RELIANCE Specification.pdf

PDF 704 KB Posted

Attached to
USCGC RELIANCE (WMEC 615) DOCKSIDE REPAIRS
Solicitation number
HSCG80-12-Q-P45602
Issued by

About this file

Specification

View the file

Other files

File Type Posted
Schedule of Supplies and Services.doc DOC document
SF30-A0001.pdf PDF
Past Perf Questionaire.doc DOC document
Solicitation.pdf PDF
SF 1449.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC RELIANCE (WMEC 615)

210 FOOT "A CLASS" MEDIUM ENDURANCE CUTTER

SPECIFICATION FOR DOCKSIDE REPAIRS

Developed By: J. Carter, Jr.

(Rev-1, 14 November 2011)

USCGC RELIANCE (WMEC-210A) DOCKSIDE AVAILABILITY 2012

ii (Rev-1)

TABLE OF CONTENTS

Revisions Record ....................................................................................................................................... iii Consolidated List of References ................................................................................................................ iv Consolidated List of Government-furnished Property ............................................................................. viii Consolidated List of Critical Inspection Items .......................................................................................... ix Principal Characteristics ............................................................................................................................. x General Requirements WORK ITEM 1: Chill Water System, General Maintenance WORK ITEM 2: Steering Gear (General), Overhaul WORK ITEM 3: Single Point Davit, Level 1 Inspect and Test (CIR) WORK ITEM 4: Helo Talon Grids, Inspect and Test (CIR) WORK ITEM 5: Grey Water Holding Tanks, Clean and Inspect WORK ITEM 6: Sewage Holding Tanks, Clean and Inspect WORK ITEM 7: Grey Water Piping, Clean and Flush WORK ITEM 8: Sewage Piping, Clean and Flush WORK ITEM 9: Deck Fittings, Inspect WORK ITEM 10: Urinal(s), Renew WORK ITEM 11: Main Diesel Engine (MDE) Exhaust Stack Uptakes, Clean WORK ITEM 12: Ship Service Diesel Generator (SSDG/EDG) Exhaust Piping, Commercial Clean ... 46 WORK ITEM 13: Boiler Exhaust Stack Uptakes, Commercial Clean WORK ITEM 14: Potable Water Pneumatic Tanks, Clean and Inspect WORK ITEM 15: Compressed Air Receivers, Clean, Inspect , and Test WORK ITEM 16: Heat Exchangers, Clean, Inspect and Hydro (CIR) WORK ITEM 17: Hand Rails (Pilothouse Deck, Bridge Wings, Fantail), Inspect and Renew WORK ITEM 18: Fan Space Deck, Preserve WORK ITEM 19: Trash Compactor (Drain Piping), Repair WORK ITEM 20: Galley Steam Preheater, Clean and Inspect WORK ITEM 21: Splash Guard, Modify WORK ITEM 22: Helo Net Safety Bars (Flight Deck), Renew WORK ITEM 23: Cold Food Service Counter, Relocate WORK ITEM 24: Condensate Piping, Renew WORK ITEM 25: Hull and Structural Plating–Degraded Weld (Steel), Repair WORK ITEM 26: Control Air Dryer Upgrade WORK ITEM 27: Ship Service Boiler(s), Renew (OPTIONAL)

Revisions Record This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

14Nov2011 Rev-1 WI26 Added WI 26: Control Air Dryer, Upgrade 14Nov2011 Rev-1 WI27 Added WI27: Ship Service Boiler(s), Renew (Optional)

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iii (Rev-1)

Consolidated List of References

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.

All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – as follows:

• MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm

• Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp

• Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws::

www.gpoaccess.gov

The Government is aware of the following internet web links where contractors may procure commercial specifications:

American Welding Society (AWS): http://www.awspubs.com/index.php ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/ NFPA: http://www.nfpa.org SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace

COAST GUARD DRAWINGS

Coast Guard Drawing 618 WMEC 085-181, Rev D, Booklet of General Plans, (ACTIVE 618) Coast Guard Drawing 618 WMEC 111-1, Rev G; Shell Expansion Framing & Cvk Coast Guard Drawing 618 WMEC 131-001, Rev M, Second & Main Deck Plating & Supports Coast Guard Drawing 6 18 WMEC 136-001, Rev K , 01, 02 and Bridge Deck Plating and Supports Coast Guard Drawing 618 WMEC 136-001, Rev L , 01 & 02 Level & Bridge Deck Plating & Support Coast Guard Drawing 618 WMEC 152-001, Rev N, Superstructure Aircastle, 01 and 02 Deckhouse Coast Guard Drawing 618 WMEC 154-001, Rev B, Aluminum Pilothouse Details Coast Guard Drawing 618 WMEC 182-001, Rev E, Main Engine Foundation (ACTIVE) Coast Guard Drawing 618 WMEC 182-002, Rev W, Foundations in Engine Room Coast Guard Drawing 6 18 WMEC 184-001, Rev R , Pilothouse and Bridge Deck Foundations Coast Guard Drawing 618 WMEC 186-002, Rev A, Talon Grid Foundations and Structural Mods 01 Level Coast Guard Drawing 618 WMEC 201-001, Rev E, Arrangement Machinery (ACTIVE 618) Coast Guard Drawing 627 WMEC 252-001, Rev F, Control Air Piping Arrangement (“B” Class) Coast Guard Drawing 618 WMEC 252-001, Rev M, Control Air Piping Arrangement Coast Guard Drawing 627 WMEC 252-004, Rev B, Propuln Cntrl & Monitoring Blck & Schem Wiring Diagram Coast Guard Drawing 618 WMEC 252-004, Rev H, Propuln Cntrl & Monitoring Blck & Schem Wiring Diagram Coast Guard Drawing 627 WMEC 252-051, Rev-, Air Treatment System for USCG 210’ Class Cutter (“B” Class) Coast Guard Drawing 618 WMEC 252-051, Rev-, Mathers Control Air Diagram & Components (“A” Class) Coast Guard Drawing 618 WMEC 256-003, Rev B, Seawater Cooling Piping Modifications Incidental to CAT 3306B EDG Installation iv (Rev-1) http://www.assistdocs.com/search/search_basic.cfm http://www.uscg.mil/directives/default.asp http://www.gpoaccess.gov/ http://www.awspubs.com/index.php http://www.techstreet.com/ http://www.nfpa.org/ http://shopping.netsuite.com/sspcmarketplace

Coast Guard Drawing 618 WMEC 259-001, Rev F, Exhaust Piping Coast Guard Drawing 627 WMEC 320-001, Rev AH, 440 & 115 Volt Power One Line Block Wiring Diagram & Miscellaneous Details Coast Guard Drawing 618 WMEC 320-001, Rev T, Major Maint Avail 440/115 Power One Line Wiring Diagram & Details Coast Guard Drawing 618 WMEC 512-003, Rev E , Arrgt of Ventilation Fan & Intake Rooms Coast Guard Drawing 618 WMEC 512-011, Rev J , Arrgt Ventilation & AC Main Deck Coast Guard Drawing 618 WMEC 514-001, Rev F, Diagram: Heating and Chilled Water System Coast Guard Drawing 618 WMEC 514-001, Rev G, Arrgt of Chilled and Hot Wtr Sys Inside Machinery Space Coast Guard Drawing 618 WMEC 514-003, Rev K, Arr. of Chilled and Hot Water System Outside Mach Space Coast Guard Drawing 6 18 WMEC 528-001, Rev L ; Arrangement of Plumbing System and Deck Drains Coast Guard Drawing 618 WMEC 528-004, Rev B; Piping Mods Garbage Macerator Installation Coast Guard Drawing 618 WMEC 528-005, Rev A; Garbage Grinder System Drain Arrangement Coast Guard Drawing 618 WMEC 533-001, Rev J, Diag Hot & Cold Potable Water Coast Guard Drawing 618 WMEC 535-001, Rev J , Diag ram Steam, Feed and Condensate System Piping Coast Guard Drawing 618 WMEC 535-002, Rev J , Arrangement Steam, Feed and Condensate System Piping Coast Guard Drawing 618 WMEC 535-003, Rev A, Steam Pip Mods INCD to Bos’n Stores & Wrkshp Vent Coast Guard Drawing 618 WMEC 535-004, Rev-, Split Pipe Drain Duct for Boiler Overboard Discharge Coast Guard Drawing 618 WMEC 551-002, Rev G, Arrangement of Compressed Air in Mach’y Space Coast Guard Drawing 618 WMEC 561-005, Rev A, Hydraulic Steering Sys Piping Arrgt (Supercedes 2200-3) Coast Guard Drawing 627 WMEC 572-001, Rev C, Details of ER and passageway Trolley Beams Coast Guard Drawing 618 WMEC 581-001, Rev B, Anchor Handling Coast Guard Drawing 618 WMEC 581-006, Rev-, Anchor Windlass Locking Ring Mod Coast Guard Drawing 618 WMEC 581-055, Rev 5, Windlass Capstan Arrangement Coast Guard Drawing FL-588-001, Rev C, Talon Grid Support Skirt Replacement Coast Guard Drawing 618 WMEC 593-001, Rev C, Dia-MSD System Coast Guard Drawing 618 WMEC 593-002, Rev F, Arrgt-MSD System Coast Guard Drawing 618-WMEC 593-50, Gen Arr Marine Sanitations Device Compartment Coast Guard Drawing 618 WMEC 593-053, Rev-, Urinal, Washout Coast Guard Drawing 618 WMEC 593-054, Rev-, Vacuum Interface Valve Outline Coast Guard Drawing 6 18 WMEC 601-002 , Rev B , Inboard Profile Coast Guard Drawing 6 18 WMEC 601-004, Rev K , General Arrangement Main and 01 Deck Coast Guard Drawing 618 WMEC 601-004, Rev J, General Arrangement Main and 01 Deck Coast Guard Drawing 618 WMEC 601-005, Rev G, General Arrangement 02 Deck , Bridge Deck, and House Top Coast Guard Drawing 618 WMEC 612-001, Rev F, Rails, Stanchions and Lifelines Coast Guard Drawing 618 WMEC 612-002, Rev C, Helicopter SAFETY Nets Coast Guard Drawing 618 WMEC 612-004, Rev B, A ft S afety N et M ods 01 L evel S afety N ets Coast Guard Drawing 618 WMEC 612-007, Rev-, Flight Deck Safety Net Replacement Coast Guard Drawing 618 WMEC 612-008, Rev C, NAVSEA Certified Flight Deck Net Installation Coast Guard Drawing 618 WMEC 634-001, Rev G , Deck Coverings Coast Guard Drawing 618 WMEC 651-001, Rev F, Arrangement Crews Galley, Mess and Scullery Coast Guard Drawing FL-8301-002, Rev A, Talon Helo Landing Grid Stanchion Bolt with Locknut NAVSEA Drawing 803-5184097, Rev B, Safety Nets, Deck Edge Grp or Al Frame, Nylon Net v (Rev-1)

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series) , Coatings and Colors Manual Coast Guard Commandant Instruction (COMDTINST) M10360.3C, Change 1, Jun 2006, Coatings and Color Manual Coast Guard Technical Publication (CG TP) 3485A, Nov 2008, Boat Davit, Single Point - Models D5000CT and D5700CT Coast Guard Technical Publication (TP) 2188, June 2010, Steam Heating Boiler – Model 5848-14E Coast Guard Technical Publication (TP) 3368, Feb 2006, Technical Documentation Helicopter Land Grid

TYPE 18-22-01

Coast Guard Technical Publication (TP) 4200, Jan 1991, SWBS 561, Manufacturer's Instruction Book, Electro-Hydraulic Steering System Surface Forces Logistics Center (SFLC) Standard Specification 0000_STD, 2009 Edition, General Requirements Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), Jan 2009, Overhaul AC Electrical Motors In-Shop Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), Jan 2009, Shipboard Electric Cable Test Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), Jan 2009, Shipboard Electrical Cable Removal, Relocation, Splice, Repair and Installation Surface Forces Logistics Center Standard Specification 3141 (SFLC Std Spec 3141), Jan 2009, Overhaul Electrical Rotating Machines Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), Jan 2009, Auxiliary Machine Systems Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), Jan 2009, Inspect, Repair, and Test Auxiliary Machine Systems Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), Jan 2009, Install New Deck Covering Systems Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), Jan 2009, Provide Temporary Services Coast Guard Technical Publication (TP) 3231B, SWBS 252, Feb 2010, Propulsion Pneumatic Control System (210 WMEC “A” and “B” Class) Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), Jan 2009, Temporary Hull

Accesses Coast Guard Technical Publication (TP) 2188, Jun 2010, Steam Heating Boiler - Model 5848-14E

OTHER REFERENCES

American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2002, Disinfection of Water-Storage Facilities American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and Welding End ASTM International (ASTM) A36, 2008, Standard Specification for Carbon Structural Steel ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets ASTM International (ASTM) D4417, 2003, Standard Test Methods for Field Measurement of Surface Profile of Blast Cleaned Steel vi (Rev-1)

ASTM International (ASTM) D5363, 2003, Standard Specification for Anaerobic Single Component Adhesives ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates Code of Federal Regulations (CFR) Title 29, Part 1915, Jul 2008, Occupational Safety and Health Standards for Shipyard Employment Code of Federal Regulations (CFR) Title 33 CFR, 2008, Navigation and Navigable Waters Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety Administration, Department Of Transportation Commercial Item Description (CID) A-A-59316, Nov 2003, Abrasive Materials for Blasting Commercial Item Description (CID) A-A-59588, Jul 2005, Rubber Silicone DOD-STD-2187, Aug 1987, Chemical Cleaning of Salt Water Piping Systems Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2003 Edition, Pressure Testing Of Steel Valves Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2002 Edition, Butterfly Valves Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-69, 2003, Pipe Hangers and Supports - Selection and Application Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 1999 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2008 Edition, Bronze Gate, Globe, Angle and Check Valves Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-89, 2003, Pipe Hangers and Supports – Fabrication and Installation Practices MIL-A-22262, Mar 1996, Abrasive Blasting Media Ship Hull Blast Cleaning MIL-PRF-16173, 2006, Corrosion Prevention Compound, Solvent Cutback, Cold-Application MIL-STD-419 D, Jul 1987, Cleaning , Protecting , and Testing Piping, Tubing, and Fittings for Hydraulic Power Transmission Equipment MIL-STD-419 D, Jul 1987, Cleaning, Protecting, and Testing Piping, Tubing, and Fittings for Hydraulic Power Transmission Equipment NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), May 1997, Requirements for Fabrication, Welding, and Inspection of Submarine Structure Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), Jan 2009, Install New Deck Covering Systems The Society for Protective Coatings (SSPC) VIS 1, 2004, Guide and Reference Photographs for Steel Surfaces Prepared by Dry Abrasive Blast Cleaning vii (Rev-1) viii (Rev-1)

Consolidated List of Government-furnished Property The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK

ITEM

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

4 N M16 Bolts NSN: 5305-01-393-1827 24 ea. 25.65 4 N M12 Bolts NSN: 5305-01-584-6095 12 ea. 33.75 4 N **Talon Grid

Stanchion Bolt Assembly, Including Locking Nut

NSN: 5340-01-481-3786 25 ea. 96.30

4 N SS (316) Lock Nuts NSN 5310-01-598-3243 127 ea 3.52

26 N Hankison Refrigerated Control Air Dryer

HPR35 1 ea. 1,095.00

26 N Filter, Coalescing (1 micron)

HF7-16-4-PL 1 ea. 176.00

26 N Hankison Replacement Filter

E716 1 ea 37.00

26 N Filter, Oil Removal HF5-16-4-PL 1ea 180.00

26 N Hankison Replacement Filter

E516 1 ea 46.00

26 N **Valve, Regulating

R74G-4AT-RSN

4820-01-205-9362

2 ea. 69.02

26 N **Valve, Ball 4820-01-243-9951 4 ea. 6.91

27 N Way-Wolff Boiler Model No. 5848-14E

NSN: 4410-01-182-1910

2 ea. 15,000.00

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter

Consolidated List of Critical Inspection Items The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000_STD, paragraph

3.2.6.5 (Inspection report particulars)):

Work Item Title 3 Single Point Davit, Level 1 Inspect and Test 4 Helo Talon Grids, Inspect and Test 16 Heat Exchangers, Clean, Inspect and Hydro ix (Rev-1)

PC_210A_WMEC_0909

Principal Characteristics

210' WMEC (A Class)

PHYSICAL CHARACTERISTICS

Length Overall 210' 6" Length, Design Waterline 200' 0" Depth (main deck at side to baseline) 19' 6" Maximum Beam 34' 0" Height of Highest Projection 88' 0" Full Load Draft 4,000 lbs Height of FM Antenna Above Baseline 90' 0" Light Ship Displacement 875 long tons Full Load Displacement 1100 long tons Shore Tie Voltage Requirements 400A / 440V Frame Spacing 1' 0"

MACHINERY CHARACTERISTICS

Main Propulsion 2 Alco Model 251B Diesel Engines, 5,000 BHP total

Ship's Service Generators 2 Caterpillar Model 3406B Diesel-driven SR4. 250 KW each @ 0.8 power factor, 440V AV, 3 phase, 60 cycle

Emergency Generator Caterpillar Model D3306B Diesel-Driven. Century Synchronous Model, ACR-507, 100KW

Number of Propellers 2 Number of Blades 4 Diameter 7' 6" Pitch Controllable Shaft RPM 300 Shaft Diameter 8.25"

TANK CAPACITIES

Diesel Fuel (95%) 48,375 gal Fresh Water (95%) 11, 108 gal JP-5 Fuel (95%) 4,697 gal Lube Oil (95%) 1,942 gal x (Rev-1)

This page was left blank intentionally. Do not delete.

xi (Rev-1)

00000_PWB_0811_FLT

REC_0000_FLT_ Commercial Project @ CG Facility (0211)

General Requirements

1. SCOPE

1.1 Intent. This item describes the general requirements to be followed by the Contractor while conducting this availability.

2. REFERENCES

COAST GUARD DRAWINGS

None.

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3C, Change 1, Jun 2006, Coatings and

Color Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General

Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes

OTHER REFERENCES

ASTM International (ASTM) D4417, 2003, Standard Test Methods for Field Measurement of Surface

Profile of Blast Cleaned Steel Commercial Item Description (CID) A-A-59316, Nov 2003, Abrasive Materials for Blasting Code of Federal Regulations (CFR) Title 33 CFR, 2008, Navigation and Navigable Waters Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety

Administration, Department Of Transportation MIL-A-22262, Mar 1996, Abrasive Blasting Media Ship Hull Blast Cleaning NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), May 1997, Requirements for

Fabrication, Welding, and Inspection of Submarine Structure The Society for Protective Coatings (SSPC) VIS 1, 2004, Guide and Reference Photographs for Steel

Surfaces Prepared by Dry Abrasive Blast Cleaning

3. REQUIREMENTS

3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.

1 (Rev-1)

NOTE

The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and also to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.2 Fire watch requirements. The Contractor shall refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec 0000, in accomplishing the following task:

• Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to four Coast Guard fire watch personnel.

• Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.

3.3 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.

3.4 HW disposal. The Contractor shall be responsible for all hazardous wastes generated by work under this contract. Label and package all hazardous wastes in 49 CFR-approved containers, and in accordance with all other applicable Federal, state, and local laws and regulations. In addition, comply with applicable parts of 40 CFR 262, applicable to handling of hazardous wastes.

3.4.1 Along with the Government, the Contractor shall be contractually considered the co-generator of all hazardous wastes; be aware that the Government will make available its facility’s EPA Generator Identification (ID) Number for manifesting of hazardous wastes.

3.4.2 The Contractor shall identify, arrange, and be responsible for the turnover of all hazardous wastes, within the confines of the Coast Guard shore facility, to the facility’s HM/HW Coordinator. Notify the ship’s HW Coordinator prior to any transfers of HW from ship to shore.

3.4.3 The Contractor shall prepare a manifest of hazardous waste to be reviewed and signed by the HM/HW Coordinator. Contact the HM/HW Coordinator for turnover of any hazardous waste; in addition, notify the COTR in writing 24 hours prior to any waste removals, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).

3.4.4 The Contractor shall be aware of the following:

3.4.4.1 No Contractor or Subcontractor shall have the authority to sign a Hazardous Waste Manifest using the Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast Guard facility without COTR or KO-approval.

3.4.4.2 Local environmental regulations at the Government facilities may be more stringent than in many jurisdictions. As with all environmental regulations, it is the Contractor's responsibility to research, prepare for, and comply with local and state regulations.

3.4.4.3 Coast Guard facilities do not have Facilities Response Plans (see 33 CFR 154 Subpart F). It is the Contractor’s responsibility to furnish the Facility Response Plan (FRP) when required for over-the-water liquids transfers to and from vessels. This requirement is applicable to transfers to/from vessels with an oil/fuel capacity of 250 barrels or more.

2 (Rev-1)

3.5 Pre-surface preparation test coupon. In order to ensure production of required surface profile, the Contractor shall accomplish the following tasks, whenever abrasive-blasting is required in a work item that is deemed a ”critical-coated’ surface:

3.5.1 Coupon material and test set-up particulars.

3.5.1.1 Conduct a performance test on all abrasive blasting operations on a Contractor- provided test coupon, prior to starting abrasive blasting operations on the vessel. Ensure the following:

• The coupon shall be a new metal plate, of the same metal type and material properties as the vessel area to be blasted - steel or aluminum plate, as applicable, and shall have no existing anchor profile - other than the surface irregularities from the manufacturing process.

• The test coupon shall be flat, with nothing welded to the side used for the anchor profile test, no thinner than a 1/8-inch plate and measuring no smaller than 1-foot by 1-foot.

• For steel substrates, the coupon shall have the mill scale intact, and be in a Rust Grade "A" condition, in accordance with SSPC-VIS 1.

• The test coupon shall be affixed so as to not permit excessive movement during the performance test, but shall not be affixed to the vessel.

3.5.1.2 Ensure that the abrasive-blasting operation for the test coupon is conducted with the identical setup and parameters that will be used blasting the designated vessel surfaces – including, but not limited to:

• The abrasive media type and media size selected to achieve the anchor profile range, as specified in the applicable work items.

• Nozzle size and type (straight bore, high velocity nozzle, angle nozzle...).

• Delivery rate and pressure settings.

3.5.1.3 Blast a one-square foot area on one side of the test coupon to the abrasive surface preparation standard specified in the work item, and perform an anchor profile test of the blasted surface in accordance with ASTM D4417, Method B or C. Notify the COTR in advance of the abrasive blasting operation test, to permit the witnessing of the test by the COTR. Submit a CFR documenting the results of the abrasive blasting operation test. The CFR shall include at a minimum, the following:

• Area of the vessel for which the verified setup will be used to abrasive blast.

• The selected abrasive media type and size.

• The nozzle size and type.

• The delivery rate and pressure.

• The test coupon starting properties (material type and surface conditions).

3 (Rev-1)

• The resultant anchor profile readings from the test (a minimum of 3 locations, separated by a minimum of 2 inches shall be recorded).

NOTES

1. A performance test of the abrasive blasting operations on a test coupon and measuring the resultant anchor profile prior to performing the abrasive blasting operation on the cutter is required. The test coupon will be used to evaluate the anchor profile produced by the equipment setup and selected abrasive media.

2. The reverse side of the test coupon may be used for the subsequent test, provided that the conditions in paragraph 3.5.1 (Coupon material and test set-up particulars) are met.

3. Ultra high pressure water jetting does not create an anchor profile and is exempt from the anchor profile test coupon check.

3.5.1.4 Repeat the abrasive blasting operation test in the following instances:

• The equipment setup, that was evaluated during the test coupon abrasive blasting performance test in paragraph 3.5.1 (Coupon material and test set-up particulars), has changed.

• The resultant anchor profile readings observed on the vessel are outside the specified anchor profile range.

• Media is changed from MIL-A-22262 to CID A-A-59316 or vice versa.

• The supplier of the abrasive blasting media changes, regardless if the new source for the media has the same specifications.

• When Directed by the COTR.

CAUTION!

Ensure that blast media from the performance test does not strike the vessel during the test.

3.6 Interim changes to SFLC Std Spec 0000. The Contractor shall be aware of the following interim changes to the SFLC Std Spec 0000:

3.6.1 Contents of paragraph 3.3.2.1.1 (Water depth) have been revised to read as follows:

“3.3.2.1.1 Water depth. Ensure that water depth is sufficient at the pier to allow the vessel's lowest underwater appendage to clear the bottom by at least two feet at:

• Ordinary low water mark on non-tidal rivers.

• At all tide conditions predicted during the availability for tidal rivers and other navigable waterways (Bay, Lake, etc.).”

3.6.2 Paragraph 3.2.11.1 (Sanitary facilities for vessel-personnel – due to disruption of grey water system) has been revised as follows:

“3.2.11.1 Sanitary facilities for vessel-personnel – due to disruption of grey water and sewage systems.

4 (Rev-1)

When the shipboard grey water and sewage systems are disrupted due to repairs required by contract work, the Contractor shall provide vessel-personnel with a sanitary facility, within a five minute walking distance from the vessel, to include the amenities listed in Table II (Sanitary Facility Amenities). Ensure the following:

• Shower stalls are equipped with privacy screens.

• Sinks are provided with fresh hot and cold water.

• Electrical convenience GFI receptacles, in accordance with NFPA 70, National Electric Code (NEC), are located in vicinity of sinks.

• Toilets have doors or privacy dividers.

• Lockers are capable of being locked.”

4. NOTES

4.1 Access to COMDTINST M10360.3. The COMDTINST M10360.3 may be accessed at the following URL address: http://www.uscg.mil/directives/cim.asp

4.2 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 0000 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

5 (Rev-1) http://www.uscg.mil/directives/cim.asp

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

Vessel Name Hull # Work Item # Work Item Title

Location of Work (incl. frame #’s) Area (sqft)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with COMDTINST M10360.3, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-based coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down

(maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-12, SP-11, SP-10…).

Verify surface anchor profile using ASTM D4417-Methods B or C against COMDTINST M10360.3. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max.

threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

Name of QP-1/NACE Inspector Signature Cert. # Date / Time

6 (Rev-1)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE &

TIME

ACTIVITY (Surface preparation, primer coat, barrier coat, top coat, etc…)

LOCATION

(Frame &

Deck, relation to equipment, etc.)

TEMPERATURE % REL.

HUMID-

ITY DEW PT. SURFACE AMBIENT ΔT

| DP - Surface |

7 (Rev-1)

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

Location of Work (Frame References) Area (sqft)

SURFACE PREPARATION METHOD PROFILE ACHIEVED (mils) Min Max Mean

SSPC-SP-10/NACE No. 2 SSPC-SP-12/NACE No. 5

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

Abrasive Manufacturer and Sieve Size: _________________________________ Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils

Place Surface Profile Replica Tape Here

Reading:__________ mils Mean Mil Reading (IAW ASTM D4417-Method C) for above 15 readings: ______________

8 (Rev-1)

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

SURFACE PREPARATION METHOD PROFILE ACHIEVED (mils) Min Max Mean

SSPC-SP-10/NACE No. 2 SSPC-SP-12/NACE No. 5

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

Abrasive Manufacturer and Sieve Size: _________________________________ Record measurements taken in the spaces provided below, to serve as permanent QA record. Maintain separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Reading: _____ mils _____ mils _____ mils _____ mils _____ mils

Reading: _____ mils _____ mils _____ mils _____ mils _____ mils

Reading: _____ mils _____ mils _____ mils _____ mils _____ mils

Reading: _____ mils _____ mils _____ mils _____ mils _____ mils

Reading: _____ mils _____ mils _____ mils _____ mils _____ mils

Reading: _____ mils _____ mils _____ mils _____ mils _____ mils

Reading: _____ mils _____ mils _____ mils _____ mils _____ mils

Reading: _____ mils _____ mils _____ mils _____ mils _____ mils

Reading: _____ mils _____ mils _____ mils _____ mils _____ mils

Reading: _____ mils _____ mils _____ mils _____ mils _____ mils Mean Mil Reading (IAW ASTM D4417-Method B) for above 10 readings (by column):

_____ mils _____ mils _____ mils _____ mils _____ mils

9 (Rev-1)

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15

DATE TEST LOCATIONS CONDUCTIVITY

(microsiemens/cm)

10 (Rev-1)

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

Coating Mfg Product Name Batch # Induction Time

Coating System Sequence (Primer/Touchup/3rd Coat, etc.)

DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2

SPOT 1 2 3 4 5 AVERAGE

VALUE

*BASE METAL

READING (BMR)

*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.

Location (Frame Reference): ___________________

SPOT 1 2 3 4 5

Overall Avg. DFT

ADJUSTMENTS

1 Avg. BMR Deviation 3 Before

Adjustments After Adjustments

Avg.

Location (Frame Reference): ___________________

SPOT 1 2 3 4 5

Overall Avg. DFT

ADJUSTMENTS

1 Avg. BMR Deviation 3 Before

Adjustments After Adjustments

Avg.

Location (Frame Reference): ___________________

SPOT 1 2 3 4 5

Overall Avg. DFT

ADJUSTMENTS

1 Avg. BMR Deviation 3 Before

Adjustments After Adjustments

Avg.

Application Method (Airless, Conventional Spray, Rolled) Average DFT

11 (Rev-1)

12 (Rev-1)

51490_JMS_0211_210_270

REC_51490_201_270_210’ WMEC ‘A’ Class (ALL) (0510)

WORK ITEM 1: Chill Water System, General Maintenance

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean and flush the Chill Water and Heat System.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 618 WMEC 514-001, Rev F, Diagram: Heating and Chilled Water System Coast Guard Drawing 618 WMEC 514-001, Rev G, Arrgt of Chilled and Hot Water System Inside

Machinery Space Coast Guard Drawing 618 WMEC 514-003, Rev K, Arr. of Chilled and Hot Water System Outside of

Machinery Space

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General

Requirements

OTHER REFERENCES

None.

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Technical Representative.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install suitable covering to seal off and protect all non-affected surfaces/equipment and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, remove protective material and inspect for the presence of contamination. Clean all equipment and spaces, contaminated due to improper protection, to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the below-listed. Handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences):

• Piping and hoses.

• Bulkheads.

• Deck plating and associated framing.

• Electrical cables.

• Thermal insulation.

NOTE

The Contractor shall provide temporary cooling for CIC, Radio, IC Gyro, and ECC.

3.2 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of the Chill Water and Heat System, to demonstrate existing operational condition. Submit a CFR.

3.3 System draining. The Contractor shall drain all existing fluid from the Chill Water and Heat System. Dispose of removed fluids in accordance with all Federal, state, and local regulations.

3.4 Coil unit line-up. Prior to commencement of system flushing, the Contractor shall ensure that all fan coil units are lined-up to the system, with the assistance of the Coast Guard Inspector.

3.5 Cleaning plan. The Contractor shall establish a plan for cleaning the Chill Water and Heat Piping System, as shown on Coast Guard Drawings 618 WMEC 514-001, 618 WMEC 514-001, and 618 WMEC 514-003, listing the step by step procedures necessary to ensure that all foreign debris is removed from the piping system.

3.5.1 Procedure requirements. Ensure that the procedure includes the following:

• Methods of cleaning.

• All safety precautions required during cleaning operations.

• List of qualified personnel who will operate machinery or handle chemicals.

• Locations in the chill water piping where cleaning will take place, and any additional fittings necessary.

• Sequence of each location that ensures all piping sections will be cleaned and all foreign debris removed.

13 (Rev-1)

3.5.2 Plan submittal. Submit the written plan to the COTR for approval at least 48 hours prior to commencing cleaning operations. Contractor shall submit CFR within 40% of start.

3.6 Flushing operations. Upon approval of the plan, the Contractor shall proceed with the flushing of the piping system, as follows:

3.6.1 Clean all system strainers and valves.

3.6.2 Flush all chill/hot water piping with a system manufacturer recommended flushing fluid until all debris is removed. Ensure that flushing fluid is directed to move scale and foreign debris away from installed machinery to prevent possible damage upon operational testing. Submit a CFR documenting date and time of flushing process, and verification of piping and FCU cleanliness.

3.6.3 Dispose of flushing fluid in accordance with all applicable Federal, state, and local regulations.

WARNING!

Do not drain ANY Fluids (including fresh water) into any space, bilge, or exterior location.

3.7 System refilling. Upon completion of all cleaning and flushing operations, the Contractor shall refill the system with suitable fresh water.

3.8 Flushing media requirements. The Contractor shall ensure that the cleaning and flushing media does not cause any damage to the Chill Water and Heat System.

3.9 Operational test – post repairs. After completion of work, the Contractor shall witness an operational test (by Coast Guard personnel) of the Chill Water and Heat System to prove satisfactory operating condition. Submit a

CFR.

4. NOTES

This section is not applicable to this work item.

14 (Rev-1)

15 (Rev-1)

56110_0510_FLT

REC_56110_FLT_210’ WMEC ‘A’ Class (ALL) (0709)

WORK ITEM 2: Steering Gear (General), Overhaul

1.1 Intent. This work item describes the requirements for the Contractor to overhaul the steering gear assembly.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 618-WMEC 561-005, Rev A, Hydraulic Steering Sys Piping Arrgt (Supercedes

2200-3)

COAST GUARD PUBLICATIONS

Coast Guard Technical Publication (TP) 4200, Jan 1991, SWBS 561, Manufacturer's Instruction Book, Electro-Hydraulic Steering System Surface Forces Logistics Center Standard Specification 3141 (SFLC Std Spec 3141), Jan 2009, Overhaul

Electrical Rotating Machines Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), Jan 2009, Auxiliary

Machine Systems

OTHER REFERENCES

MIL-STD-419 D, Jul 1987, Cleaning, Protecting, and Testing Piping, Tubing, and Fittings for Hydraulic

Power Transmission Equipment

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.3 Protective measures - hydraulic system. The Contractor shall maintain existing hydraulic system cleanliness; take all necessary precautions to prevent the introduction of contaminants into the hydraulic system.

Whenever disconnecting or removing components from the hydraulic system, completely seal all openings to the rest of the system, immediately, using either caps (for externally threaded connection points), bolt-on blanks, or taped-on discs/covers (durable plastic or sheet-metal no less than 1/16-inch thick).

NOTE

Plastic bags may be used only when arrangement or configuration prevents the use of the other sealing methods specified above.

3.1.4 Interferences.

None.

3.2 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of the steering system, to demonstrate existing operational condition. Submit a

CFR.

3.2.1 Run the rudders hard over to hard over and record the time. If a pressure gauge is installed, the record the pressure at hard over.

3.2.2 Use an ammeter to record the amperage at startup and at three different positions – hard over, amidships, and hard over.

3.2.3 Submit a list of readings to the Coast Guard Inspector of the pump and motor units, measuring discharge pressure, flow and motor current draw.

3.3 Removal. The Contractor shall drain the hydraulic fluid (approximately 150 gallons) to a suitable container and dispose of in accordance with Federal, state and local regulations.

3.4 Disassembly. The Contractor shall remove/disassemble the steering system assembly to the extent necessary to accomplish overhaul procedures.

3.5 Overhaul. The Contractor shall remove, clean, inspect and reinstall the steering system components as shown on Coast Guard Drawing 618-WMEC 561-005, and in accordance with TP 4200 and MIL-STD-419.

3.5.1 Couplings. Remove, clean, inspect and reinstall the couplings as shown on Coast Guard Drawing 618- WMEC 561-005, and in accordance with TP 4200. Renew all O-rings and seals.

3.5.2 Pumps. Remove, disassemble, clean, inspect, reassemble, and reinstall pump assemblies in accordance with TP 4200. Clean and visually inspect all disassembled components for wear and deterioration. Renew the bearings, shafts seals, springs and gaskets.

3.5.3 Electric motors. Remove both pump motors to a suitable repair facility for overhaul in accordance with TP 4200. Completely disassemble, overhaul, test, and reassemble the motors in accordance with SFLC Std Spec 3141. Renew the bearings and lubricate in accordance with manufacturers instructions.

3.5.4 Hydraulic power unit components. Remove, disassemble, clean, inspect, reassemble and reinstall the following components with new gaskets, seals and O-rings:

• Directional Control valves.

16 (Rev-1)

• Flow Control valves.

• Check valves.

• Relief valves.

• Level & Temp switch assemblies.

• Divert/Unloading valves.

• Pressure switches.

3.5.5 Filters, strainers and magnetic plugs. Renew all hydraulic power unit filters and clean all strainers and magnetic plugs in accordance with TP 4200.

3.5.6 Hydraulic cylinders. Remove, disassemble, clean, inspect, reassemble, and reinstall both hydraulic cylinders in accordance with TP 4200. Visually inspect all the components for wear and deterioration. Remove all burrs, nicks and scratches with emery cloth. Reassemble with new gaskets, seals and O-rings.

3.5.7 Hydraulic hose renewal. Renew the hydraulic hose assemblies in accordance with SFLC Std Spec 5000, Appendix C, Paragraph C2.2 (Hose assemblies).

3.5.8 Hydraulic reservoir cleaning. Clean the hydraulic reservoirs with a lint-free cloth to remove all foreign debris.

3.5.9 Report. Submit CFR of all findings.

3.6 System restoration. The Contractor shall reinstall all removed components of the steering system back to their original configuration as shown on Coast Guard Drawing 618-WMEC 561-005, and in accordance with TP 4200. Properly lubricate the system in accordance with TP 4200.

3.7 Hydraulic fluid renewal. The Contractor shall renew the system hydraulic fluid in accordance with TP 4200 and SFLC Std Spec 5000, Appendix C, Paragraph C2.1 (Fluids).

3.8 Hydraulic fluid filtering. The Contractor shall filter the system hydraulic fluid in accordance with SFLC Std Spec 5000, Appendix C, Paragraph C2.1 (Fluids).

3.9 Alignment. The Contractor shall accomplish alignment procedures for the steering system in accordance with TP 4200.

3.10 Operational test – post repairs. After completion of work, the Contractor shall witness an operational test (by Coast Guard personnel) of the steering system to prove satisfactory operating condition. Record the time from hard over to hard over with one and two pumps. With a single pump on line it should be 16 seconds or less;

with two pumps, it should be 8 seconds or less. Submit a CFR.

4. NOTES

17 (Rev-1)

18 (Rev-1)

58310_JLW_0311_FLT

REC_58310_FLT_210’ WMEC ‘A’ Class (ALL) (0309)

WORK ITEM 3: Single Point Davit, Level 1 Inspect and Test

1.1 Intent. This work item describes the requirements for the Contractor to conduct Level 1 Inspect and Test of the Single Point Davit.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

None.

COAST GUARD PUBLICATIONS

Coast Guard Technical Publication (CG TP) 3485A, Nov 2008, Boat Davit, Single Point - Models

D5000CT and D5700CT Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), Jan 2009, Auxiliary

Machine Systems

OTHER REFERENCES

None.

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph:

• 3.2 (Level 1 inspect and test task particulars – task #1).

3.1.2 Reference documents. The Contractor shall use CG TP 3485A for guidance. Perform all work in accordance with SFLC Std Spec 5000.

3.2 Level 1 inspect and test task particulars.

ADDITION REQUIREMENTS

# TASK

TYPE

QTY COMPONENT

OR ASSEMBLY

APPENDIX

AND PARA.

FROM

5000_STD

OTHER

1 Operate and Inspect

1 SPD Davit 3.2.1 Submit (CIR).

2 Groom and Lubricate

1 SPD Davit 3.2.6 Perform all maintenance specified in Chapter 4 of TP-3632.

3 Final Operational And/Or Weight Test

1 SPD Davit B2.7 After completion of all other work, perform the operational and weight testing for this system. Main Hoist test weights are as follows:

Static: 7500 (+375, -0) lbs Dynamic: 6250 (+313, -0) lbs Rated: 5000 (+0, -250) lbs Submit a CFR.

4 Fabricate and Install

1 Label plate B2.9

3.3 Special requirements for various components. If a Change Request has been authorized for additional work on any of the components listed in Table 1 below, the Contractor shall refer to the corresponding Appendix or paragraph of SFLC Std Spec 5000, as applicable.

TABLE 1 – SPECIAL REQUIREMENTS

COMPONENT

APPENDIX &

PARAGRAPH IN SFLC

STD SPEC 5000

Fluids C2.1 Hose assemblies…

This is the start of the file's text. The full file is on GovTribe.