2012 Survey Timeline
| 2012 AFRTS Worldwide Audience Survey Timeline | ||||
| Activity | Days | Cume | Phase | |
| Totals | Completion |
Date
| Phase One - Initial Survey Development | ||
| Contract Award | ||
| Initial Orientation & Coordination Workshop at DMA HQ (1 workday) | ||
| Contractor visits AFN-BC | ||
| Contractor develops and submits initial survey methodology | ||
| Govt reviews and responds to initial survey methodology | 4 | |
| Contractor revises and submits survey methodology | ||
| Govt reviews and responds to revised survey methodology | 3 | |
| Contractor develops initial survey instrument(s) | ||
| Govt reviews and responds to initial survey instrument(s) | 5 | |
| Contractor revises and submits survey instrument(s) | ||
| Contractor tests survey instrument(s) | ||
| Govt sends survey instrument(s) to DMDC/WHS for review | 1 | |
| DMDC/WHS review survey instrument (30 workdays) | 30 | |
| Govt receives and coordinates DMDC/WHS comments and required revisions | 1 | |
| Contractor presents preliminary analysis and report based upon survey instrument design and test | ||
| Govt provides survey revisions | 1 | |
| Contractor submits final draft of survey instrument(s) | ||
| Govt reviews and accepts survey instrument(s) | 2 | |
| Phase Total | ||
| Phase Two - Final Survey Development | ||
| Govt requests names/addresses from DMDC | 1 | |
| DMDC develops and provides names/addresses | 10 | |
| Govt provides names/addresses to Contractor | 1 | |
| Contractor prepares introductory cards/e-mail for invited participants | ||
| Contractor prepares website for participant use | ||
| Phase Total | ||
| Phase Three - Conduct Survey | ||
| Contractor mails/e-mails initial survey invitations | ||
| Contractor receives and monitors survey returns | ||
| Contractor sends survey reminders | ||
| Contractor receives and monitors additional survey returns | ||
| Contractor tabulates and analyzes survey returns | ||
| Phase Total | ||
| Phase Four - Final Report | ||
| Contractor submits initial draft of data tables, executive summary,survey report and recommendations | ||
| Govt reviews initial draft and submits comments | 5 | |
| Contractor revises draft report and recommendations | ||
| Contractor provides briefing and all final deliverables | ||
| Phase Total | ||
| Project Complete | 30-Apr-13 | |
| *Accomodations should be made for the Thanksgiving and Christmas/New Year holidays. |