing 75-WAGL 4400-3, Rev E, Propeller to Suit IF1312 MDE
Coast Guard Drawing 75-WLIC 116-003, Rev B, Hull Framing Plan
Coast Guard Drawing 75-WLIC 602-003, Rev -, Outboard Profile
Coast Guard Drawing 75-WLIC 602-004, Rev -, Inboard Profile
Coast Guard Drawing 75-WLIC 85-001, Rev A, Booklet Of General Plans
Coast Guard Drawing 75-WLIC-259-001, Rev B , DIAGRAM – EXHAUST SYSTEMS
Coast Guard Drawing 75-WLIC-259-002, Rev A , ARRG'T & DET - EXHAUST SYSTEMS
Coast Guard Drawing 75-WLIC-583-001, Rev A, Davit Arrangement and Details
Coast Guard Drawing FL 6713-203, Rev -, CRP-V850 Transducer (SS505) Adapter Assembly
NAVSEA Drawing 803-921865, Rev R, Cathodic Protection Hull Zinc Anodes vii (Rev-0)
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual
Coast Guard Technical Publication (TP) 3494, 09-DEC-03, Shaft Seal - Type Fse
Coast Guard Technical Publication (TP) 5491, SWBS 256, Apr 2013, Keel Grid Cooler (Duramax)
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2012, General Requirements
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2014, Auxiliary Machine Systems
Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2014, Clean Shipboard Ventilation Systems
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2012, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2014, Drydocking
Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2014, Temporary Services
OTHER REFERENCES
ASTM International (ASTM) D1709, 2008, Standard Test Methods for Impact Resistance of Plastic Film by the Free-Falling Dart Method
ASTM International (ASTM) D1922, 2008, Standard Test Method for Propagation Tear Resistance of Plastic Film and Thin Sheeting by the Pendulum Method
ASTM International (ASTM) D3359, 2009, Standard Test Methods for Measuring Adhesion by Tape Test
ASTM International (ASTM) D3359, 2010, Standard Test Methods for Measuring Adhesion by Tape Test
ASTM International (ASTM) D4138, 2013, Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means
ASTM International (ASTM) D5363, 2008; Standard Specification for Anaerobic Single-Component Adhesives (An)
ASTM International (ASTM) D882, 2009, Standard Test Method for Tensile Properties of Thin Plastic Sheeting
Commercial Item Description (CID) A-A-52624, Nov 2008, Antifreeze, Multi Engine Type, Ethylene Glycol (For Caterpillar equipment applications, use CAT Extended Life Pre-Mix coolant.)
Commercial Item Description (CID) A-A-59313, Nov 2003, Thread Compound; Anti-seize, Zinc Dust- Petrolatum
Federal Specification (Fed Spec) HH-P-151, Mar 1991, Packing; Rubber-Sheet, Cloth-Insert viii (Rev-0)
Federal Specification (Fed Spec) QQ-N-281, Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections
International Standard For Organization (ISO) 484/2, 1981, Shipbuilding - Ship Screw Propeller - Manufacturing Tolerances - Part 2: Propellers of Diameter Between 0.80 and 2.50 m, Inclusive
MIL PRF-16173, Sep 2006, Corrosion Prevention Compound, Solvent Cut Back, Cold Application
MIL-A-18001, May 2005, Anodes, Sacrificial Zinc Alloy (Commercially Accepted - ASTM B418)
MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning
MIL-DTL-24244, May 2000, Insulation Material, With Special Corrosion, Chloride, and Fluoride Requirements
MIL-I-16411, Nov 1988, Insulation Felt, Thermal, Glass Fiber
MIL-PRF-16173, 2006, Corrosive Preventive Compound, Solvent Cutback, Cold Application
MIL-PRF-16173, Sep 2006, Corrosion Prevention Compound, Solvent Cut-Back, Cold-Application
MIL-PRF-24647, 2013, Paint System, Anticorrosive and Antifouling, Ship Hull
MIL-PRF-24647, Apr 2013, Paint System, Anticorrosive and Antifouling, Ship Hull
MIL-PRF-24647, Jun 2006, Paint System, Anticorrosive and Antifouling, Ship Hull
MIL-PRF-24647, Jun 2006, Paint System, Anticorrosive and Antifouling, Ship Hull
MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant
MIL-Y-1140, Sep 1985, Yarn, Cord, Sleeving, Cloth, And Tape- Glass
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2004, Solvent Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power Tool Cleaning to Bare Metal
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.3 (SSPC-SP 3), 2004, Power Tool Cleaning
The Society for Protective Coatings (SSPC), May 2012, Paint Application Specification No. 2 (PA-2), Measurement of Dry Coating Thickness with Magnetic Gages
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, 2007, Near-White Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 12/NACE No.5, 2002, Surface Preparation and Cleaning of Metals by Waterjetting Prior to Recoating
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 12/NACE No.5, 2007, Surface Preparation and Cleaning of Steel & Other Hard Materials by High and Ultrahigh Pressure Water Jetting
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 7/NACE No.4, 2007, Brush-Off Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP WJ-2/NACE WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP WJ-4/NACE WJ-4, 2012, Waterjet Cleaning of Metals – Light Cleaning ix (Rev-0)
The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Blast Cleaning x (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
25 Y **Propeller shaft 2010-01-557-1512 1 ea. 19,184.17 27 N Wartsila FSE H74537-02
Major Overhaul Kit
(WLP001365-001)
NSN: 01-560-3274 2 ea. 7,680.00
29 Y **Propeller right hand NSN: 2010-01-534-9089 1 ea. 10,129.00 29 Y **Propeller left hand NSN: 2010-01-534-9095 1 ea. 10,129.00 31 N ***Fathometer
Transducer, Shallow Water, 50-200 kHz
(Airmar Technology
SS555)
NSN: 5845-01-465-9723.
1 ea. $346.28
32 N ***Fathometer Transducer, Shallow Water, 50-200 kHz
(Airmar Technology
SS505)
NSN: 5845-01-465-9723.
1 ea. $346.28
34 Y **Rudder assembly NSN: 2 ea. 25,000.00 34 Y **Rudder stock NSN: 2 ea. 12,000.00 50 Y *Transducer Cover Plate N/A 1 ea. 50.00 51 Y *Transducer Cover Plate N/A 4 ea. 50.00
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT Service Center ff xi (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):
Work Item
Title
3 Hull Plating (U/W Body), Ultrasonic Testing - Tender
4 Hull Plating (U/W Body), Ultrasonic Testing - Barge
20 Tanks (MP Fuel Stowage and Overflow), Clean and Inspect - Tender
21 Voids (Non-Accessible), Leak Test - Tender
22 Voids (Non-Accessible), Leak Test
25 Propulsion Shafting, Remove, Inspect, and Reinstall
26 Propulsion Shafting, Optical Or Laser Alignment Check
27 Propulsion Shaft Seals, Mechanical & Inflatable, Overhaul and Renew
28 Propulsion Shaft Bearings (External), Check Clearances
34 Rudder Assembly; Remove, Inspect and Reinstall
39 U/W Body, Preserve (100%) - Tender
40 U/W Body, Preserve (100%) - Barge xii (Rev-0)
PRINCIPAL CHARACTERISTICS - TENDER
75' WLIC (D-CLASS), TENDER
PHYSICAL
Length overall 75' 0" Depth 7' 7-3/4" Maximum beam 22' 0" Height of highest projection 32' 0" Full load draft 4' 4 11/16" LCF Draft Full load displacement 148.49 Long Tons Fresh Water Shore tie voltage requirements 440 VAC / 3 Phase Frame spacing 1' 6"
HULL
Hull material Steel
MACHINERY
Number of propellers 2 Number of blades 4 Diameter of propeller 48" Pitch 40" fixed
RPM 400
Shaft Diameter 4.5”
TANK CAPACITIES
Fuel tanks Fresh water tanks Lube oil xiii (Rev-0)
PRINCIPAL CHARACTERISTICS - BARGE
68' CGB (B-CLASS: 68016 -68020), BARGE
PHYSICAL
Length overall 68' 6-1/2" Depth 7' 0" Maximum beam 28' 0" Full load draft 3' 0" Full load displacement 117 Long Tons Shore tie voltage requirements 440 VAC / 3 Phase Frame spacing 1' 0"
1 (Rev-0)
00000_0315_FLT
REC_00000_FLT_ Commercial Project @ Contractor’ Facility (1212)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.
NOTE
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
2 (Rev-0)
3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.
3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).
NOTE
Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes (provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.
3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.
3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 Contractor operated (non USCG) facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.
3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, 3 (Rev-0) and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to adequately accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix A, Requirements For Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.
3.6 Local Policy. None.
3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2014 Edition Standard Specifications and supersede published content:
None.
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
4 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
Vessel Name Hull # Work Item # Work Item Title
Location of Work (incl. frame #’s) Area (sqft)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down
(maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max.
threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
Name of QP-1/NACE Inspector Signature Cert. # Date / Time
5 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE &
TIME
ACTIVITY
(Surface preparation, primer coat, barrier coat, top coat, etc…)
LOCATION
(Frame & Deck, relation to equipment, etc.)
TEMPERATURE
% REL.
HUMID-
ITY DEW
PT.
SURFACE AMBIENT
ΔT
| DP -
Surface |
6 (Rev-0)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
Location of Work (Frame References) Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils) Min Max Mean
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
Abrasive Manufacturer and Sieve Size: _________________________________
Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils
Mean Mil Reading (IAW ASTM D4417-Method C) for above 15 readings: ______________
7 (Rev-0)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils) Min Max Mean
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
Abrasive Manufacturer and Sieve Size: _________________________________
Record measurements taken in the spaces provided below, to serve as permanent QA record. Maintain separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils Mean Mil Reading (IAW ASTM D4417-Method B) for above 10 readings (by column):
_____ mils _____ mils _____ mils _____ mils _____ mils
8 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15
DATE TEST LOCATIONS
CONDUCTIVITY
(microsiemens/cm)
9 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
Coating Mfg Product Name Batch # Induction
Time Coating System Sequence
(Primer/Touchup/3rd Coat, etc.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2
SPOT 1 2 3 4 5
AVERAGE
VALUE
*BASE METAL
READING (BMR)
*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation
3 Before Adjustments
After Adjustments
Avg.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation
3 Before Adjustments
After Adjustments
Avg.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation
3 Before Adjustments
After Adjustments
Avg.
Application Method (Airless, Conventional Spray, Rolled) Average DFT
10 (Rev-0)
11000_0815_FLT
REC_11000_UWHIB_FLT_75’ WLIC (‘D’ Class: Hulls 75306, 75309, 75310) (1211)
WORK ITEM 1: Hull Plating (U/W Body), Inspect- Tender
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to inspect/survey the vessel’s Under Water (U/W) hull plating, including U/W appendages and coating system.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 75D WAGL 0700-004, Rev -, 75FT “D” Class Towboat Docking Block Arrangement
Coast Guard Drawing 75D WAGL 1101-001, Rev C, Shell Expansion (75306-75307)
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
OTHER REFERENCES
ASTM International (ASTM) D4138, 2013, Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means
The Society for Protective Coatings (SSPC), May 2012, Paint Application Specification No. 2 (PA-2), Measurement of Dry Coating Thickness with Magnetic Gages
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
11 (Rev-0)
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).
3.2 Inspection. The Contractor shall accompany the Underwater Hull Inspection Board (UWHIB) in the performance of the below inspection tasks, as applicable, using the drawings listed in Section 2 (References) as guidance. The Contractor shall provide the following, to facilitate the UWHIB in assessing the condition of the designated U/W hull components and systems:
A hull repair supervisor and a marker.
Temporary staging and other necessary equipment, as applicable, for ensuring safe access to all areas of the U/W hull.
NOTES
1. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.
2. Some of the components and/or systems addressed in this work item may not be applicable to all vessel classes.
3.2.1 Hull plating.
3.2.1.1 The Contractor shall inspect the condition of the hull plating (including thruster tunnel plating, as applicable), for the presence of marine growth, deformation, and any evidence of major corrosion or electrolytic action.
3.2.1.2 The Contractor shall inspect the hull and keel areas, report on the condition of butt-welded seams, doubler plates, lap seams, and for any signs of damaged plating or unusual waviness in the plating.
3.2.2 Sea chests and all other cooling system intake components. The Contractor shall inspect all sea chests, tunnels, hull openings, and grates for general appearance, loose, damaged, or missing grates, loose or missing fasteners, condition of sea strainers and lockwire on bolts, marine growth on grating slots, and any obstructions in the openings that might prevent proper suction and discharge of water.
3.2.3 Rudders. The Contractor shall check general condition, condition around the drain plugs, and check for pitting, if any, on the leading and trailing edges.
3.2.4 Propeller and shaft associated components. The Contractor shall inspect the condition of propellers for propellers for signs of corrosion, pitting, erosion, fouling, cracks, dings, and nicks by side and blade;
inspect fairwaters, rope guards, shafts, and mechanical seals - look for missing screws, physical damage to the blades, pitting, condition of dunce caps, and condition of securing devices.
3.2.5 Transducers. The Contractor shall check general condition for cuts, cracks, corrosion, and surface
12 (Rev-0) defects around the openings. Check transducer securing nuts for tightness, and inspect cables for chafing and other damage.
3.2.6 Zinc anodes.
3.2.6.1 The Contractor shall remove all marine growth and oxide coating from all hull, rudder, shaft strut, sea chest, z-drive, and thruster tunnel zinc anodes, or water jet drives anodes, as applicable, using a light-wire brush.
3.2.6.2 The Contractor shall visually inspect all zinc anodes; check the soundness of mounting strap and stud welds, missing fasteners, and percentage of remaining material.
3.2.7 Coating system inspections. The Contractor shall accomplish the below inspections, in conjunction with the underwater hull inspection conducted by the Underwater Hull Inspection Board (UWHIB).
Document the condition found as “Partial - Condition A”, “Partial - Condition B”, “Partial Condition C”, or “100%”, as applicable (see 4.1 (Definitions)). Submit a CFR.
NOTE
The following inspections are for determining the existing condition of the coating system for the underwater body surfaces, which are deemed “Critical-coated” surfaces; they must be carried out by a SSPC-QP-1 certified contractor/sub-Contractor or a NACE Inspector – see SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
3.2.7.1 Visual. Perform a visual inspection of the existing U/W body coating system.
3.2.7.2 Dry film thickness(DFT) measurements. Take total DFT measurements of the U/W body coating system, in accordance with SSPC-PA 2.
4. NOTES
4.1 Definitions.
4.1.1 "Partial – Condition A”: The condition that exists where the substrate is exposed in up to 33% of the entire U/W body.
4.1.2 "Partial - Condition B": The condition that exists where the anticorrosive (AC) undercoating system has incurred damage, but, the u/w body hull substrate is not exposed in any location.
4.1.3 "Partial - Condition C”: The condition that exists where damage is confined to the antifoulant (AF) topcoating; the epoxy undercoating system is not exposed in any location.
4.1.4 "100%”: The condition that exists where more than 33% of the U/W body hull substrate is exposed.
4.2 UWHIB convention. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.
13 (Rev-0)
11000_0815_FLT
REC_11000_UWHIB_FLT_68' Barge (ALL) (1211)
WORK ITEM 2: Hull Plating (U/W Body), Inspect - Barge
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to inspect/survey the vessel’s Under Water (U/W) hull plating, including U/W appendages and coating system.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 68 CGB 0700-003, Rev -, 68FT Steel Barge Docking Block Arrangement (“A” and “B” Class)
Coast Guard Drawing 68 CGB 1101-001, Rev -, 68FT Structural Sections & Details
Coast Guard Drawing 68 CGB 1101-003, Rev C, 68FT Steel Barge Lines, Plating, and Deck & Bottom Framing Plans (CGB 68016-68017)
Coast Guard Drawing 68 CGB 1101-003, Rev C, 68FT Steel Barge Lines, Plating, and Deck & Bottom Framing Plans (CGB 68018-68020)
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
OTHER REFERENCES
ASTM International (ASTM) D4138, 2013, Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means
The Society for Protective Coatings (SSPC), May 2012, Paint Application Specification No. 2 (PA-2), Measurement of Dry Coating Thickness with Magnetic Gages
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
14 (Rev-0)
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).
3.2 Inspection. The Contractor shall accompany the Underwater Hull Inspection Board (UWHIB) in the performance of the below inspection tasks, as applicable, using the drawings listed in Section 2 (References) as guidance. The Contractor shall provide the following, to facilitate the UWHIB in assessing the condition of the designated U/W hull components and systems:
A hull repair supervisor and a marker.
Temporary staging and other necessary equipment, as applicable, for ensuring safe access to all areas of the U/W hull.
NOTES
1. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.
2. Some of the components and/or systems addressed in this work item may not be applicable to all vessel classes.
3.2.1 Hull plating.
3.2.1.1 The Contractor shall inspect the condition of the hull plating (including thruster tunnel plating, as applicable), for the presence of marine growth, deformation, and any evidence of major corrosion or electrolytic action.
3.2.1.2 The Contractor shall inspect the hull and keel areas, report on the condition of butt-welded seams, doubler plates, lap seams, and for any signs of damaged plating or unusual waviness in the plating.
3.2.2 Sea chests and all other cooling system intake components. The Contractor shall inspect all sea chests, tunnels, hull openings, and grates for general appearance, loose, damaged, or missing grates, loose or missing fasteners, condition of sea strainers and lockwire on bolts, marine growth on grating slots, and any obstructions in the openings that might prevent proper suction and discharge of water.
3.2.3 Rudders. The Contractor shall check general condition, condition around the drain plugs, and check for pitting, if any, on the leading and trailing edges.
3.2.4 Propeller and shaft associated components. The Contractor shall inspect the condition of propellers for propellers for signs of corrosion, pitting, erosion, fouling, cracks, dings, and nicks by side and blade;
15 (Rev-0) inspect fairwaters, rope guards, shafts, and mechanical seals - look for missing screws, physical damage to the blades, pitting, condition of dunce caps, and condition of securing devices.
3.2.5 Transducers. The Contractor shall check general condition for cuts, cracks, corrosion, and surface defects around the openings. Check transducer securing nuts for tightness, and inspect cables for chafing and other damage.
3.2.6 Zinc anodes.
3.2.6.1 The Contractor shall remove all marine growth and oxide coating from all hull, rudder, shaft strut, sea chest, z-drive, and thruster tunnel zinc anodes, or water jet drives anodes, as applicable, using a light-wire brush.
3.2.6.2 The Contractor shall visually inspect all zinc anodes; check the soundness of mounting strap and stud welds, missing fasteners, and percentage of remaining material.
3.2.7 Coating system inspections. The Contractor shall accomplish the below inspections, in conjunction with the underwater hull inspection conducted by the Underwater Hull Inspection Board (UWHIB).
Document the condition found as “Partial - Condition A”, “Partial - Condition B”, “Partial Condition C”, or “100%”, as applicable (see 4.1 (Definitions)). Submit a CFR.
NOTE
The following inspections are for determining the existing condition of the coating system for the underwater body surfaces, which are deemed “Critical-coated” surfaces; they must be carried out by a SSPC-QP-1 certified contractor/sub-Contractor or a NACE Inspector – see SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
3.2.7.1 Visual. Perform a visual inspection of the existing U/W body coating system.
3.2.7.2 Dry film thickness(DFT) measurements. Take total DFT measurements of the U/W body coating system, in accordance with SSPC-PA 2.
4. NOTES
4.1 Definitions.
4.1.1 "Partial – Condition A”: The condition that exists where the substrate is exposed in up to 33% of the entire U/W body.
4.1.2 "Partial - Condition B": The condition that exists where the anticorrosive (AC) undercoating system has incurred damage, but, the u/w body hull substrate is not exposed in any location.
4.1.3 "Partial - Condition C”: The condition that exists where damage is confined to the antifoulant (AF) topcoating; the epoxy undercoating system is not exposed in any location.
4.1.4 "100%”: The condition that exists where more than 33% of the U/W body hull substrate is exposed.
16 (Rev-0)
4.2 UWHIB convention. The COR will convene the UWHIB as soon as possible after the vessel has been dry-docked and before any work (except U/W hull cleaning/wash down) is performed on the U/W hull and appendages.
17 (Rev-0)
11010_UT_0712_FLT
REC_11010_UT_FLT_75’ WLIC (‘D’ Class: Hull 75306 (0911)
WORK ITEM 3: Hull Plating (U/W Body), Ultrasonic Testing - Tender
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to conduct ultrasonic testing (UT) of U/W hull plating.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 75D WAGL 700-004, Rev -, 75FT “D” Class Towboat Docking Block Arrangement
Coast Guard Drawing 75D WAGL 1101-001, Rev C, Shell Expansion (75306-75307)
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes
OTHER REFERENCES
None.
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the…