USCGC DILIGENCE (WMEC 616)

210 FOOT "A CLASS" MEDIUM ENDURANCE CUTTER

SPECIFICATION FOR DOCKSIDE (DS2) REPAIRS

FY2013

Developed By: J Carter Jr.

(Rev-1, 05 October 2012)

USCGC DILIGENCE (WMEC-210A) DOCKSIDE AVAILABILITY FY2013

TABLE OF CONTENTS

Revisions Record ...................................................................................................................................................... iii Consolidated List of References ............................................................................................................................... iv Consolidated List of Government-furnished Property ............................................................................................. ix Consolidated List of Critical Inspection Items .......................................................................................................... x Principal Characteristics ........................................................................................................................................... xi General Requirements WORK ITEM 1: Tanks (MP Fuel Service, Stowage and Overflow), Clean, Inspect and Partial Preserve WORK ITEM 2: Tanks (Potable Water/Ballast), Clean, Inspect and Partial Preserve WORK ITEM 3: Tanks (Lube/Hydraulic Oil), Clean, Inspect and Partial Preserve WORK ITEM 4: Chain Locker, Inspect and Preserve WORK ITEM 5: Voids (Accessible), Clean, Inspect and Partial Preserve WORK ITEM 6: Tanks (Dirty Oil and Waste), Clean, Inspect and Partial Preserve WORK ITEM 7: Vent Ducts (Engine and Motor Room All), Commercial Cleaning WORK ITEM 8: Vent Ducts (Galley and Pantry Room All), Commercial Cleaning WORK ITEM 9: Vent Ducts (Laundry Exhaust), Commercial Cleaning WORK ITEM 10: Vent Ducts (All Other), Commercial Cleaning WORK ITEM 11: Anchor Windlass, Inspect and Service WORK ITEM 12: Anchor(s), Anchor Chain(s) and Ground Tackle, Inspect and Repair WORK ITEM 13: Warping Capstan, Inspect and Service WORK ITEM 14: Control Air Dryer, Upgrade WORK ITEM 15: Sewage Tank Vent Piping, Install WORK ITEM 16: Ship Service Boiler(S), Renew WORK ITEM 17: Forecastle Bulwark, Repair WORK ITEM 18: Steering System Actuators, Repair WORK ITEM 19: Railing, Inspect and Repair WORK ITEM 20: Steam Supply and Return Piping, Renew WORK ITEM 21: Oily Water Holding Tank (OWHT) Vent, Install WORK ITEM 22: Tanks (Aviation Fuel Service, Storage and Overflow ), Clean, Insp and Partial Preserve WORK ITEM 23: Propulsion Shafting, Strain Gage, Alignment Inspections WORK ITEM 24: Reverse Osmosis Desalination Plant, Overhaul WORK ITEM 25: Towing Bitts, Chocks, and Fairleads; Inspect and Test ii (Rev-1)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

05Oct2012 Rev-1 WI 24 Added GFE List to Specification and Table.

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iii (Rev-1)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.

All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – as follows:

• MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm

• Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp

• Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws::

www.gpoaccess.gov

The Government is aware of the following internet web links where contractors may procure commercial specifications:

• American Welding Society (AWS): http://www.awspubs.com/index.php

• ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/

• NFPA: http://www.nfpa.org

• SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace

COAST GUARD DRAWINGS

Coast Guard Drawing 618 WMEC 085-161, Rev D, Booklet of General Plans Coast Guard Drawing 618 WMEC 111-001, Rev G, Shell Expansion Framing & C.V.K Coast Guard Drawing 618 WMEC 111-003, Rev -, Forward Bulwark Details Coast Guard Drawing 618 WMEC 116-001, Rev-, Forepeak Framing, Chain Locker, & Transverse

Bulkheads #12 & 15-1/2 Coast Guard Drawing 618 WMEC 117-001, Rev H, Transverse Web Frames Fwd and Aft of Midship Coast Guard Drawing 618 WMEC 117-003, Rev-, Midship and Type Sections Coast Guard Drawing 618 WMEC 123-002, Rev G, New Double Bottom Fuel Tank Structural Details Coast Guard Drawing 618 WMEC 123-003, Rev G, Lube Oil, Dirty Oil and Diesel Oil Overflow Tanks

Structural Details Coast Guard Drawing 618 WMEC 131-001, Rev M, Second & Main Deck Plating & Supports Coast Guard Drawing 618 WMEC 152-001, Rev N, Superstructure Aircastle 01 & 02 Deckhouse Coast Guard Drawing 618 WMEC 182-002, Rev W, Foundations in Engine Room Coast Guard Drawing 618 WMEC 185-001, Rev K, A/C Machinery and Sewage Disposal Room Fdns Coast Guard Drawing 618 WMEC 186-006, Rev -, Installation of Jared Anchor Windlass and Warping

Capstan “A” Class MEP Coast Guard Drawing 618 WMEC 244-001, Rev B, Shafting Alignment Coast Guard Drawing 618 WMEC 244-003, Rev G, Shafting Arrangement & Details (Water Lubricated

Bearing) Coast Guard Drawing 618 WMEC 244-004, Rev A, Shafting Alignment (RELIANCE) iv (Rev-1) http://www.assistdocs.com/search/search_basic.cfm http://www.uscg.mil/directives/default.asp http://www.gpoaccess.gov/ http://www.awspubs.com/index.php http://www.techstreet.com/ http://www.nfpa.org/ http://shopping.netsuite.com/sspcmarketplace

Coast Guard Drawing 618 WMEC 252-001, Rev N, Control Air Arrangement (“A” Class) Coast Guard Drawing 618 WMEC 252-004, Rev H, Propulsion Control & Monitoring Block &

Schematic Wiring Diagram Coast Guard Drawing 618 WMEC 252-006, Rev-, Air Treatment System Coast Guard Drawing 618 WMEC 256-002, Rev F, Evaporator Waste Heat Arrangement and Details Coast Guard Drawing 618 WMEC 261-001, Rev G, Diagram – Fuel Oil Coast Guard Drawing 618 WMEC 261-002, Rev L, Arrangement – Fuel Oil Coast Guard Drawing 618 WMEC 320-001, Rev AN, Major Maintenance Availability 440 & 115 Power

One Line Wiring Diagram & Details Coast Guard Drawing 618 WMEC 320-001, Rev AN, MMA 440 & 115 Volt Power One Line, Block

Wiring Diagram & Details Coast Guard Drawing 618 WMEC 436-001, Rev J, Central Alarm System Cabling Block Diagram Coast Guard Drawing 618 WMEC 512-004, Rev J, Fan Rooms Coast Guard Drawing 618 WMEC 512-005, Rev C, Ventilation Diagram – Third Deck Coast Guard Drawing 618 WMEC 512-006, Rev D, Ventilation Diagram – Second Deck Coast Guard Drawing 618 WMEC 512-007, Rev D, Ventilation Diagram – Main Deck Coast Guard Drawing 618 WMEC 512-008, Rev C, Ventilation Diagram – 01 Deck & Abv Coast Guard Drawing 618 WMEC 512-019, Rev A, Ventilation Mods to DC Shop and Steering Gear

Room Coast Guard Drawing 618 WMEC 529-004, Rev C, Diagram – Oily Water Separator System Coast Guard Drawing 618 WMEC 529-005, Rev F, Arrangement – Oily Water Separator System Coast Guard Drawing 618 WMEC 529-007, Rev- , Sigma OWS & Bilge Monitor Installation

Arrangement Coast Guard Drawing 618 WMEC 533-001, Rev L, Diagram Hot & Cold Potable Water System Coast Guard Drawing 618 WMEC 533-002, Rev N, Arrangement Hot & Cold Potable Water System Coast Guard Drawing 618 WMEC 535-001, Rev J, Diagram Steam, Feed and Condensate System Piping Coast Guard Drawing 618 WMEC 535-002, Rev J, Arrangement Steam Feed and Condensate System

Piping Coast Guard Drawing 618 WMEC 535-004, Rev-, Split Pipe Drain Duct for Boiler Overboard Discharge Coast Guard Drawing 618 WMEC 561-005, Rev A, Hydraulic Steering System Piping Arrangement for

Hulls 618 & 619 Coast Guard Drawing 618 WMEC 581-001, Rev B, Anchor Handling Coast Guard Drawing 618 WMEC 581-001, Rev C, Anchor Handling Coast Guard Drawing 618 WMEC 581-006, Rev-, Anchor Windlass Locking Ring Mod Coast Guard Drawing 618 WMEC 581-052, Rev-, Windlass Reducer and Motor Capstan Assembly Coast Guard Drawing 618 WMEC 581-053, Rev-, Warping Capstan Assembly Drawing Coast Guard Drawing 618 WMEC 581-055, Rev 5, Windlass Capstan Arrangement Coast Guard Drawing 618 WMEC 582-002, Rev -, Mooring Bits & Chocks Coast Guard Drawing 618 WMEC 582-003, Rev -,Towing Bitt Construction and Foundation DT Coast Guard Drawing 618 WMEC 582-004, Rev -,Bitt Mod Coast Guard Drawing 618 WMEC 593-001, Rev C, Diagram - MSD System Coast Guard Drawing 618 WMEC 593-002, Rev F, Arrangement - MSD System v (Rev-1)

Coast Guard Drawing 618 WMEC 593-003, Rev B, Sewage Vacuum Flush System Elementary Wiring Diagram Control CKT K-1SA

Coast Guard Drawing 618 WMEC 593-054, Rev-, Vacuum Interface Valve Outline Coast Guard Drawing 618 WMEC 593-055, Rev-, Sewage Ejector Outline and Installation Coast Guard Drawing 618 WMEC 593-057, Rev-, Sewage Pump Outline Coast Guard Drawing 618 WMEC 601-001, Rev F, Outboard Profile Coast Guard Drawing 618 WMEC 601-002, Rev B, Inboard Profile Coast Guard Drawing 618 WMEC 601-003, Rev H, General Arrangement 2nd and 3rd Decks Coast Guard Drawing 618 WMEC 601-003, Rev H, General Arrangement, Second and Third Decks Coast Guard Drawing 618 WMEC 601-004, Rev K, General Arrangement Main and 01 Decks Coast Guard Drawing 618 WMEC 612-001, Rev F, Rails, Stanchions & Lifelines Coast Guard Drawing 618 WMEC 635-002, Rev J, Sheathing and Insulation Coast Guard Drawing 618 WMEC 635-003, Rev E, Sheathing and Insulation in Machinery Spaces Coast Guard Drawing 618 WMEC 644-003, Rev F, Sanitary Partitions Coast Guard Drawing 618 WMEC 85-181, Rev D, Booklet of General Plans, (ACTIVE 618) Coast Guard Drawing 618WMEC 535-002, Rev J, Arr. Steam, Feed & Condensate System Piping Coast Guard Drawing 627 WMEC 252-001, Rev G, Control Air Piping Arrangement (“B” Class) Coast Guard Drawing 627 WMEC 252-004, Rev D, Propulsion Control & Monitoring Block &

Schematic Wiring Diagram Coast Guard Drawing 627 WMEC 320-001, Rev AP, 440 & 115 Volt Power One Line Block Wiring

Diagram & Miscellaneous Details Coast Guard Drawing 627 WMEC 533-007, Rev B, Reverse Osmosis Desalinator Arrangement & Details

(not applicable to this vessel class, but can be used for guidance, with understanding variations will exist)

NAVSEA Drawing 804-5959214, Rev-, Piping Insulation - Installation Details

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors

Manual Coast Guard Technical Publication (TP) 2188, Jun 2010, Steam Heating Boiler - Model 5848-14E Coast Guard Technical Publication (TP) 3231A, Feb 2012, Manufacturer's Instruction Book - SWBS

Group(s) 242-245 Coast Guard Technical Publication (TP) 3231B, SWBS 252, Feb 2010, Propulsion Pneumatic Control

System (210 WMEC “A” and “B” Class) Coast Guard Technical Publication (TP) 3240A, SWBS 581, Oct 2011, Anchor Windlass Coast Guard Technical Publication (TP) 3240A, SWBS 582, Oct 2011, Warping Capstan Coast Guard Technical Publication (TP) 3241, SWBS 593, Jun 2011, Vacuum Sewage System Coast Guard Technical Publication (TP) 3941A, July 2011, Reverse Osmosis Desalination Plant - Model

RC5000

Coast Guard Technical Publication (TP) 4200, Jan 1991, SWBS 561, Manufacturer's Instruction Book, Electro-Hydraulic Steering System Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 0000, Jan 2009, General

Requirements vi (Rev-1)

Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 0740, Jan 2009, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), Jan 2009, Temporary Hull Accesses

Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), Jan 2009, Overhaul AC Electrical Motors In-Shop

Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 5000, Jan 2009, Inspect, Repair, And Test Auxiliary Machine Systems

Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), Jan 2009, Clean Shipboard Ventilation Systems

OTHER REFERENCES

American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2002, Disinfection of Water-Storage Facilities American National Standards Institute/NSF International (ANSI/NSF) 61, 2008, Drinking Water System

Components - Health Effects ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets ASTM International (ASTM) D4417, 2003, Standard Test Methods for Field Measurement of Surface

Profile of Blast Cleaned Steel ASTM International (ASTM) F683, 2003, Standard Practice for Selection and Application of Thermal

Insulation for Piping and Machinery ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates Code of Federal Regulations (CFR) Title 33 CFR, 2008, Navigation and Navigable Waters Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety

Administration, Department Of Transportation Commercial Item Description (CID) A-A-59316, Nov 2003, Abrasive Materials for Blasting Federal Specification (Fed Spec) QQ-N-281, Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections Federal Specification (Fed Spec) RR-C-271, Nov 1995, Chain and Attachments, Welded and Weldless Federal Standard (FED-STD) 595, 2008, Colors Used In Government Procurement Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-58, 2009, Pipe

Hangers and Supports – Materials, Design, Manufacture, Selection, Application and Installation MIL-A-22262, Mar 1996, Abrasive Blasting Media Ship Hull Blast Cleaning MIL-C-24633, Apr 1998, Chain, Stud Link, Anchor, Low Alloy Steel, Flash Butt Welded MIL-DTL-23549, Feb 2007, Grease, General Purpose MIL-STD-419 D, Jul 1987, Cleaning, Protecting, and Testing Piping, Tubing, and Fittings for Hydraulic

Power Transmission Equipment NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), May 1997, Requirements for

Fabrication, Welding, and Inspection of Submarine Structure Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and

Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2004, Solvent Cleaning The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP vii (Rev-1) viii (Rev-1)

The Society for Protective Coatings (SSPC) VIS 1, 2004, Guide and Reference Photographs for Steel Surfaces Prepared by Dry Abrasive Blast Cleaning

CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK

ITEM

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

14 N Hankison Refrigerated

Control Air Dryer PN: HPR35 1 ea. $1,095.00

14 N Filter, Coalescing (1 micron)

PN: HF7-16-4-PL 1 ea. $176.00

14 N Hankison Replacement Filter

PN: E716 1 ea. $37.00

14 N Filter, Oil Removal PN: HF5-16-4-PL 1 ea. $180.00 14 N Hankison Replacement

Filter PN: E516 1 ea. $46.00

14 N **Valve, Ball NSN: 4820-01-243-9951 4 ea. $6.91

16 N Way-Wolff Boiler Model No. 5848-14E

NSN: 4410-01-182-1910

2 ea. $35,000.00

16 N Gasket NSN: 5330-01-386-5911 2 ea. $492.10 16 N Burner Assembly NSN: 4530-01-082-1141 2 ea. $4279.50

N 5 Micron Filter

NSN: 4601-01-396-1460 2 ea.

$92.00

24 N 20 Micron Filter

NSN: 4610-01-396-1465 2 ea.

$72.00

24 N Drive Belt

NSN: 3030-00-482-4654 2 ea.

$7.00

24 N Membrane

NSN: 4330-01-491-9780

12ea $611.00

Y High Pressure Pump

NSN: 4320-01-503-5378 2 ea.

$5,601.00

24 N Bromine Cartidge

NSN: 4610-01-514-7266 2 ea.

$150.00

24 N Carbon Filter

NSN: 4330-01-503-3219 2 ea.

$70.00

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter ix (Rev-1)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000_STD, paragraph

3.2.6.5 (Inspection report particulars)):

Work Item Title

11 Anchor Windlass, Inspect and Service

12 Anchors, Anchor Chain(s) and Ground Tackle, Inspect and Repair

13 Warping Capstan, Inspect and Service x (Rev-1)

PC_210A_WMEC_0909

PRINCIPAL CHARACTERISTICS

210' WMEC (A Class)

PHYSICAL CHARACTERISTICS

Length Overall 210' 6"

Length, Design Waterline 200' 0"

Depth (main deck at side to baseline) 19' 6"

Maximum Beam 34' 0"

Height of Highest Projection 88' 0"

Full Load Draft 4,000 lbs

Height of FM Antenna Above Baseline 90' 0"

Light Ship Displacement 875 long tons

Full Load Displacement 1100 long tons

Shore Tie Voltage Requirements 400A / 440V

Frame Spacing 1' 0"

MACHINERY CHARACTERISTICS

Main Propulsion 2 Alco Model 251B Diesel Engines, 5,000 BHP total

Ship's Service Generators 2 Caterpillar Model 3406B Diesel-driven SR4.

250 KW each @ 0.8 power factor, 440V AV, 3 phase, 60 cycle

Emergency Generator Caterpillar Model D3306B Diesel-Driven.

Century Synchronous Model, ACR-507, 190KW

Number of Propellers 2

Number of Blades 4 xi (Rev-1) xii (Rev-1)

Diameter 7' 6"

Pitch Controllable

Shaft RPM 300

Shaft Diameter 8.25"

TANK CAPACITIES

Diesel Fuel (95%) 48,375 gal

Fresh Water (95%) 11, 108 gal

JP-5 Fuel (95%) 4,697 gal

Lube Oil (95%) 1,942 gal

1 (Rev-1)

00000_PWB_0312_FLT

REC_0000_FLT_ Commercial Project @ CG Facility (0212)

General Requirements

1. SCOPE

1.1 Intent. This item describes the general requirements to be followed by the Contractor while conducting this availability.

2. REFERENCES

COAST GUARD DRAWINGS

None.

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3C, Change 1, Jun 2006, Coatings and

Color Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General

Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes

OTHER REFERENCES

ASTM International (ASTM) D4417, 2003, Standard Test Methods for Field Measurement of Surface

Profile of Blast Cleaned Steel Commercial Item Description (CID) A-A-59316, Nov 2003, Abrasive Materials for Blasting Federal Standard (FED-STD) 595, 2008, Colors Used In Government Procurement MIL-A-22262, Mar 1996, Abrasive Blasting Media Ship Hull Blast Cleaning NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), May 1997, Requirements for

Fabrication, Welding, and Inspection of Submarine Structure The Society for Protective Coatings (SSPC) VIS 1, 2004, Guide and Reference Photographs for Steel

Surfaces Prepared by Dry Abrasive Blast Cleaning Code of Federal Regulations (CFR) Title 33 CFR, 2008, Navigation and Navigable Waters Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety

Administration, Department Of Transportation

2 (Rev-1)

3. REQUIREMENTS

3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.

NOTE

The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and also to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.2 Fire watch requirements. The Contractor shall refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec 0000, in accomplishing the following task:

• Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to four Coast Guard fire watch personnel.

• Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.

3.3 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.

NOTE

NAVSEA APPROVAL IS NOT REQUIRED FOR WELDING PROCEDURES SUBMITTED BUT THE

PROCEDURES MUST BE REVIEWED AND SHOWN TO SATISFY THE REQUIREMENTS SET

FORTH IN NAVSEA TP 1688, BY A WELDING REGULATORY AGENCY. THE REQUIREMENTS

FOR WELDING WELDOX 900 SHALL BE CONSIDERED THE SAME AS THOSE FOR WELDING

HY-130

3.4 HW disposal. The Contractor shall be responsible for all hazardous wastes generated by work under this contract. Label and package all hazardous wastes in 49 CFR-approved containers, and in accordance with all other applicable Federal, state, and local laws and regulations. In addition, comply with applicable parts of 40 CFR 262, applicable to handling of hazardous wastes.

3.4.1 Along with the Government, the Contractor shall be contractually considered the co-generator of all hazardous wastes; be aware that the Government will make available its facility’s EPA Generator Identification (ID) Number for manifesting of hazardous wastes.

3.4.2 The Contractor shall identify, arrange, and be responsible for the turnover of all hazardous wastes, within the confines of the Coast Guard shore facility, to the facility’s HM/HW Coordinator. Notify the ship’s HW Coordinator prior to any transfers of HW from ship to shore.

3.4.3 The Contractor shall prepare a manifest of hazardous waste to be reviewed and signed by the HM/HW Coordinator. Contact the HM/HW Coordinator for turnover of any hazardous waste; in addition, notify the COTR in writing 24 hours prior to any waste removals, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).

3.4.4 The Contractor shall be aware of the following:

3 (Rev-1)

3.4.4.1 No Contractor or Subcontractor shall have the authority to sign a Hazardous Waste Manifest using the Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast Guard facility without COTR or KO-approval.

3.4.4.2 Local environmental regulations at the Government facilities may be more stringent than in many jurisdictions. As with all environmental regulations, it is the Contractor's responsibility to research, prepare for, and comply with local and state regulations.

3.4.4.3 Coast Guard facilities do not have Facilities Response Plans (see 33 CFR 154 Subpart F). It is the Contractor’s responsibility to furnish the Facility Response Plan (FRP) when required for over-the-water liquids transfers to and from vessels. This requirement is applicable to transfers to/from vessels with an oil/fuel capacity of 250 barrels or more.

3.5 Interim changes and additions to SFLC Std Spec 0000. The Contractor shall be aware of the following interim changes and additions to the 2009 Edition of SFLC Std Spec 0000:

3.5.1 Acronyms and term definitions – paragraph 1.3 (Acronym and term definitions).

3.5.1.1 The term “COTR” has been replaced with “COR”, which is defined as follows:

“COR”: Contracting Officer’s Representative – the person delegated by the KO as the on-scene representative for matters concerning performance of work; this includes correctness, timeliness, and quality of the Contractor’s work. Normally, the CO/OINC is designated the COR.”

3.5.1.2 Definition addition for the term “Ungrounded, as follows:

• “Ungrounded”: A power system where all of the current-carrying conductors and windings

(including any neutral connection) are insulated from ground. In contrast, a generator or transformer in which at least one conductor or point (usually the midpoint or corner of a delta winding or the common center of a wye winding) is intentionally grounded, either solidly or through an impedance, is considered grounded. Note that the distinction concerns only current-carrying conductors; for both ungrounded and grounded power systems, non-current carrying metal parts and equipment grounding conductors are always bonded to earth ground for personnel safety. At non-Governmental facilities, dockside wye connected transformer secondary windings are almost always grounded and are generally not suitable for connection to a Coast Guard cutter without a separate Contractor furnished isolation transformer.”

3.5.2 Changes to paragraph 3.2.4 2.3 (QP-1 Inspector or Tech Rep duties).

“3.2.4.2.3 QP 1 Inspector or Tech Rep duties.

3.2.4.2.3.1 The Coating Inspector for the “QP 1-certified” Contractor or the Contractor-provided NACE-certified Tech Rep shall remain on site, to perform the following duties, as applicable, for each work item that involves preservation of “critical-coated surfaces”:

• Verify inspection instrument calibration.

• Verify and approve the suitability of ambient conditions before surface preparation is begun, and before each coat of paint is applied.

• Verify all aspects of surface preparation – including, but not limited to:

o Cleanliness of compressed air.

o Adequacy of solvent cleaning.

4 (Rev-1) o Proper handling of blast media.

o Actual surface preparation procedure.

• Inspect and approve final surface preparation, before application of primer coat.

• Supervise and approve coating system preparation and application procedures, including but not limited to: mixing and thinning, stripe coating application, spray techniques, and film thickness measurements and recordings.

• Determine when applied coats have sufficiently cured for overcoating, or for system service resumption (see paragraph A2.1.18 (Critical drying time requirements)).

• Complete and sign the quality assurance (QA) inspection forms (see QA-1 thru QA-5), provided in Appendix A (Requirements for Preservation of Ship Structures) of this document.

• Submit all completed QA inspection forms to the COR (through the Contractor), upon completion of work.

3.2.4.2.3.2 The Contractor shall ensure the NACE Inspector is formally informed - via suitable subcontract documentation- and is willing and able to perform of all duties listed above. Submit documentation of this contract and assumption of duties to the KO at the Arrival Conference.”

3.5.3 Changes to contents of paragraph 3.2.5 (Planning document).

“3.2.5 Planning document. The Contractor shall generate a legible Planning Document (PD) with the following characteristics:

• Graphical in format (see Fig. 1 (Sample Planning Document Submittal)).

• Shows overall period of performance for each CLIN, with start and stop dates of major sub-tasks.

• Contains due dates for Critical Inspection Reports (CIR) and any events requiring Coast

Guard Inspector presence.

• Identifies all work item time periods that require OEM Tech Rep assistance.

• Identifies the “critical paths” for the project.

• Shows calculations for the “float” along the critical paths and labels the critical paths with the number of delay days the critical paths can absorb without affecting the final delivery date.

NOTE

Float is the number of days that the critical paths can be delayed without affecting the final delivery date.

3.2.5.1 Ensure that the PD also includes the names, contact information, and written commitment from all Tech Reps required by the Contract - indicating they are available for work during the proposed time period.

3.2.5.2 Submit a preliminary electronic copy of the PD to the COR - for Government review - no later than one week after contract award.

3.2.5.3 Submit 3 copies of the PD to the COR, 15 days prior to the start of the performance period, and at all weekly Progress Meetings.

NOTE

5 (Rev-1)

A separate document, specifically prepared for the Government is not desired or required. A copy or summary of the Contractor’s internal scheduling document is preferred.

FIG. 1 - SAMPLE PLANNING DOCUMENT SUBMITTAL

ID Task Name 1 Overhaul Anchors & Anchor Chains 2 Remove from Cutter

3 Inspect & Measure Chains

4 Submit Critical Inspection Report

5 Preserve Anchors & Chains

6 Reinstall to Cutter

W T F S S M T W T F S S M T W T F S S M T W T F S S M Mar 18, '01 Mar 25, '01 Apr 1, '01 Apr 8

ID Task Name 1 Overhaul Anchors & Anchor Chains 2 Remove from Cutter

3 Inspect & Measure Chains

4 Submit Critical Inspection Report

5 Preserve Anchors & Chains

6 Reinstall to Cutter

W T F S S M T W T F S S M T W T F S S M T W T F S S M Mar 18, '01 Mar 25, '01 Apr 1, '01 Apr 8

3.2.5.4 When the critical path extends beyond or encroaches upon the final delivery date, provide a resource constraint and scheduling evaluation of the critical path before any request for extension will be entertained. Submit the resource constraint and scheduling evaluation via a CFR.

NOTE

The intent of the resource constraint and scheduling evaluation is to identify the resources necessary to ‘crash’ the critical path or make adjustments to the production schedule to meet the delivery date in lieu of a project extension.”

3.5.4 Additional sub-paragraphs to paragraph to 3.2.6.5 (Inspection report particulars).

“3.2.6.5.3 CFR tracking system. The Contractor shall create and maintain a CFR tracking system for the project. At a minimum, ensure that the CFR tracking system shall list all required reports, broken down by the following:

• Work item and paragraph number.

• Due dates.

• Submission dates.

• CFR/CIR submission number.

3.2.6.5.3.1 Be aware that the COR will respond via the CFR reply as to whether the CIR/CFR ‘fully’ or ‘partially’ satisfied the inspection and reporting requirements in the associated work item.

3.2.6.5.3.2 When submitting a CFR, ensure that the applicable work item and paragraph number for which the inspection report is being submitted is included on the CFR.

3.2.6.5.3.3 Submit a copy of the CFR tracking sheet to the COR at the arrival conference.

3.2.6.5.3.4 At a minimum the Contractor shall update and submit a copy of the CFR tracking sheet to the COR the day before each weekly progress meeting. At the required CFR due date, submit the CFR tracking sheet to the COR via a CFR for review and formal archiving with the project records.”

3.5.5 Changes to contents of paragraph 3.2.11.1 (Sanitary facilities for vessel-personnel due to disruption of grey water and sewage systems).

6 (Rev-1)

“3.2.11.1 (Sanitary facilities for vessel-personnel due to disruption of grey water and sewage systems.

When the shipboard grey water and sewage systems are disrupted due to repairs required by contract work, the Contractor shall provide vessel-personnel with a sanitary facility, within a five minute walking distance from the vessel, to include the amenities listed in Table II (Sanitary Facility Amenities). Ensure the following:

• Shower stalls are equipped with privacy screens.

• Sinks are provided with fresh hot and cold water.

• Electrical convenience GFI receptacles, in accordance with NFPA 70, National Electric

Code (NEC), are located in vicinity of sinks.

• Toilets have doors or privacy dividers.

• Lockers are capable of being locked.”

3.5.6 Changes to contents of paragraph 3.3.2.1.1 (Water depth).

“3.3.2.1.1 Water depth. Ensure that water depth is sufficient at the pier to allow the vessel's lowest underwater appendage to clear the bottom by at least two feet at:

• Ordinary low water mark on non-tidal rivers.

• At all tide conditions predicted during the availability for tidal rivers and other navigable waterways (Bay, Lake, etc.).”

3.5.7 Electrical compliance planning.

“3.3.14 Electrical compliance planning. For cutter availabilities, the Contractor shall submit to the KO the following electrical compliance planning documentation during the pre-award phase of the contract.

3.3.14 1 Shore power. When ungrounded shore power is to be provided per SFLC Std Spec 8635, provide a one line electrical diagram showing how such power will be supplied, including the winding and grounding configuration and rating of any generator or isolation transformer. For drydock availabilities, separate diagrams should be submitted for waterborne and non-waterborne periods.

3.3.14.2 Arc welding. When electric arc welding is to be performed per SFLC Std Spec 0740 while the vessel is waterborne, provide a diagram showing the general proposed location of each welding machine, the grounding configuration of each machine, and the return current conductor size and length. For drydock availabilities, separate diagrams may be necessary for waterborne and non-waterborne periods.

3.3.14.3 Hull bonding and lightning protection. For work periods while the vessel is not waterborne, provide a diagram showing how the hull grounding straps required by SFLC Std Spec 8635 will be sized (length and gauge) and connected.

3.3.14.4 Tool and equipment power. Provide a diagram showing how Contractor tool and equipment power will be supplied and distributed for dockside and shipboard use in accordance with SFLC Std Spec 0450. For drydock availabilities, separate diagrams should be submitted for waterborne and non-waterborne periods.”

3.5.8 Changes to paragraph to A2.1.1.3 (Document submission).

A1.1 “A2.1.1.3 Document submission.

A1.2 A2.1.1.3.1 For all work involving preservation of “critical-coated surfaces”, ensure the following

7 (Rev-1) is submitted to the COR at the Arrival Conference, for each coating system intended to be applied:

• Coating system manufacturer’s name.

• Product data sheets.

• MSDS.

• COC.

A1.3 A2.1.1.3.2 Documentation shall be broken out by work item, to also include the following information:

• Brand name.

• Color.

• Intended mil thickness.

• Time between coats.

• Intended final cure time prior to immersion or full duty rating, as applicable.

A1.4 A2.1.1.3.3 For work involving preservation of surfaces not designated as “critical-coated surfaces”, submit all product data sheets, MSDS, and COC to the COR, prior to commencement of work.”

3.5.9 Requirements changes to paragraphs A2.1.5 (Tenting) and A2.1.6 (Ambient condition control).

“A2.1.5 Tenting and ambient condition control – “for critical-coated surfaces”.

A2.1.5.1 When the ambient condition parameters necessary for full paint cure or to meet environmental conditions, as required in paragraph A.2.1.4 (Ambient condition parameters), cannot be met for successful application and curing of “critical-coated” surface coating systems, the Contractor shall provide the following, at no additional cost to the Government:

• Suitable tenting, as applicable, for exterior surface preservation.

• Suitable ambient condition control equipment, which may include, but not be limited to the below-listed, to create and maintain ambient conditions recommended by the coating system’s manufacturer, and facilitate successful coating application and curing.

o AC system.

o Heaters.

o Blowers.

o Dehumidifiers.

A2.1.5.2 Submit an ambient condition control plan to the COR within 24 hours prior to initiating ambient condition control process

NOTE

The Contractor is expected to be aware of the advent of environmental conditions that are adverse to preservation of critical-coated surfaces and include all costs in

3.5.10 Pre-surface preparation requirements – additional to paragraph A2.1.7 (Pre-surface preparation requirements).

“A2.1.7.4 Coupon test. In order to ensure production of required surface profile, the Contractor shall accomplish the following, tasks, whenever abrasive-blasting is required in a work item:

8 (Rev-1)

A2.1.7.4.1 Conduct a performance test on all abrasive blasting operations on a Contractor- provided test coupon, prior to starting abrasive blasting operations on the vessel. Use a new metal plate, of the same metal type and material properties as the area to be blasted, steel or aluminum plate, as applicable. For steel plates, the new plate shall have the mill scale intact and the plate will be in a Rust Grade "A" condition, per the SSPC-VIS 1 visual standard cards. No existing anchor profile, other than the surface irregularities from the manufacturing process are permitted on the test coupon. The test coupon shall be flat, with nothing welded to the side used for the anchor profile test, no thinner than a 1/8-inch plate and measuring no smaller than 1-foot by 1-foot. The test coupon shall be affixed so as to not permit excessive movement during the performance test.

CAUTION!

Do not affix the coupon to the vessel nor shall the blast media from the performance test strike the vessel during the test

A2.1.7.4.2 Ensure that the abrasive blasting operation test on the test coupon is with the very same setup that will be used to blast the vessel. The setup shall include, but not be limited to:

• The abrasive media to be used (material and media size).

• Nozzle size and type (straight bore, high velocity nozzle, angle nozzle...).

• Delivery rate and pressure settings.

A2.1.7.4.3 Blast an one-square foot area on one side of the test coupon to the abrasive surface preparation standard specified in the applicable work item and perform an anchor profile test of the blasted surface in accordance with ASTM D4417, method A or C. Notify the COR in advance of the abrasive blasting operation test, to permit the witnessing of the test by appropriate Coast Guard personnel. Submit a CFR documenting the results of the abrasive blasting operation test. CFR shall include at a minimum, the following:

• Area of the vessel that the verified setup will be used to abrasive blast with.

• The abrasive media used.

• The nozzle size and type.

• The delivery rate and pressure.

• The test coupon starting properties (material type and surface conditions).

• The resultant anchor profile readings from the test.

NOTES

1. ULTRA HIGH PRESSURE WATER JETTING DOES NOT CREATE AN ANCHOR PROFILE

AND IS EXEMPT FROM THE ANCHOR PROFILE TEST COUPON CHECK.

2. THE REVERSE SIDE OF THE TEST COUPON MAY BE USED FOR THE SUBSEQUENT

TEST, PROVIDED THAT THE CONDITIONS IN PARAGRAPH A2.1.7.4 (COUPON TEST) ARE

MET.

A2.1.7.4.3 Repeat the abrasive blasting operation test in the following instances:

• The setup, as defined in paragraph A2.1.7.4.1 is changed.

• The resultant anchor profile readings observed on the vessel are outside the specified anchor profile range.

• Media is changed from MIL-A-22262 to CID A-A-59316 or vice versa.

• The supplier of the abrasive blasting media changes, regardless if the new source for the

9 (Rev-1) media has the same specifications.

• When Directed by the COR.

NOTE

A performance test of the abrasive blasting operations on a test coupon and measuring the anchor profile prior to performing the operation on the cutter, in order to confirmed that the anchor profile range that the operation is going to produce. An abrasive blasting operation test is prudent, as there are enough variables in the equipment setup and media properties that the resulting anchor profiles from one contractor to the next vary significantly.

3.5.11 Post-surface preparation requirements - additional to paragraph A2.1.8 (Post-surface preparation requirements).

A2.1.8.8 Substrate profile measurements - during and post-surface preparation. In order to ensure production of required surface profile, the Contractor shall accomplish the following tasks, whenever abrasive-blasting is required in a work item for complete preservation of a ”critical-coated” surface:

A2.1.8.8.1 During surface preparation by abrasive blasting or waterjetting operations, spot check the existing anchor profile per 500-square feet, in order to 'project' the need to manage the excessive anchor inspect for both excessive and insufficient anchor profiles . When the Contractor elects to prepare a substrate by waterjetting, the Contractor shall inspect the substrate for areas of insufficient or excessive anchor profile, both visually and in accordance with ASTM D4417, Method A or C. Submit a CFR detailing the location, square footage, measured anchor profiles, and the anchor profile range required for the applicable coating system.

A2.1.8.8 2 Post completion of surface preparation, measure the profile of the resultant bare surfaces, in accordance with ASTM D4417, Method A or C.”

3.5.12 Caution verbiages – additional to paragraph A2.1.18 (Critical drying and cure time requirements).

“CAUTIONS!

1. Hard cure times or cure time prior to immersion for any “critical coated system” shall be met as published on the Product Data Sheets available online. No early undocking or relaxation of these published requirements is permitted without prior approval from the KO. Coating system manufacturer’s Sales or Technical Representatives may not relax these requirements. Painting and curing of all tank coating systems (except for tanks that are inboard and not touching the skin of the vessel (side and/or bottom) shall occur while the cutter is out of the water.

2. CAPAC systems shall not be energized until full cure of all underwater paint systems has occurred.”

3.5.13 Preservation Plan.

“A2.2 Preservation Plan (PP). The contractor shall submit a PP to the COR at the arrival conference, to allow for review of all work items pertaining to the preservation of the vessel. At a minimum, PP shall include the following and be broken down by work item:

• Coatings to be applied – listed by manufacturer and product identification numbers.

• Target wet and dry film thickness values.

• Authorized reducers/solvents - including maximum percent by volume for reducers/solvents.

• Colors by FED-STD-595 color number.

10 (Rev-1)

• Application method for each coat.

• Application pressure and nozzle size requirements listed on the manufacturer’s product data sheet(s).

• Minimum recoat windows for applying subsequent coats, maximum recoat windows to apply subsequent coats, adjusted for anticipated temperatures.

• Any special instructions or environmental limits listed by the coating manufacturer.

• Intended final cure times prior to immersion or full duty rating (as applicable).”

3.5.14 Changes to paragraph B2.2.3.3.1.

“B2.2.3.3.1 Do not release lead or lead-contaminated materials into the environment. Conduct periodic air monitoring (as appropriate) for lead in the worker’s breathing zone, during the course of any abatement work involving lead containing materials, to prevent exposure at or above the PEL. Submit results of all air monitoring samples to the COR, within 24 hours of completion of sampling.”

3.5.15 Booming requirements during the offload or on-load of petroleum products.

“B2.2.10 Booming requirements during the offload or load of petroleum products. The Contractor shall provide a containment boom system and boom off the cutter during all petroleum cargo on-loads and offloads. The cutter shall be boomed off by the contractor during both shipyard functions and the final bunkering of the cutter by ship's force. The contractor is responsible to provide the labor to deploy and recover the boom during all operations, including operations conducted by ship's force. The containment boom shall at a minimum, fullly encapsulate the cutter from the pier wall in front of the cutter to the pier wall at the stern of the cutter. When moored alongside a pier that does not provide a fully intact pier wall that will contain a spill, the containment boom shall wrap completely around the cutter on all sides to provide spill containment. For tug and barge configurations, the containment boom shall encapsulate both the cutter and the barge, as applicable.”

4. NOTES

4.1 Access to COMDTINST M10360.3. The COMDTINST M10360.3 may be accessed at the following URL address: http://www.uscg.mil/directives/cim.asp

4.2 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 0000 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

http://www.uscg.mil/directives/cim.asp

11 (Rev-1)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

Vessel Name Hull # Work Item # Work Item Title

Location of Work (incl. frame #’s) Area (sqft)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with COMDTINST M10360.3, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-based coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-12, SP-11, SP-10…).

Verify surface anchor profile using ASTM D4417-Methods B or C against COMDTINST M10360.3. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max.

threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

Name of QP-1/NACE Inspector Signature Cert. # Date / Time

12 (Rev-1)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE &

TIME

ACTIVITY (Surface preparation, primer coat, barrier coat, top coat, etc…)

LOCATION

(Frame &

Deck, relation to equipment, etc.)

TEMPERATURE % REL.

HUMID-

ITY DEW PT. SURFACE AMBIENT ΔT

| DP - Surface |

13 (Rev-1)

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

Location of Work (Frame References) Area (sqft)

SURFACE PREPARATION METHOD

PROFILE ACHIEVED (mils) Min Max Mean

SSPC-SP-10/NACE No. 2 SSPC-SP-12/NACE No. 5

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

Abrasive Manufacturer and Sieve Size: _________________________________

Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place…