Attachment_2-FT4A_Components_Repair_Contract_Delivery_Schedule.pdf

PDF 102 KB Posted

Attached to
USCG FT4A Gas Turbine Components
Solicitation number
HSCG40-17-R-31722
Issued by

About this file

Attachment 2: FT4A Components Repair Contract Delivery Schedule

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CLIN Description Schedule

Group I – Manifolds

B.1 Initial Receiving Report IAW paragraph 3.2.1 and 3.3 30 calendar days after issuance of a delivery order

B.2 Disassembly Condition Inspection Report IAW 3.2.2 and 3.4 30 calendar days after submittal of Initial Receiving Report

B.3

Reassembly Report IAW paragraph 3.2.3 14 calendar days after completion of repair/overhaul of the component(s) and any testing required.

B.4

Gas Turbine Component overhaul, testing and PPP&M IAW paragraph 3.5, 3.8 and 5.0

40 calendar days after receipt of

Coast Guard authority of proceed with repairs/overhaul.

B.5 Certificate of Conformance IAW 3.1.6 14 calendar days after completion of overhaul and testing

B.6 GFP and GFM Report IAW paragraph of 3.2.4 15 calendar days after receipt of discrepant GFP/GFM.

B.8-B.25

Contingency parts To be completed during the same time frame as B.4 (including option years)

Group II – Combustion Chambers

B.26 Initial Receiving Report IAW paragraph 3.2.1 and 3.3 30 calendar days after issuance of a delivery order

B.27 Disassembly Condition Inspection Report IAW 3.2.2 and 3.4 30 calendar days after submittal of Initial Receiving Report

B.28

Reassembly Report IAW paragraph 3.2.3 14 calendar days after completion of repair/overhaul of the component(s) and any testing required.

B.29

Gas Turbine Component overhaul, testing and PPP&M IAW paragraph 3.5, 3.8 and 5.0

40 calendar days after receipt of

Coast Guard authority of proceed with repairs/overhaul.

B.30 Certificate of Conformance IAW 3.1.6 14 calendar days after completion of overhaul and testing

B.31 GFP and GFM Report IAW paragraph of 3.2.4 15 calendar days after receipt of discrepant GFP/GFM.

B.33-B.44

Contingency parts To be completed during the same time frame as B.29 (including option years)

Group III – Pressure and Dump Valves

B.45 Initial Receiving Report IAW paragraph 3.2.1 and 3.3 30 calendar days after issuance of a delivery order

B.46 Disassembly Condition Inspection Report IAW 3.2.2 and 3.4 30 calendar days after submittal of Initial Receiving Report

B.47

Reassembly Report IAW paragraph 3.2.3 14 calendar days after completion of repair/overhaul of the component(s) and any testing required.

B.48

Gas Turbine Component overhaul, testing and PPP&M IAW paragraph 3.5, 3.8 and 5.0

40 calendar days after receipt of

Coast Guard authority of proceed with repairs/overhaul.

B.51 Certificate of Conformance IAW 3.1.6 14 calendar days after completion of overhaul and testing

B.52 GFP and GFM Report IAW paragraph of 3.2.4 15 calendar days after receipt of discrepant GFP/GFM.

B.54-B.97

Contingency parts To be completed during the same time frame as B.48 (including option years)

Group IV – Pumps

B.98 Initial Receiving Report IAW paragraph 3.2.1 and 3.3 30 calendar days after issuance of a delivery order

B.99 Disassembly Condition Inspection Report IAW 3.2.2 and 3.4 30 calendar days after submittal of Initial Receiving Report

B.100

Reassembly Report IAW paragraph 3.2.3 14 calendar days after completion of repair/overhaul of the component(s) and any testing required.

B.101

Gas Turbine Component overhaul, testing and PPP&M IAW paragraph 3.5, 3.8 and 5.0

40 calendar days after receipt of

Coast Guard authority of proceed with repairs/overhaul.

B.104 Certificate of Conformance IAW 3.1.6 14 calendar days after completion of overhaul and testing

B.105 GFP and GFM Report IAW paragraph of 3.2.4 15 calendar days after receipt of discrepant GFP/GFM.

B.107-B.149

Contingency parts To be completed during the same time frame as B.101 (including option years)

Group V – Actuator Valves

B.150 Initial Receiving Report IAW paragraph 3.2.1 and 3.3 30 calendar days after issuance of a delivery order

B.151 Disassembly Condition Inspection Report IAW 3.2.2 and 3.4 30 calendar days after submittal of Initial Receiving Report

B.152

Reassembly Report IAW paragraph 3.2.3 14 calendar days after completion of repair/overhaul of the component(s) and any testing required.

B.153

Gas Turbine Component overhaul, testing and PPP&M IAW paragraph 3.5, 3.8 and 5.0

40 calendar days after receipt of

Coast Guard authority of proceed with repairs/overhaul.

B.156 Certificate of Conformance IAW 3.1.6 14 calendar days after completion of overhaul and testing

B.157 GFP and GFM Report IAW paragraph of 3.2.4 15 calendar days after receipt of discrepant GFP/GFM.

B.159-B.170

Contingency parts To be completed during the same time frame as B.153 (including option years)

Group VI – 1 st Stage Nozzle Guide Vanes (each)

B.171 Initial Receiving Report IAW paragraph 3.2.1 and 3.3 30 calendar days after issuance of a delivery order

B.172 Disassembly Condition Inspection Report IAW 3.2.2 and 3.4 30 calendar days after submittal of Initial Receiving Report

B.173

Reassembly Report IAW paragraph 3.2.3 14 calendar days after completion of repair/overhaul of the component(s) and any testing required.

B.174

Gas Turbine Component overhaul, testing and PPP&M IAW paragraph 3.5, 3.8 and 5.0

40 calendar days after receipt of

Coast Guard authority of proceed with repairs/overhaul.

B.175 Certificate of Conformance IAW 3.1.6 14 calendar days after completion of overhaul and testing

B.176 GFP and GFM Report IAW paragraph of 3.2.4 15 calendar days after receipt of discrepant GFP/GFM.

B.178-B.182

Contingency parts To be completed during the same time frame as B.174 (including option years)

Group VII – 1 st Stage Nozzle Guide Vanes (set of 80)

B.183 Initial Receiving Report IAW paragraph 3.2.1 and 3.3 30 calendar days after issuance of a delivery order

B.184 Disassembly Condition Inspection Report IAW 3.2.2 and 3.4 30 calendar days after submittal of Initial Receiving Report

B.185

Reassembly Report IAW paragraph 3.2.3 14 calendar days after completion of repair/overhaul of the component(s) and any testing required.

B.186

Gas Turbine Component overhaul, testing and PPP&M IAW paragraph 3.5, 3.8 and 5.0

40 calendar days after receipt of

Coast Guard authority of proceed with repairs/overhaul.

B.187 Certificate of Conformance IAW 3.1.6 14 calendar days after completion of overhaul and testing

B.188 GFP and GFM Report IAW paragraph of 3.2.4 15 calendar days after receipt of discrepant GFP/GFM.

B.190-B.194

Contingency parts To be completed during the same time frame as B.186 (including option years)

Group VIII – Oil Tank and Fairing

B.195 Initial Receiving Report IAW paragraph 3.2.1 and 3.3 30 calendar days after issuance of a delivery order

B.196 Disassembly Condition Inspection Report IAW 3.2.2 and 3.4 30 calendar days after submittal of Initial Receiving Report

B.197

Reassembly Report IAW paragraph 3.2.3 14 calendar days after completion of repair/overhaul of the component(s) and any testing required.

B.198

Gas Turbine Component overhaul, testing and PPP&M IAW paragraph 3.5, 3.8 and 5.0

40 calendar days after receipt of

Coast Guard authority of proceed with repairs/overhaul.

B.200 Certificate of Conformance IAW 3.1.6 14 calendar days after completion of overhaul and testing

B.201 GFP and GFM Report IAW paragraph of 3.2.4 15 calendar days after receipt of discrepant GFP/GFM.

B.203-B.207

Contingency parts To be completed during the same time frame as B.198 (including option years)

Group IX – Inlet Vane Case

B.208 Initial Receiving Report IAW paragraph 3.2.1 and 3.3 30 calendar days after issuance of a delivery order

B.209 Disassembly Condition Inspection Report IAW 3.2.2 and 3.4 30 calendar days after submittal of Initial Receiving Report

B.210

Reassembly Report IAW paragraph 3.2.3 14 calendar days after completion of repair/overhaul of the component(s) and any testing required.

B.211

Gas Turbine Component overhaul, testing and PPP&M IAW paragraph 3.5, 3.8 and 5.0

40 calendar days after receipt of

Coast Guard authority of proceed with repairs/overhaul.

B.212 Certificate of Conformance IAW 3.1.6 14 calendar days after completion of overhaul and testing

B.213 GFP and GFM Report IAW paragraph of 3.2.4 15 calendar days after receipt of discrepant GFP/GFM.

B.215-B.220

Contingency parts To be completed during the same time frame as B.211 (including option years)

Group X – Free Turbine Scissors Mount Assembly

B.221 Initial Receiving Report IAW paragraph 3.2.1 and 3.3 30 calendar days after issuance of a delivery order

B.222 Disassembly Condition Inspection Report IAW 3.2.2 and 3.4 30 calendar days after submittal of Initial Receiving Report

B.223

Reassembly Report IAW paragraph 3.2.3 14 calendar days after completion of repair/overhaul of the component(s) and any testing required.

B.224

Gas Turbine Component overhaul, testing and PPP&M IAW paragraph 3.5, 3.8 and 5.0

40 calendar days after receipt of

Coast Guard authority of proceed with repairs/overhaul.

B.225 Certificate of Conformance IAW 3.1.6 14 calendar days after completion of overhaul and testing

B.226 GFP and GFM Report IAW paragraph of 3.2.4 15 calendar days after receipt of discrepant GFP/GFM.

B.228-B.247

Contingency parts To be completed during the same time frame as B.224 (including option years)

Group XI – Free Output Shaft

B.248 Initial Receiving Report IAW paragraph 3.2.1 and 3.3 30 calendar days after issuance of a delivery order

B.249 Disassembly Condition Inspection Report IAW 3.2.2 and 3.4 30 calendar days after submittal of Initial Receiving Report

B.250

Reassembly Report IAW paragraph 3.2.3 14 calendar days after completion of repair/overhaul of the component(s) and any testing required.

B.253

Gas Turbine Component overhaul, testing and PPP&M IAW paragraph 3.5, 3.8 and 5.0

40 calendar days after receipt of

Coast Guard authority of proceed with repairs/overhaul.

B.254 Certificate of Conformance IAW 3.1.6 14 calendar days after completion of overhaul and testing

B.255 GFP and GFM Report IAW paragraph of 3.2.4 15 calendar days after receipt of discrepant GFP/GFM.

B.257-B.259

Contingency parts To be completed during the same time frame as B.253 (including option years)

Group XII – Magnetic Pickup Assembly

B.260 Initial Receiving Report IAW paragraph 3.2.1 and 3.3 30 calendar days after issuance of a delivery order

B.261 Disassembly Condition Inspection Report IAW 3.2.2 and 3.4 30 calendar days after submittal of Initial Receiving Report

B.262

Reassembly Report IAW paragraph 3.2.3 14 calendar days after completion of repair/overhaul of the component(s) and any testing required.

B.263 Gas Turbine Component overhaul, testing and PPP&M IAW 40 calendar days after receipt of paragraph 3.5, 3.8 and 5.0 Coast Guard authority of proceed with repairs/overhaul.

B.264 Certificate of Conformance IAW 3.1.6 14 calendar days after completion of overhaul and testing

B.265 GFP and GFM Report IAW paragraph of 3.2.4 15 calendar days after receipt of discrepant GFP/GFM.

B.267-B.278

Contingency parts To be completed during the same time frame as B.263 (including option years)

Group XIII – Combustion Chamber Support Assembly

B.279 Initial Receiving Report IAW paragraph 3.2.1 and 3.3 30 calendar days after issuance of a delivery order

B.280 Disassembly Condition Inspection Report IAW 3.2.2 and 3.4 30 calendar days after submittal of Initial Receiving Report

B.281

Reassembly Report IAW paragraph 3.2.3 14 calendar days after completion of repair/overhaul of the component(s) and any testing required.

B.282

Gas Turbine Component overhaul, testing and PPP&M IAW paragraph 3.5, 3.8 and 5.0

40 calendar days after receipt of

Coast Guard authority of proceed with repairs/overhaul.

B.283 Certificate of Conformance IAW 3.1.6 14 calendar days after completion of overhaul and testing

B.284 GFP and GFM Report IAW paragraph of 3.2.4 15 calendar days after receipt of discrepant GFP/GFM.

B.286-B.292

Contingency parts To be completed during the same time frame as B.282 (including option years)

B.293

Gas Turbine Component Status Report IAW paragraph 3.2.5 Monthly (no later than the 15 th calendar day) while any gas turbine components are being repaired/tested/PPP&M.

File details come from the government source that posted it. Updated .