Clev Step 1 Work Summary.docx
DOCX document 14 KB Posted
- Attached to
- Station Clevelend Ohio Federal contract opportunity
- Solicitation number
- HSCG50-10-R-PFDCLH
About this file
Summary of Work
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 2 Phase 1.doc | DOC document | |
| Concept Arch Site Plan.pdf | ||
| Amendment 1 Phase 1.doc | DOC document | |
| Site Visit Attendance.pdf | ||
| Phase I Past Perf.doc | DOC document | |
| Cleveland Step 1 Solicitation.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The scope of work includes all architectural and engineering design, construction, permitting, and other related services necessary to provide a fully functional new facility located on government owned property. The Contractor will be furnished with conceptual (10%) design drawings indicating space layouts, program requirements, baseline exterior elevations, and performance specifications by the Government and will then proceed with completing the 100% building and site designs. The design of the architectural, structural, mechanical, electrical, civil, life safety, or other engineering features of the project shall be accomplished or reviewed and approved by architects and engineers registered in the State of Ohio to practice in the particular professional field involved. The Contractor shall be responsible for constructing the project in accordance with the accepted design. Design and construction shall be accomplished within a total 24 month performance period after date of award.
The new building will be a two-story, approximately 24,500 gross square foot facility including office, administrative and conference spaces, locker, shower, restroom and fitness facilities, berthing rooms, weapons storage, a galley/dining area, radio room and secure communications room. Mitigating measures to address unacceptable settlement will have to be taken due to the presence of highly compressible soils within the project area. A potential for methane gas beneath the proposed building site exists, and therefore a methane gas collection, venting, and detection system will be required as part of the site preparation. Other sitework includes site utilities, grading, constructing new sidewalks and parking areas, landscaping, and the construction of a 100-foot communications tower. A new emergency generator and fuel tank will also be supplied adjacent to the new building. Mechanical and electrical systems include HVAC with DDC, plumbing, fire protection, power, lighting, telecommunications, fire detection and alarm. The Contractor shall provide interior systems furniture plans, designed and coordinated with the building construction. An interior designer currently holding a Professional level membership in the America Society of Interior Designers shall select all interior systems and finishes.
The Government intends to include optional bid items in the solicitation to be awarded pending funds availability. The work includes (1) demolition of a one story, approximately 21,000 SF building immediately adjacent to the site of the new building; (2) demolition of an approximately 1,200 SF building on site; (3) construction of approximately 1,200 LF of ornamental fence around the perimeter of the base; and (4) burying approximately 240 LF of overhead electrical and telecommunication lines near the entrance to the Base.
The design proposals shall incorporate energy efficient design and construction and shall include sustainable design features sufficient for the Contractor to obtain a “silver” rating by the U.S. Green Building Council LEED-NC Version 3.0.