SPECIFICATIONS FOR USCGC STEADFAST (WMEC-623) 210 FOOT B CLASS CUTTER DOCKSIDE REPAIRS
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PUBLICATIONS-STEADFAST.zip | ZIP file | |
| STEADFAST DRAWINGS.zip | ZIP file | |
| Solicitation-Steadfast.pdf | ||
| Past Performance Questionnaire.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC STEADFAST (WMEC 623)
210 FOOT "B CLASS" MEDIUM ENDURANCE CUTTER
SPECIFICATION FOR DOCKSIDE REPAIRS
Developed By: LT J. Carter
(Rev-0, 9 Sept 2011)
USCGC STEADFAST (WMEC-210B) DOCKSIDE AVAILABILITY 2012
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record ....................................................................................................................................... iii
Consolidated List of References ................................................................................................................ iv Consolidated List of Government-furnished Property .............................................................................. vii Consolidated List of Critical Inspection Items ........................................................................................ viii Principal Characteristics ............................................................................................................................ ix WORK ITEM 1: Main Diesel Engine’s (MDE’s), Stack Uptakes, Commercially Clean
WORK ITEM 2: SSDGs and EDG Exhaust Piping, Commercially Clean WORK ITEM 3: Boiler, Exhaust Uptakes, Commercially Clean WORK ITEM 4: Vent Ducts (Engine and Motor Room, All) Commercially Clean
WORK ITEM 5: Vent Ducts (Galley and Pantry Room, All) Commercially Clean WORK ITEM 6: Vent Ducts (Laundry Exhaust) Commercially Clean WORK ITEM 7: Compressed Air Receivers, Clean, Inspect and Test
WORK ITEM 8: Anchors, Anchor Chains and Ground Tackle, Inspect, Repair and Preserve (CIR) WORK ITEM 9: Warping Capstan, Level 2, Inspect and Repair (CIR)
WORK ITEM 10: Single Point Davit, Level 1, Inspect and Test (CIR) WORK ITEM 11: Deck Fittings, Inspect WORK ITEM 12: Electrical Wiring, Air conditioning(A/C), Upgrade (TCTO)
WORK ITEM 13: Control Air Dryer, Upgrade (TCTO) WORK ITEM 14: Weight Handling Gear, Inspect and Test (CIR)
WORK ITEM 15: Anchor Windless(s) Level 2, Inspect and Repair (CIR) .…………………...…...…..55
WORK ITEM 16: Chain Locker(s), Inspect (CIR)
WORK ITEM 17: Chain Locker(s), Preserve Partial (Option Item).……………………………………60 iii (Rev-0)
Revisions Record
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-0)
Consolidated List of References
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.
All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free or charge. Other Government documents may be accessed – free of charge – as follows:
MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm
Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp
Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws::
www.gpoaccess.gov
The Government is aware of the following internet web links where contractors may procure commercial specifications:
American Welding Society (AWS): http://www.awspubs.com/index.php
ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/
NFPA: http://www.nfpa.org
SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace
COAST GUARD DRAWINGS
Coast Guard Drawing FL 2605-031, Rev D, Mechanical Chain Stopper, 1-7/8" Buoy Chain
Coast Guard Drawing 6 27 WMEC 252-051, Rev- , Air Treatment Sys USCG 210’ Class Cutter (“B” Class)
Coast Guard Drawing 618 WMEC 252 -001, Rev M, Control Air Arrangement (“A” Class)
Coast Guard Drawing 618 WMEC 252-051 , Rev-, Mathers Control Air Diagram & Components (“A” Class)
Coast Guard Drawing 618 WMEC 320-057 , Rev B , Carrier A/C Plant Controller Upgrade (A & B Class applicable)
Coast Guard Drawing 627 WMEC 252-001, Rev F , Control Air Piping Arrangement (“B” Class)
Coast Guard Drawing 627 WMEC 252-001, Rev F, Control Air Piping Arrangement
Coast Guard Drawing 627 WMEC 259-001, Rev D, Arrangement Exhaust Piping
Coast Guard Drawing 627 WMEC 512-006, Rev D, Ventilation Diagram – Second Deck
Coast Guard Drawing 627 WMEC 512-007, Rev D, Ventilation Diagram – Main Deck
Coast Guard Drawing 627 WMEC 512-008, Rev D, Ventilation Diagram – 01 Deck & Abv
Coast Guard Drawing 627 WMEC 512-020, Rev -, Arrangement Vent and AC 02 Level
Coast Guard Drawing 627 WMEC 512-021, Rev -, Arrangement Vent and AC 01 Level
Coast Guard Drawing 627 WMEC 512-026, Rev -, Arrangement Vent and AC Main Deck
Coast Guard Drawing 627 WMEC 512-029, Rev -, Arrangement Vent and AC 2nd Deck
Coast Guard Drawing 627 WMEC 512-030, Rev -, Arrangement Vent and AC 3rd Deck
Coast Guard Drawing 627 WMEC 551-002, Rev D, Arrangement of Compressed Air in Machinery Space
Coast Guard Drawing 627 WMEC 581-001, Rev-, Anchor Handling
Coast Guard Drawing FL 2605-037, Rev A -, Mechanical Chain Stopper Reinstallation
COAST GUARD PUBLICATIONS
http://www.assistdocs.com/search/search_basic.cfm http://www.uscg.mil/directives/default.asp http://www.gpoaccess.gov/ http://www.awspubs.com/index.php http://www.techstreet.com/ http://www.nfpa.org/ http://shopping.netsuite.com/sspcmarketplace v (Rev-0)
Coast Guard Commandant Instruction (COMDTINST) M10360.3C, Change 1, Jun 2006, Coatings and Color
Manual
Coast Guard Commandants Instruction (CONDTINST) M9000.6F, Naval Engineering Manual
Coast Guard Technical Publication (CG TP) 3485A, Nov 2008, Boat Davit, Single Point - Models D5000CT and D5700CT
Coast Guard Technical Publication (TP)
Coast Guard Technical Publication (TP) 3231B , SWBS 252 , Feb 2010 , Propulsion Pneumatic Control
System (2 1 0 WMEC “ A ” and “B” Class)
Coast Guard Technical Publication (TP) 3965 , May 2011 , Air Conditioning System, R-134A - Model
90RMC025-D-6-D005/MS1
Surface Forces Logistics Center (SFLC) Standard Specification 0000_STD, 200 9 Edition, General
Requirements
Surface Forces Logistics Center Standard Specification 0 74 0 (SFLC Std Spec 0 74 0 ), Jan 2009, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740 ), Jan 2009, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Jan 2009, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), Jan 2009, Overhaul AC
Electrical Motors In-Shop
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), Jan 2009, Auxiliary
Machine Systems
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), Jan 2009, Inspect, Repair, and Test Auxiliary Machine Systems
Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100 ), Jan 2009, Clean
Shipboard Ventilation Systems
OTHER REFERENCES
ASTM International (ASTM) D4417, 2003, Standard Test Methods for Field Measurement of Surface Profile of Blast Cleaned Steel
ASTM International (ASTM) F683, 2003, Standard Practice for Selection and Application of Thermal
Insulation for Piping and Machinery
ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates
Code of Federal Regulations (CFR) Title 29, Part 1915, Jul 2008, Occupational Safety and Health Standards for Shipyard Employment
Code of Federal Regulations (CFR) Title 33 CFR, 2008, Navigation and Navigable Waters
Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency
Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety
Administration, Department Of Transportation
Commercial Item Description (CID) A-A-59316, Nov 2003, Abrasive Materials for Blasting
Federal Specification (Fed Spec) RR-C-271, Nov 1995, Chain and Attachments, Welded and Weldless
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-69, 2003, Pipe Hangers and Supports - Selection and Application
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-89, 2003 , Pipe Hangers and Supports – Fabrication and Installation Practices
MIL-A-22262, Mar 1996, Abrasive Blasting Media Ship Hull Blast Cleaning
MIL-C-24633 , Apr 1998 , Chain, Stud Link, Anchor, Low Alloy Steel, Flash Butt Welded vi (Rev-0)
MIL-DTL-23549, Feb 2007 , Grease, General Purpose
NOTE TO USER : In all of this spec, modify as required for the availability. Please provide any additions to the SME for incorporation into the REC file.
NAVSEA Drawing 804-5773931, Rev A, Acoustic & Thermal Insulation For Compartments Installation
Details
NAVSEA Drawing 804-5959214, Rev-, Piping Insulation - Installation Details
The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2004, Solvent Cleaning
The Society for Protective Coatings (SSPC) VIS 1, 2004, Guide and Reference Photographs for Steel Surfaces
Prepared by Dry Abrasive Blast Cleaning vii (Rev-0)
Consolidated List of Government-furnished Property
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
13 N Hankison Refrigerated
Control Air Dryer HPR35 1 ea. 1,095.00
13 N Filter, Air Line 4330-01-495-4256/4ZL49 2 ea. 70.00 viii (Rev-0)
Consolidated List of Critical Inspection Items
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000_STD, paragraph
3.2.6.5 (Inspection report particulars)):
Work
Item Title 8 Anchor Chain (s) and Ground Tackle, Inspect and Repair
9 Warping Capstan , Level 2 Inspect and Repair
10 Single Point Davit , Level 1 Inspect and Test
Weight Handling Gear
Anchor Windless(s), Level 2 Inspect and Repair
16 Chain Lockers, Inspect ix (Rev-0)
PC_210B_WMEC_0909
Principal Characteristics
210' WMEC (B-Class)
PHYSICAL CHARACTERISTICS
Length Overall 210' 6" Length, Design Waterline 200' 0" Depth (main deck at side to baseline) 19' 6" Maximum Beam 34' 0" Height of Highest Projection 88' 0" Full Load Draft 4,000 lbs Height of FM Antenna Above Baseline 90' 0" Light Ship Displacement 875 long tons Full Load Displacement 1100 long tons Shore Tie Voltage Requirements 400A / 440V Frame Spacing 1' 0"
MACHINERY CHARACTERISTICS
Main Propulsion 2 Alco Model 251B Diesel Engines, 5,000 BHP total
Ship's Service Generators 2 Caterpillar Model 3406B Diesel-driven SR4. 250
KW each @ 0.8 power factor, 440V AV, 3 phase, 60 cycle
Emergency Generator Caterpillar Model D3306 Diesel-Driven. Century
Synchronous Model, ACR-507, 100KW
Number of Propellers 2 Number of Blades 4 Diameter 7' 6" Pitch Controllable Shaft RPM 300 Shaft Diameter 8.25"
TANK CAPACITIES
Diesel Fuel (95%) 48,375 gal Fresh Water (95%) 11, 108 gal JP-5 Fuel (95%) 4,697 gal Lube Oil (95%) 1,942 gal
1 (Rev-0)
00000_PWB_0211_FLT
REC_0000_FLT_ Commercial Project @ CG Facility (0211)
General Requirements
1. SCOPE
1.1 Intent. This item describes the general requirements to be followed by the Contractor while conducting this availability.
2. REFERENCES
COAST GUARD DRAWINGS
None.
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3C, Change 1, Jun 2006, Coatings and
Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes
OTHER REFERENCES
ASTM International (ASTM) D4417, 2003, Standard Test Methods for Field Measurement of Surface
Profile of Blast Cleaned Steel
Commercial Item Description (CID) A-A-59316, Nov 2003, Abrasive Materials for Blasting
Code of Federal Regulations (CFR) Title 33 CFR, 2008, Navigation and Navigable Waters
Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency
Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety
Administration, Department Of Transportation
MIL-A-22262, Mar 1996, Abrasive Blasting Media Ship Hull Blast Cleaning
The Society for Protective Coatings (SSPC) VIS 1, 2004, Guide and Reference Photographs for Steel
Surfaces Prepared by Dry Abrasive Blast Cleaning
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.
NOTE
2 (Rev-0)
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and also to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.2 Fire watch requirements. The Contractor shall refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec
0000, in accomplishing the following task:
Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two
Coast Guard fire watch personnel.
3.3 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.
3.4 HW disposal. The Contractor shall be responsible for all hazardous wastes generated by work under this contract. Label and package all hazardous wastes in 49 CFR-approved containers, and in accordance with all other applicable Federal, state, and local laws and regulations. In addition, comply with applicable parts of 40
CFR 262, applicable to handling of hazardous wastes.
3.4.1 Along with the Government, the Contractor shall be contractually considered the co-generator of all hazardous wastes; be aware that the Government will make available its facility’s EPA Generator Identification
(ID) Number for manifesting of hazardous wastes.
3.4.2 The Contractor shall identify, arrange, and be responsible for the turnover of all hazardous wastes, within the confines of the Coast Guard shore facility, to the facility’s HM/HW Coordinator. Notify the ship’s HW
Coordinator prior to any transfers of HW from ship to shore.
3.4.3 The Contractor shall prepare a manifest of hazardous waste to be reviewed and signed by the HM/HW
Coordinator. Contact the HM/HW Coordinator for turnover of any hazardous waste; in addition, notify the
COTR in writing 24 hours prior to any waste removals, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).
3.4.4 The Contractor shall be aware of the following:
3.4.4.1 No Contractor or Subcontractor shall have the authority to sign a Hazardous Waste Manifest using the
Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast
Guard facility without COTR or KO-approval.
3.4.4.2 Local environmental regulations at the Government facilities may be more stringent than in many jurisdictions. As with all environmental regulations, it is the Contractor's responsibility to research, prepare for, and comply with local and state regulations.
3.4.4.3 Coast Guard facilities do not have Facilities Response Plans (see 33 CFR 154 Subpart F). It is the
Contractor’s responsibility to furnish the Facility Response Plan (FRP) when required for over-the-water liquids transfers to and from vessels. This requirement is applicable to transfers to/from vessels with an oil/fuel capacity of 250 barrels or more.
3.5 Pre-surface preparation test coupon. In order to ensure production of required surface profile, the Contractor shall accomplish the following tasks, whenever abrasive-blasting is required in a work item that is deemed a
”critical-coated’ surface:
3 (Rev-0)
3.5.1 Coupon material and test set-up particulars.
3.5.1.1 Conduct a performance test on all abrasive blasting operations on a Contractor- provided test coupon, prior to starting abrasive blasting operations on the vessel. Ensure the following:
The coupon shall be a new metal plate, of the same metal type and material properties as the vessel area to be blasted - steel or aluminum plate, as applicable, and shall have no existing anchor profile - other than the surface irregularities from the manufacturing process.
The test coupon shall be flat, with nothing welded to the side used for the anchor profile test, no thinner than a 1/8-inch plate and measuring no smaller than 1-foot by 1-foot.
For steel substrates, the coupon shall have the mill scale intact, and be in a Rust Grade "A" condition, in accordance with SSPC-VIS 1.
The test coupon shall be affixed so as to not permit excessive movement during the performance test, but shall not be affixed to the vessel.
3.5.1.2 Ensure that the abrasive-blasting operation for the test coupon is conducted with the identical setup and parameters that will be used blasting the designated vessel surfaces – including, but not limited to:
The abrasive media type and media size selected to achieve the anchor profile range, as specified in the applicable work items.
Nozzle size and type (straight bore, high velocity nozzle, angle nozzle...).
Delivery rate and pressure settings.
3.5.1.3 Blast a one-square foot area on one side of the test coupon to the abrasive surface preparation standard specified in the work item, and perform an anchor profile test of the blasted surface in accordance with ASTM
D4417, Method B or C. Notify the COTR in advance of the abrasive blasting operation test, to permit the witnessing of the test by the COTR. Submit a CFR documenting the results of the abrasive blasting operation test. The CFR shall include at a minimum, the following:
Area of the vessel for which the verified setup will be used to abrasive blast.
The selected abrasive media type and size.
The nozzle size and type.
The delivery rate and pressure.
The test coupon starting properties (material type and surface conditions).
The resultant anchor profile readings from the test (a minimum of 3 locations, separated by a minimum of
2 inches shall be recorded).
NOTES
1. A performance test of the abrasive blasting operations on a test coupon and measuring the resultant anchor profile prior to performing the abrasive blasting operation on the cutter is required. The test coupon will be used to evaluate the anchor profile produced by the equipment setup and selected abrasive media.
2. The reverse side of the test coupon may be used for the subsequent test, provided that the conditions in paragraph 3.5.1 (Coupon material and test set-up particulars) are met.
3. Ultra high pressure water jetting does not create an anchor profile and is exempt from the anchor profile test coupon check.
4 (Rev-0)
3.5.1.4 Repeat the abrasive blasting operation test in the following instances:
The equipment setup, that was evaluated during the test coupon abrasive blasting performance test in paragraph 3.5.1 (Coupon material and test set-up particulars), has changed.
The resultant anchor profile readings observed on the vessel are outside the specified anchor profile range.
Media is changed from MIL-A-22262 to CID A-A-59316 or vice versa.
The supplier of the abrasive blasting media changes, regardless if the new source for the media has the same specifications.
When Directed by the COTR.
CAUTION!
Ensure that blast media from the performance test does not strike the vessel during the test.
3.6 Interim changes to SFLC Std Spec 0000. The Contractor shall be aware of the fact that the requirements of paragraph 3.3.2.1.1 (Water depth) have been revised to read as follows:
“3.3.2.1.1 Water depth. Ensure that water depth is sufficient at the pier to allow the vessel's lowest underwater appendage to clear the bottom by at least two feet at:
Ordinary low water mark on non-tidal rivers.
At all tide conditions predicted during the availability for tidal rivers and other navigable waterways (Bay, Lake, etc.).”
4. NOTES
4.1 Access to COMDTINST M10360.3. The COMDTINST M10360.3 may be accessed at the following URL address: http://www.uscg.mil/directives/cim.asp
4.2 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 0000 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
http://www.uscg.mil/directives/cim.asp
5 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
Vessel Name Hull # Work Item # Work Item Title
Location of Work (incl. frame #’s) Area (sqft)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with COMDTINST M10360.3, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-based coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down
(maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-12, SP-11, SP-10…).
Verify surface anchor profile using ASTM D4417-Methods B or C against COMDTINST M10360.3. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max.
threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
Name of QP-1/NACE Inspector Signature Cert. # Date / Time
6 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE &
TIME
ACTIVITY (Surface preparation, primer coat, barrier coat, top coat, etc…)
LOCATION
(Frame &
Deck, relation to equipment, etc.)
TEMPERATURE % REL.
HUMID-
ITY DEW PT. SURFACE AMBIENT ΔT
| DP - Surface |
7 (Rev-0)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
Location of Work (Frame References) Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils) Min Max Mean
SSPC-SP-10/NACE No. 2 SSPC-SP-12/NACE No. 5
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
Abrasive Manufacturer and Sieve Size: _________________________________
Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Mean Mil Reading (IAW ASTM D4417-Method C) for above 15 readings: ______________
8 (Rev-0)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils) Min Max Mean
SSPC-SP-10/NACE No. 2 SSPC-SP-12/NACE No. 5
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
Abrasive Manufacturer and Sieve Size: _________________________________
Record measurements taken in the spaces provided below, to serve as permanent QA record. Maintain separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils
Reading: _____ mils _____ mils _____ mils _____ mils _____ mils Mean Mil Reading (IAW ASTM D4417-Method B) for above 10 readings (by column):
_____ mils _____ mils _____ mils _____ mils _____ mils
9 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15
DATE TEST LOCATIONS CONDUCTIVITY
(microsiemens/cm)
10 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
Coating Mfg Product Name Batch # Induction
Time Coating System Sequence
(Primer/Touchup/3rd Coat, etc.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2
SPOT 1 2 3 4 5 AVERAGE
VALUE
*BASE METAL
READING (BMR)
*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation 3 Before
Adjustments After Adjustments
Avg.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation 3 Before
Adjustments After Adjustments
Avg.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation 3 Before
Adjustments After Adjustments
Avg.
Application Method (Airless, Conventional Spray, Rolled) Average DFT
11 (Rev-0)
25901_0611_FLT
REC_25901_FLT_210' WMEC 'B' Class (ALL) (0411)
WORK ITEM 1: Main Diesel Engine (MDE) Exhaust Stack Uptakes (All), Commercially Clean
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean the #1 & #2 Main Diesel
Engine (MDE) exhaust stacks.
1.2 Government-furnished equipment.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 627 WMEC 259-001, Rev D, Arrangement Exhaust Piping
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General
Requirements
OTHER REFERENCES
Code of Federal Regulations (CFR) Title 29, Part 1915, Jul 2008, Occupational Safety and Health
Standards for Shipyard Employment
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
12 (Rev-0)
3.1.3 Protective measures. The Contractor shall furnish and install suitable covering to seal off and protect all non-affected surfaces/equipment and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, remove protective material and inspect for the presence of contamination. Clean all equipment and spaces, contaminated due to improper protection, to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the below-listed. Handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5
(Interferences):
Access covers.
Exhaust stack.
MDE.
Piping.
Pipe insulation.
Vent ducting.
Wiring.
Exhaust pipe expansion joints.
Exhaust insulation blankets.
3.1.5 Scaffolding. The Contractor shall, in accordance with 29 CFR 1915, Subpart E, erect suitable staging or scaffolding, as required, to facilitate to perform work.
3.1.6 Safety precaution. The Contractor shall rig suitable safety netting, to protect workers during possible falls, and to protect the Engine Room and machinery from falling tools.
3.2 Work plan. The Contractor shall develop and submit, to the COTR, a plan for collecting and disposing of waste extracted during cleaning process. Ensure that the proposed plan shall detail how and where exhaust piping will be disconnected, how entire length of exhaust piping will be divided/sectioned for cleaning, and precautions to protect the MDE. The Contractor shall perform this work upon receiving Coast Guard approval of the plan.
3.3 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of the exhaust stack system, to demonstrate existing operational condition.
Submit a CFR.
3.4 Cleaning. The Contractor shall clean the interior surfaces of the exhaust piping to the MDE, shown on Coast
Guard Drawings 627 WMEC 295-001, to a condition free from soot, tar, and any other foreign matter as follows:
3.4.1 Disconnect the exhaust piping as necessary to facilitate cleaning.
3.4.2 Thoroughly sweep, mechanically clean, and vacuum the interior of each exhaust pipe system, including the mufflers, from the exhaust outlet to the topmost location outside the vessel. Ensure that all tar deposits, soot deposits, and all other surface contaminants are completely removed.
3.4.3 Upon completion of cleaning, do the following:
3.4.3.1 Remove all debris from the pipe surfaces, stack deck, and Engine Room areas by vacuuming. Dispose of all cleaning materials and generated debris in accordance with all applicable Federal, state, and local regulations.
13 (Rev-0)
3.4.3.2 Reassemble exhaust piping; renew all flange connection gaskets with suitable high temperature, non-asbestos-containing gasket materials, and renew all fasteners.
3.5 Inspection and report. The Contractor shall perform a visual inspection of the following components; submit a CFR:
Exhaust stack access hatches, including all associated studs and nuts.
All cleaned exhaust stack surfaces.
All exhaust expansion joints, including associated bolts.
3.6 Touch-up preservation. The Contractor shall prepare and touch-up coat all disturbed surfaces to match existing adjacent surfaces in accordance with COMDTINST M10360.3, Appendix B (Cutter and Boat Interior
Painting Systems). Abide by all touch-up requirements outlined in SFLC Std Spec 0000, Appendix A
(Requirements for Preservation of Ship Structures).
3.7 Operational test – post repairs. After completion of work, the Contractor shall witness an operational test (by
Coast Guard personnel) of the exhaust stack system to prove satisfactory operating condition. Submit a CFR.
4. NOTES
This section is not applicable to this work item.
14 (Rev-0)
25902_0611_FLT
REC_25902_FLT_210' WMEC 'B' Class (ALL) (1109)
WORK ITEM 2: Ship Service Diesel Generators (SSDGs) and (EDG) Exhaust Piping (All), Commercially Clean
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean the #1 & #2 Ship Service Diesel
Generator (SSDG) and Emergency Diesel Generator (EDG) exhaust piping.
1.2 Government-furnished equipment.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 627 WMEC 259-001, Rev D, Arrangement Exhaust Piping
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General
Requirements
OTHER REFERENCES
Code of Federal Regulations (CFR) Title 29, Part 1915, Jul 2008, Occupational Safety and Health
Standards for Shipyard Employment
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install suitable covering to seal off and protect all non-affected surfaces/equipment and spaces in the vicinity of the work area against contamination during the
15 (Rev-0) performance of work. Upon completion of work, remove protective material and inspect for the presence of contamination. Clean all equipment and spaces, contaminated due to improper protection, to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the below-listed. Handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5
(Interferences):
Access covers.
Exhaust stack.
SSDG.
EDG
Vent ducting.
Wiring.
Exhaust pipe expansion joints.
Exhaust insulation blankets.
3.1.5 Safety precaution. The Contractor shall rig suitable safety netting, to protect workers during possible falls, and to protect the Engine Room and machinery from falling tools.
3.1.6 Access openings.
Not applicable.
3.2 Work plan. The Contractor shall develop and submit to the COTR, a plan for collecting and disposing of waste extracted during cleaning process. Ensure that the proposed plan shall detail how and where exhaust piping will be disconnected, how entire length of exhaust piping will be divided/sectioned for cleaning, and precautions to protect the SSDG. The Contractor shall perform this work upon receiving Coast Guard approval of the plan.
3.3 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of the exhaust stack system, to demonstrate existing operational condition.
Submit a CFR.
3.4 Cleaning. The Contractor shall clean the interior surfaces of the exhaust piping to the SSDG, shown on Coast
Guard Drawing(s) 627 WMEC 295-001, to a condition free from soot, tar, and any other foreign matter as follows:
3.4.1 Disconnect the exhaust piping as necessary to facilitate cleaning.
3.4.2 Thoroughly sweep, mechanically clean, and vacuum the interior of each exhaust pipe system, including the mufflers, from the exhaust outlet to the topmost location outside the vessel. Ensure that all tar deposits, soot deposits, and all other surface contaminants are completely removed.
3.4.3 Upon completion of cleaning, do the following:
3.4.3.1 Remove all debris from the pipe surfaces, stack deck, and Engine Room areas by vacuuming. Dispose of all cleaning materials and generated debris in accordance with all applicable Federal, state, and local regulations.
3.4.3.2 Reassemble exhaust piping; renew all flange connection gaskets with suitable high temperature, non-
16 (Rev-0) asbestos-containing gasket materials. Renew all fasteners.
3.5 Inspection and report. The Contractor shall perform a visual inspection of the following components; submit a CFR:
Exhaust stack access hatches, including all associated studs and nuts.
All cleaned exhaust stack surfaces.
All exhaust expansion joints, including associated bolts.
3.6 Touch-up preservation. The Contractor shall prepare and touch-up coat all disturbed surfaces to match existing adjacent surfaces in accordance with COMDTINST M10360.3, Appendix B (Cutter and Boat Interior
Painting Systems). Abide by all touch-up requirements outlined in SFLC Std Spec 0000, Appendix A
(Requirements for Preservation of Ship Structures).
3.7 Operational test – post repairs. After completion of work, the Contractor shall witness an operational test (by
Coast Guard personnel) of the exhaust stack system to prove satisfactory operating condition. Submit a CFR.
17 (Rev-0)
25903_0611_FLT
REC_25903_FLT_210' WMEC 'B' Class (ALL)
WORK ITEM 3: Boiler Exhaust Stack Uptakes , Commercially Clean
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean the Boiler exhaust stack uptakes.
1.2 Government-furnished equipment.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 627 WMEC 259-001, Rev D, Arrangement Exhaust Piping
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center (SFLC) Standard Specification 0000_STD, 2009 Edition, General
Requirements
OTHER REFERENCES
None.
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install suitable covering to seal off and protect all non-affected surfaces/equipment and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, remove protective material and inspect for the presence of contamination. Clean all equipment and spaces, contaminated due to improper protection, to original condition of
18 (Rev-0) cleanliness.
3.1.4 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the below-listed. Handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5
(Interferences):
Access covers.
Exhaust stack.
Boiler.
Exhaust pipe expansian joints.
Exhaust insulation blankets.
3.1.5 Safety precaution. The Contractor shall rig suitable safety netting, to protect workers during possible falls, and to protect the Engine Room and machinery from falling tools.
3.2 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of the exhaust stack system, to demonstrate existing operational condition.
Submit a CFR.
3.3 Cleaning. The Contractor shall clean the interior surfaces of the exhaust piping to the Boiler, shown on Coast
Guard Drawing(s) 627 WMEC 295-001, to a condition free from soot, tar, and any other foreign matter as follows:
3.3.1 Disconnect the exhaust piping as necessary to facilitate cleaning.
3.3.2 Thoroughly sweep, mechanically clean, and vacuum the interior of each exhaust pipe system, including the mufflers, from the exhaust outlet to the topmost location outside the vessel. Ensure that all tar deposits, soot deposits, and all other surface contaminants are completely removed.
3.3.3 Upon completion of cleaning, do the following:
3.3.3.1 Remove all debris from the pipe surfaces, stack deck, and Engine Room areas by vacuuming. Dispose of all cleaning materials and generated debris in accordance with all applicable Federal, state, and local regulations.
3.3.3.2 Reassemble exhaust piping; renew all flange connection gaskets with suitable high temperature, non-asbestos-containing gasket materials. Renew all fasteners.
3.4 Inspection and report. The Contractor shall perform a visual inspection of the following components; submit a CFR:
Exhaust stack access hatches, including all associated studs and nuts.
All cleaned exhaust stack surfaces.
All exhaust expansion joints, including associated bolts.
3.5 Touch-up preservation. The Contractor shall prepare and touch-up coat all disturbed surfaces to match existing adjacent surfaces in accordance with COMDTINST M10360.3, Appendix B (Cutter and Boat Interior
Painting Systems). Abide by all touch-up requirements outlined in SFLC Std Spec 0000, Appendix A
(Requirements for Preservation of Ship Structures).
19 (Rev-0)
3.6 Operational test – post repairs. After completion of work, the Contractor shall witness an operational test (by
Coast Guard personnel) of the exhaust stack system to prove satisfactory operating condition. Submit a CFR.
20 (Rev-0)
51200_0711_FLT
REC_51200_FLT_210’ WMEC ‘B’ Class (ALL) (0511)
WORK ITEM 4: Vent Ducts (Engine and Motor Room, JP-5 Space, Fwd Aux and MSD - All), Commercially Clean
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the designated shipboard ventilation systems (Engine and Motor Room, JP-5 Space, Fwd Aux and MSD).
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 627 WMEC 512-006, Rev D, Ventilation Diagram – Second Deck
Coast Guard Drawing 627 WMEC 512-007, Rev D, Ventilation Diagram – Main Deck
Coast Guard Drawing 627 WMEC 512-008, Rev D, Ventilation Diagram – 01 Deck & Abv
Coast Guard Drawing 627 WMEC 512-020, Rev -, Arrangement Vent and AC 02 Level
Coast Guard Drawing 627 WMEC 512-021, Rev -, Arrangement Vent and AC 01 Level
Coast Guard Drawing 627 WMEC 512-026, Rev -, Arrangement Vent and AC Main Deck
Coast Guard Drawing 627 WMEC 512-029, Rev -, Arrangement Vent and AC 2nd Deck
Coast Guard Drawing 627 WMEC 512-030, Rev -, Arrangement Vent and AC 3rd Deck
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General
Requirements
Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), Jan 2009, Clean
None.
3. REQUIREMENTS
3.1 General.
21 (Rev-0)
3.1.1 CIR.
3.1.2 Technical Representative.
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install suitable covering to seal off and protect all non-affected surfaces/equipment and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, remove protective material and inspect for the presence of contamination. Clean all equipment and spaces, contaminated due to improper protection, to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the below-listed. Handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5
(Interferences):
Ducting screens.
Dishwasher/laundry ducting.
Ceiling tiles and supports.
Overhead sheathing.
3.2 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of the ventilation systems included in this work item, to demonstrate existing operational condition. Submit a CFR.
3.3 Cleaning requirements. The Contractor shall clean and inspect the following ventilation systems, shown on
Coast Guard Drawings 627 WMEC 512-006, 627 WMEC 512-007, 627 WMEC 512-008, 627 WMEC 512-020, 627 WMEC 512-021, 627 WMEC 512-026, 627 WMEC 512-029, and 627 WMEC 512-030, in accordance with
SFLC Std Spec 5100. Submit a CFR.
22 (Rev-0)
VENTILATION
SYSTEM
TYPE DUCT
WORK
NUMBER
LOCATION
Engineroom EXHAUST 2-121-2
Engineroom SUPPLY 01-103-1
Engineroom EXHAUST 01-104-2
Engineroom SUPPLY 01-103-2
Engineroom EXHAUST 2-132-1
Engineroom EXHAUST 01-104-1
JP-5 Space EXHAUST 4-156-0-E
Fwd Aux EXHAUST 3-96-1
MSD Space EXHAUST 01-101-2
3.4 Notification. The Contractor shall give written notification to the COTR, 48 hours before starting ventilation cleaning work.
3.5 Operational test – post repairs. After completion of work, the Contractor shall, in the presence of the Coast
Guard Inspector, thoroughly test and prove the ventilation systems to be satisfactory operating condition. Submit a CFR.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
23 (Rev-0)
51201_0411_FLT
WORK ITEM 5: Vent Ducts (Galley, Gaylord Hood and Pantry Room-All), Commercially Clean
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the designated shipboard ventilation systems (Galley, Gaylord Hood and Pantry Room-All).
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 627 WMEC 512-006, Rev D, Ventilation Diagram – Second Deck
Coast Guard Drawing 627 WMEC 512-007, Rev D, Ventilation Diagram – Main Deck
Coast Guard Drawing 627 WMEC 512-008, Rev D, Ventilation Diagram – 01 Deck & Abv
Coast Guard Drawing 627 WMEC 512-020, Rev -, Arrangement Vent and AC 02 Level
Coast Guard Drawing 627 WMEC 512-021, Rev -, Arrangement Vent and AC 01 Level
Coast Guard Drawing 627 WMEC 512-026, Rev -, Arrangement Vent and AC Main Deck
Coast Guard Drawing 627 WMEC 512-029, Rev -, Arrangement Vent and AC 2nd Deck
Coast Guard Drawing 627 WMEC 512-030, Rev -, Arrangement Vent and AC 3rd Deck
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General
Requirements
24 (Rev-0)
3.1.2 Technical Representative.
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install suitable covering to seal off and protect all non-affected surfaces/equipment and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, remove protective material and inspect for the presence of contamination. Clean all equipment and spaces, contaminated due to improper protection, to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the below-listed. Handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5
(Interferences):
Ducting screens.
Dishwasher/laundry ducting.
Ceiling tiles and supports.
Overhead sheathing.
3.2 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of the ventilation systems included in this work item, to demonstrate existing operational condition. Submit a CFR.
3.3 Cleaning requirements. The Contractor shall clean and inspect the following ventilation systems, shown on
Coast Guard Drawings 627 WMEC 512-006, 627 WMEC 512-007, 627 WMEC 512-008, 627 WMEC 512-020, VENTILATION SYSTEM TYPE LOCATION
1-160-2 SUPPLY DRY PROVISIONS
STOREROOM (1-159-2-A);
GALLEY (1-146-0-Q)
1-160-1 EXHAUST DRY STORES (1-159-1-A);
GALLEY (1-146-0-Q)
1-110-2 EXHAUST UPTAKE (1-108-0-Q)
1-146-0-Q EXHAUST GAYLORD HOOD
1-160-1 EXHAUST GAYLORD FAN
3.4 Additional requirements. In addition to the above, the Contractor shall accomplish the following:
3.4.1 Notification. Give written notification to the COTR, 48 hours before starting ventilation cleaning work.
25 (Rev-0)
3.4.2 Additional protective covering. In addition to providing protective covering as specified in SFLC Std Spec
5100, subsection 3.1.3 (Protective measures), provide additional protective covering for all food preparation and serving surfaces in the immediate work area, as applicable, to prevent contamination.
3.4.3 Avoidance of meal preparation and service. Ensure that cleaning of galley ventilation systems is scheduled between 1900 and 0530 so that it WILL NOT interfere with meal preparation and service.
3.5 Operational test – post repairs. After completion of work, the Contractor shall witness an operational test (by
Coast Guard personnel) of the ventilation systems included in this work item to prove satisfactory operating condition. Submit a CFR.
26 (Rev-0)
51202_0411_FLT
WORK ITEM 6: Vent Ducts (Laundry Exhaust), Commercially Clean
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the designated shipboard ventilation systems.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 627 WMEC 512-006, Rev D, Ventilation Diagram –…
This is the start of the file's text. The full file is on GovTribe.