Boots_Q A.pdf

PDF 16 KB Posted

Attached to
Bates Uniform Footwear Federal contract opportunity
Solicitation number
HQ0034-15-R-0128
Issued by
DOD Washington Headquarters Service

About this file

Please see that attached responses to questions.

View the file

Other files for this federal contract opportunity

Other files attached to Bates Uniform Footwear, newest first.
File Type Posted
HQ0034-15-R-0128_AMD_1.pdf PDF
SOW_PLC2_Boot_Requirement_20152307_AMD_1.pdf PDF
Brand_Name_Justification_for_PFPA_Boots_FINAL.pdf PDF
HQ0034-15-R-0128.pdf PDF
SOW_PLC2_Boot_Requirement_20152007.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HQ0034-15-R-0128

Questions & Answers

1. Please advise how many total days the shoe-mobile is expected to be available to provide this service (in total - all sites combined). It appears to be 2 days in week 1 (Monday and Tuesday), 2 days in week 2 (Wednesday and Thursday), and then undetermined in week 3.

ANSWER: Week one will be spent entirely at the Raven Rock Mountain Complex. Week two will be spent entirely at the Pentagon (PLC2). Week Three will be used as a “make up” week with two days spent at each location.

2. Please advise how payment will be made for the boots. We expect we will issue an invoice against a PO issued by your organization. We expect your organization would then send us a check as payment. Please confirm if this is accurate.

ANSWER: The chosen vendor will be expected to invoice against the contract via iRAPT formally known as wide area work flow.

3. Where is the Raven Rock Mountain Complex located?

ANSWER: To arrive at the front gate use address: 450 Harbaugh Valley Rd, Fairfield, PA 17320.

4. Bates manufactures boots with and without a safety toe cap. Do you require safety toe boots or soft toe boots?

ANSWER: Soft toe boots are required.

5. Please clarify the service schedule. Are you planning on outfitting all 800 staff members within a three week period of time, or do you expect weekly service all year long?

ANSWER: It is expected that all 800 staff member will be fitted within a 5 week time frame. This will be an amendment from the 3 week time frame given in the solicitation Scope of Work.

Schedule

WEEK WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5

Make Up

WEEK 5

Make Up

LOCATION PLC2 RRMC PLC2 PLC2 PLC2 RRMC (or

PLC2)

DAY Mon-Fri Tues - Fri Mon-Fri Mon-Fri Mon Wed-Fri

Tues

TIME 12PM-

12AM

10AM-

10PM

12PM-

12AM

10AM-

10PM

8AM-8PM 10AM-10PM

6. Will you please extend the due date of the solicitation by one week to allow sufficient time to prepare a response?

ANSWER: The response date will be extended. Please see amendment 1.