SCOPE OF WORK

View the file

Other files

File Type Posted
RW004RFQPKG.doc DOC document
RW004WR.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1.1. Scope of Work to Replace Gate Motor, B&B rack and pinion hydraulic slide gate operator with soft stop/start for SNNE USCG South Portland ME.

1.2. Location of Project: USCG Sector Northern New England 259 High Street, South Portland, Maine 04106.

1.3. Points of Contact: contracting questions; Mrs. Beverly Primm (617)223-3119, technical questions; CWO3 Victor A. Herschaft (207) 318-2146, site visit scheduling EM1 Jackie Barker (207) 812-8154.

1.4. Work Covered by Contract: The contractor shall provide all labor, materials, equipment, transportation, and supervision necessary to perform the work as described herein. All work shall be conducted per this scope of work and all applicable Federal, State and local laws, regulations, codes, and directives. This summary is not all inclusive and delineates only those work items deemed as major to the contract. Ancillary work items not listed below, though necessary to attain the completed project, shall be included in the contract at no additional cost.

1.5. Vendor will verify Coast Guards work that the electrical supply to the circuit is isolated, all electrical components in and around affected areas, and tag out in accordance with unit tag out procedures. All obstructions will be removed, including anything within the area of skid installation.

1.6. Vendor will protect all affected areas and equipment from damage.

1.7. Vendor will remove and dispose of damaged gate operator.

1.8. Vendor will not re-use existing rollers, will op test and advise of re-use of limit switch, sensing driveway pads and reconnect motor gear to fence gear.

1.9. Military Regulations; the contractor, his employees, and sub-contractors shall become familiar with and obey all Coast Guard regulations. All personnel employed on the project shall keep within the limits of the work and avenues of ingress and egress, and shall not enter any other areas outside the work unless required to do so in the performance of their duties. The contractor’s equipment shall be conspicuously marked for identification. There shall be no smoking outside of designated smoking areas.

1.10. Work Hours; the contractor shall perform all site work during normal operational hours of 0800 and 1600, Monday through Friday, except during Federal Holidays. Any deviation from these work hours must be arranged with the unit prior to the commencement of work.

1.11. Performance; all work shall be completed within 30 days of the notice to proceed.

1.12. Cleanup of Work Areas; The contractor shall remove and properly dispose of all trash and debris incident to the contract work from the limits of government property, as well as all adjacent affected areas. Disposal shall be in accordance with Federal, State, and Local regulations. Any floor, wall, or ceiling surfaces that may have been stained or soiled by the contract work shall be restored to pre-construction condition.

1.13. Acceptance of Work; prior to the acceptance of work by the Coast Guard: the contractor shall arrange through the Engineering Officer or someone designated by him, an inspection of the work site to ensure proper operation, to identify necessary corrective work, and to ensure proper work areas cleanup.

Note: Work shall not begin on this job until you have received authorization from the contracting officer and have obtained either a copy of the Government Purchase Order.