Highway Safety Improvement Program (HSIP) Crosswalk Improvement Project
This is a project description document for the Highway Safety Improvement Program (HSIP) Crosswalk Improvement Project in California. The project encompasses crosswalk improvements at six intersections: LaCadena Drive at B Street, LaCadena Drive at D Street, LaCadena Drive at E Street, LaCadena Drive at Hanna Street, Ninth Street at D Street, and Washington Street at RV Center Drive (West). The scope of work includes installation of Rapid Rectangular Flashing Beacons (RRFB), traffic signs, ADA-compliant ramps, and pavement striping at each location. The work is designed to enhance pedestrian safety and accessibility at these high-traffic intersections through standardized safety improvements.
The project is funded through the Highway Safety Improvement Program, a federal-state partnership focused on reducing traffic fatalities and serious injuries. Specific details regarding contract duration, bidding deadlines, award dates, pricing structures, and any contractor set-asides or incumbent information are not detailed in the available project overview documentation.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF COLTON
PUBLIC WORKS AND UTILITY SERVICES DEPARTMENT
160 S 10TH STREET, COLTON, CA 92324
CONTRACT DOCUMENTS & SPECIFICATIONS
FOR:
HIGHWAY SAFETY IMPROVEMENT PROGRAM (HSIP)
CROSSWALK IMPROVEMENT PROJECT - HSIPSL-5065(035):
1. LaCadena Drive at B Street
2. LaCadena Drive at D Street
3. LaCadena Drive at E Street
4. LaCadena Drive at Hanna Street
5. Ninth Street at D Street
6. Washington Street at RV Center Drive (West)
BID PUBLISHED:
BIDS MUST BE SUBMITTED
ONLINE BY:
BID OPENING DATE:
Sept. 23 & 30, 2026
Oct. 15, 2026, 3:00 P.M.
Oct. 15, 2026, 3:00 P.M.
CITY OF COLTON
PUBLIC WORKS AND UTILITY SERVICES DEPARTMENT
CONTRACT DOCUMENTS & SPECIFICATIONS
FOR:
Highway Safety Improvement Program (HSIP) Crosswalk Improvement Project - HSIPSL-5065(035)
Prepared Under the Supervision of:
Victor Ortiz, P.E., City Engineer Date
Sept. 10, 2026
TABLE OF CONTENTS
Page No.
- i -
NOTICE INVITING BIDS
INSTRUCTIONS TO BIDDERS
BID FORM
BID SCHEDULE
BID BOND
DESIGNATION OF SUBCONTRACTORS
INFORMATION REQUIRED OF BIDDERS
NON-COLLUSION AFFIDAVIT
CONTRACT
LABOR CODE CERTIFICATION
CONTRACTOR REGISTRATION CERTIFICATION
PERFORMANCE BOND
PAYMENT BOND (LABOR AND MATERIALS)
GENERAL CONDITIONS
ARTICLE 1. DEFINITIONS
ARTICLE 2. CONTRACT DOCUMENTS
ARTICLE 3. CONTRACTS DOCUMENTS: COPIES & MAINTENANCE
ARTICLE 4. DETAIL DRAWINGS AND INSTRUCTIONS
ARTICLE 5. EXISTENCE OF UTILITIES AT THE WORK SITE
ARTICLE 6. SCHEDULE
ARTICLE 7. SUBSTITUTIONS
ARTICLE 8. SHOP DRAWINGS
ARTICLE 9. SUBMITTALS
ARTICLE 10. MATERIALS
ARTICLE 11. CONTRACTOR’S SUPERVISION
ARTICLE 12. WORKERS
ARTICLE 13. SUBCONTRACTORS
ARTICLE 14. PERMITS AND LICENSES
ARTICLE 15. UTILITY USAGE
ARTICLE 16. INSPECTION FEES FOR PERMANENT UTILITIES
ARTICLE 17. TRENCHES
ARTICLE 18. DIVERSION OF RECYCLABLE WASTE MATERIALS
ARTICLE 19. REMOVAL OF HAZARDOUS MATERIALS
ARTICLE 20. SANITARY FACILITIES
ARTICLE 21. AIR POLLUTION CONTROL
ARTICLE 22. COMPLIANCE WITH STATE STORM WATER PERMIT
ARTICLE 23. CLEANING UP
ARTICLE 24. LAYOUT AND FIELD ENGINEERING
ARTICLE 25. EXCESSIVE NOISE
ARTICLE 26. TESTS AND INSPECTIONS
ARTICLE 27. PROTECTION OF WORK AND PROPERTY
ARTICLE 28. CONTRACTORS MEANS AND METHODS
ARTICLE 29. INSPECTOR’S FIELD OFFICE
ARTICLE 30. AUTHORIZED REPRESENTATIVES
ARTICLE 31. HOURS OF WORK
ARTICLE 32. PAYROLL RECORDS
ARTICLE 33. PREVAILING RATES OF WAGES
ARTICLE 34. EMPLOYMENT OF APPRENTICES
ARTICLE 35. NONDISCRIMINATION/EQUAL EMPLOYMENT OPPORTUNITY
TABLE OF CONTENTS
Page No.
- ii -
ARTICLE 36. LABOR/EMPLOYMENT SAFETY
ARTICLE 37. EMPLOYER’S LIABILITY INSURANCE
ARTICLE 38. COMMERCIAL GENERAL LIABILITY INSURANCE
ARTICLE 39. AUTOMOBILE LIABILITY INSURANCE
ARTICLE 40. BUILDER’S RISK [“ALL RISK”]
ARTICLE 41. FORM AND PROOF OF CARRIAGE OF INSURANCE
ARTICLE 42. TIME FOR COMPLETION AND LIQUIDATED DAMAGES
ARTICLE 43. COST BREAKDOWN AND PERIODIC ESTIMATES
ARTICLE 44. MOBILIZATION
ARTICLE 45. PAYMENTS
ARTICLE 46. PAYMENTS WITHHELD AND BACKCHARGES
ARTICLE 47. CHANGES AND EXTRA WORK
ARTICLE 48. OCCUPANCY
ARTICLE 49. INDEMNIFICATION
ARTICLE 50. RECORD (“AS BUILT”) DRAWINGS
ARTICLE 51. RESOLUTION OF CONSTRUCTION CLAIMS
ARTICLE 52. CITY’S RIGHT TO TERMINATE CONTRACT
ARTICLE 53. WARRANTY AND GUARANTEE
ARTICLE 54. DOCUMENT RETENTION & EXAMINATION
ARTICLE 55. SOILS INVESTIGATIONS
ARTICLE 56. SEPARATE CONTRACTS
ARTICLE 57. NOTICE AND SERVICE THEREOF
ARTICLE 58. NOTICE OF THIRD PARTY CLAIMS
ARTICLE 59. STATE LICENSE BOARD NOTICE
ARTICLE 60. INTEGRATION
ARTICLE 61. ASSIGNMENT
ARTICLE 62. CHANGE IN NAME AND NATURE OF CONTRACTOR’S LEGAL ENTITY
ARTICLE 63. ASSIGNMENT OF ANTITRUST ACTIONS
ARTICLE 64. PROHIBITTED INTERESTS
ARTICLE 65. LAWS AND REGULATIONS
ARTICLE 66. PATENET FEES OR ROYALTIES
ARTICLE 67. OWNERSHIP OF DRAWING
ARTICLE 68. NOTICE OF TAXABLE POSSESSORY
SPECIAL PROVISIONS .............................................................................. SP-1 TECHNICAL PROVISIONS .......................................................................TP-1
DAVIS BACON PREVAILING WAGE
NOTICE INVITING BIDS
CITY OF COLTON
NOTICE INVITING BIDS
The City of Colton, Public Works Department (“City”) will receive electronic bids for the Highway Safety Improvement Program (HSIP) Crosswalk Improvement Project - HSIPSL-5065(035) via the City of Colton’s Bidnet Direct vendor portal website at: www.bidnetdirect.com/california/cityofcolton no later than 3:00 P.M., October 15, 2026. Bids received after this time will not be accepted. Bids shall be valid for 60 calendar days after the bid opening date.
Bids must be prepared and submitted on the approved Bid forms and in the manner prescribed in the Instructions to Bidders.
WORK: The Works consists of, but not limited to crosswalk improvements including installation of Rapid Rectangular Flashing Beacon (RRFB), traffic signs, ADA ramps and striping at the following intersections:
1. LaCadena Drive at B Street
2. LaCadena Drive at D Street
3. LaCadena Drive at E Street
4. LaCadena Drive at Hanna Street
5. Ninth Street at D Street
6. Washington Street at RV Center Drive (West)
The project shall be completed within 90 working days from the start date established in the Notice to Proceed .
The City of Colton hereby affirmatively ensures that minority business enterprises will be afforded full opportunity to submit Bids in response to this Notice, and that minorities nor minority business enterprises will not be discriminated against on the basis of race, color, national origin, ancestry, sex, or religion in any consideration leading to the award of contract. For further information, please see the form titled “Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity (Executive Order 11246)” within the Bid Documents.
Bidders may obtain a copy of the Contract Documents, Project documents, and plan holders via the City of Colton’s Bidnet Direct vendor portal website at: www.bidnetdirect.com/california/cityofcolton beginning September, 2026.
Bids submitted online must be accompanied by a digital copy of the Bid Bond in favor of the City in an amount not less than ten percent (10%) of the submitted Total Bid Price. The apparent low bidder will be required to provide the original bid bond within 7 days of the bid opening.
Each bid shall be accompanied by the security referred to in the Contract Documents, the non-collusion affidavit, the list of proposed subcontractors, and all additional documentation required by the Instructions to Bidders.
The successful bidder will be required to furnish the City with a Performance Bond equal to 100% of the successful bid, and a Payment (Labor and Materials) Bond equal to 100% of the successful bid, prior to execution of the Contract. All bonds are to be secured from a surety that meets all of the State of California bonding requirements, as defined in Code of Civil Procedure Section 995.120, and is admitted by the State of California.
http://www.bidnetdirect.com/california/cityofcolton
NOTICE INVITING BIDS
Pursuant to Public Contract Code Section 22300, the successful bidder may substitute certain securities for funds withheld by City to ensure his performance under the Contract.
The Director of Industrial Relations has determined the general prevailing rate of per diem wages in the locality in which this work is to be performed for each craft or type of worker needed to execute the Contract which will be awarded to the successful bidder, copies of which are on file and will be made available to any interested party upon request at Public Works Department of City of Colton or online at http://www.dir.ca.gov/dlsr. A copy of these rates shall be posted by the successful bidder at the job site.
The successful bidder and all subcontractor(s) under him, shall comply with all applicable Labor Code provisions, which include, but are not limited to the payment of not less than the required prevailing rates to all workers employed by them in the execution of the Contract, the employment of apprentices, the hours of labor and the debarment of contractors and subcontractors. Each bidder shall be a licensed contractor pursuant to the Business and Professions Code and shall be licensed in the following appropriate classification(s) of contractor’s license(s), for the work bid upon, and must maintain the license(s) throughout the duration of the Contract: Bidders shall possess the following California Contractor’s license in order to perform the Work of this Project: Class “A” or a letter from Contractor’s Licensing Board outlining the combination of various licenses necessary to perform all the work at the time the bid is submitted to the City. Pursuant to Public Contract Code Section 3400(b), if the City has made any findings designating certain materials, products, things, or services by specific brand or trade name, such findings and the materials, products, things, or services and their specific brand or trade names will be set forth in the Special Conditions. Award of Contract: The City shall award the Contract for the Project to the lowest responsive, responsible bidder as determined from the base bid alone by the City.
The City reserves the right to reject any or all bids or to waive any irregularities or informalities in any bids or in the bidding process.
“CONTRACTORS MUST LIST ALL OF THEIR SUBCONTRACTORS REGARDLESS OF THE
DOLLAR AMOUNT”. This requirement supersedes Section 9 Designation of subcontractors of the Notice of Inviting Bids.
All questions must be emailed via the City of Colton’s BidNet page at:
www.bidnetdirect.com/california/cityofcolton. Questions must be submitted by October 15, 2026.
Published Date: September 23 & 30, 2026 http://www.bidnetdirect.com/california/cityofcolton
INSTRUCTION TO BIDDERS
CITY OF COLTON
DEPARTMENT OF PUBLIC WORKS
INSTRUCTIONS TO BIDDERS
1. AVAILABILITY OF CONTRACT DOCUMENTS
Bids must be submitted to the City on the Bid Forms which are a part of the Bid Package for the Project.
Prospective bidders may obtain one (1) complete set (hardcopy) of Contract Documents for a fee of $10.00. Contract Documents may be obtained from the City at the location(s) and at the time(s) indicated in the Notice Inviting Bids. Prospective bidders are encouraged to telephone in advance to determine the availability of Contract Documents. Any applicable charges for the Contract Documents are outlined in the Notice Inviting Bids. The City may also make the Contract Documents available for review at one or more plan rooms, as indicated in the Notice Inviting Bids.
2. EXAMINATION OF CONTRACT DOCUMENTS
The City has made copies of the Contract Documents available, as indicated above. Bidders shall be solely responsible for examining the Project Site and the Contract Documents, including any Addenda issued during the bidding period, and for informing itself with respect to local labor availability, means of transportation, necessity for security, laws and codes, local permit requirements, wage scales, local tax structure, contractors’ licensing requirements, availability of required insurance, and other factors that could affect the Work. Bidders are responsible for consulting the standards referenced in the Contract.
Failure of Bidder to so examine and inform itself shall be at its sole risk, and no relief for error or omission will be given except as required under State law.
3. INTERPRETATION OF CONTRACT DOCUMENTS
Discrepancies in, and/or omissions from the Plans, Specifications or other Contract Documents or questions as to their meaning shall be immediately brought to the attention of the City by submission of a written request for an interpretation or correction to the City. Such submission, if any, must be on the BidNet page for the project.
Any interpretation of the Contract Documents will be made only by written addenda duly issued online on the Bidnet project page. The City will not be responsible for any explanations or interpretations provided in any other manner. No person is authorized to make any oral interpretation of any provision in the Contract Documents to any bidder, and no bidder should rely on any such oral interpretation.
Bids shall include complete compensation for all items that are noted in the Contract Documents as the responsibility of the Contractor.
4. INSPECTION OF SITE
Each prospective bidder is responsible for fully acquainting itself with the conditions of the Project Site (which may include more than one site), as well as those relating to the construction and labor of the Project, to fully understand the facilities, difficulties and restrictions which may impact the cost or effort required to complete the Project.
5. ADDENDA
The City reserves the right to revise the Contract Documents prior to the bid opening date. Revisions, if any, shall be made by written Addenda posted on the Bidnet project page. All addenda issued by the City shall be included in the bid and made part of the Contract Documents. Pursuant to Public Contract Code Section 4104.5, if the City issues an Addendum which includes material changes to the Project less than 72 hours prior to the deadline for submission of bids, the City will extend the deadline for submission of bids. The City may determine, in its sole discretion, whether an Addendum warrants postponement of the bid submission date. Please Note: Bidders are responsible for ensuring that they have reviewed any and all Addenda. To this end, each bidder should verify on the BidNet project page, all Addenda issued, if any, prior to the bid opening.
6. ALTERNATE BIDS (IF APPLICABLE)
If alternate bid items are called for in the Contract Documents, the lowest bid will be determined on the basis of the base bid only. However, the City may choose to award the contract on the basis of the base bid alone or the base bid and any alternate or combination of alternates. The time required for completion of the alternate bid items has been factored into the Contract duration and no additional Contract time will be awarded for any of the alternate bid items. The City may elect to include one or more of the alternate bid items, or to otherwise remove certain work from the Project scope of work, accordingly each Bidder must ensure that each bid item contains a proportionate share of profit, overhead and other costs or expenses which will be incurred by the Bidder.
7. COMPLETION OF BID FORMS
Bids shall only be prepared using copies of the Bid Forms which are included in the Contract Documents.
The use of substitute bid forms other than clear and correct photocopies of those provided by the City will not be permitted. Bids shall be executed by an authorized signatory as described in these Instructions to Bidders. In addition, Bidders shall fill in all blank spaces (including inserting “N/A” where applicable) and initial all interlineations, alterations, or erasures to the Bid Forms. Bidders shall neither delete, modify, nor supplement the printed matter on the Bid Forms nor make substitutions thereon. use of black or blue ink, indelible pencil or a typewriter is required. Deviations in the bid form may result in the bid being deemed non-responsive.
8. MODIFICATIONS OF BIDS
Each Bidder shall submit its Bid in strict conformity with the requirements of the Contract Documents.
Unauthorized additions, modifications, revisions, conditions, limitations, exclusions or provisions attached to a Bid may render it non-responsive and may cause its rejection. Bidders shall neither delete, modify, nor supplement the printed matter on the Bid Forms, nor make substitutions thereon. Oral, telephonic and electronic modifications will not be considered, unless the Notice Inviting Bids authorizes the submission of electronic bids and modifications thereto and such modifications are made in accordance with the Notice Inviting Bids.
9. DESIGNATION OF SUBCONTRACTORS
Pursuant to State law, the Bidders must designate the name and location of each subcontractor who will perform work or render services for the Bidder in an amount that exceeds one-half of one percent (1/2%) of the Bidder’s Total Bid Price or $10,000, as well as the portion of work each such subcontractor will perform on the form provided herein by the City. No additional time will be provided to bidders to submit any of the requested information in the Designation of Subcontractor form.
10. LICENSING REQUIREMENTS
Pursuant to Section 7028.15 of the Business and Professions Code and Section 3300 of the Public Contract
Code, all bidders must possess proper licenses for performance of this Contract. Subcontractors must possess the appropriate licenses for each specialty subcontracted. Pursuant to Section 7028.5 of the Business and Professions Code, the City shall consider any bid submitted by a contractor not currently licensed in accordance with state law and pursuant to the requirements found in the Contract Documents to be nonresponsive, and the City shall reject the Bid. The City shall have the right to request, and Bidders shall provide within five (5) calendar days, evidence satisfactory to the City of all valid license(s) currently held by that Bidder and each of the Bidder’s subcontractors, before awarding the Contract. Please also note that, pursuant to Public Contract Code Section 20676, sellers of "mined material" must be on an approved list of sellers published pursuant to Public Resources Code Section 2717(b) in order to supply mined material for this Contract.
11. SIGNING OF BIDS
All Bids submitted shall be executed by the Bidder or its authorized representative. Bidders may be asked to provide evidence in the form of an authenticated resolution of its Board of Directors or a Power of Attorney evidencing the capacity of the person signing the Bid to bind the Bidder to each Bid and to any Contract arising therefrom.
If a Bidder is a joint venture or partnership, it may be asked to submit an authenticated Power of Attorney executed by each joint venturer or partner appointing and designating one of the joint venturers or partners as a management sponsor to execute the Bid on behalf of Bidder. Only that joint venturer or partner shall execute the Bid. The Power of Attorney shall also: (1) authorize that particular joint venturer or partner to act for and bind Bidder in all matters relating to the Bid; and (2) provide that each venturer or partner shall be jointly and severally liable for any and all of the duties and obligations of Bidder assumed under the Bid and under any Contract arising therefrom. The Bid shall be executed by the designated joint venturer or partner on behalf of the joint venture or partnership in its legal name.
12. BID GUARANTEE (BOND)
Each bid shall be accompanied by: (a) cash; (b) a certified check made payable to the City; (c) a cashier’s check made payable to the City; or (d) a bid bond payable to the City executed by the bidder as principal and surety as obligor in an amount not less than 10% of the maximum amount of the bid. Personal sureties and unregistered surety companies are unacceptable. The surety insurer shall be California admitted surety insurer, as defined in Code of Civil Procedure Section 995.120. The cash, check or bid bond shall be given as a guarantee that the bidder shall execute the Contract if it be awarded to the bidder, shall provide the payment and performance bonds and insurance certificates and endorsements as required herein within ten (10) calendar days after notification of the award of the Contract to the bidder. Failure to provide the required documents may result in forfeiture of the bidder’s bid deposit or bond to the City and the City may award the Contract to the next lowest responsive, responsible bidder, or may call for new bids.
13. SUBMISSION OF SEALED BIDS
Once the Bid and supporting documents have been completed and signed as set forth herein, they shall be submitted on the BidNet project page. No oral, paper or telephonic bids will be considered. No forms transmitted via the internet, e-mail, facsimile, or any other electronic means will be considered unless specifically authorized by City as provided herein, DELIVERY AND OPENING OF BIDS
Bids will be received by the City online via the BidNet project page at the web address shown in the Notice Inviting Bids up to the date and time shown therein. It is the Bidder’s sole responsibility to ensure that its Bid is uploaded as specified. Bids may be submitted earlier than the dates(s) and time(s) indicated.
Bids will be automatically tabulated on the BidNet project page at the date and time stated in the Notice Inviting Bids. The City may in its sole discretion, elect to postpone the opening of the submitted Bids.
City reserves the right to reject any or all Bids and to waive any informality or irregularity in any Bid. In the event of a discrepancy between the written amount of the Bid Price and the numerical amount of the Bid Price, the written amount shall govern.
14. WITHDRAWAL OF BID
Prior to bid opening, a Bid may be withdrawn by the Bidder on the BidNet project page.
15. BASIS OF AWARD; BALANCED BIDS
The City shall award the Contract to the lowest responsive, responsible Bidder submitting a responsive Bid. The City may reject any Bid which, in its opinion when compared to other bids received or to the City’s internal estimates, does not accurately reflect the cost to perform the Work. The City may reject as non-responsive any bid which unevenly weights or allocates costs, including but not limited to overhead and profit to one or more particular bid items.
16. DISQUALIFICATION OF BIDDERS; INTEREST IN MORE THAN ONE BID
No bidder shall be allowed to make, submit or be interested in more than one bid. However, a person, firm, corporation or other entity that has submitted a subproposal to a bidder, or that has quoted prices of materials to a bidder, is not thereby disqualified from submitting a subproposal or quoting prices to other bidders submitting a bid to the City. No person, firm, corporation, or other entity may submit subproposal to a bidder, or quote prices of materials to a bidder, when also submitting a prime bid on the same Project.
17. INSURANCE REQUIREMENTS
The successful bidder shall procure the insurance in the form and in the amount specified in the Contract Documents.
18. AWARD PROCESS
Once all Bids are opened and reviewed to determine the lowest responsive and responsible Bidder, the City Council may award the contract. The apparent successful Bidder should begin to prepare the following documents: (1) the Performance Bond; (2) the Payment (Labor and Materials) Bond; and (3) the required insurance certificates and endorsements. Once the City notifies the Bidder of the award, the Bidder will have ten (10) consecutive calendar days from the date of this notification to execute the Contract and supply the City with all of the required documents and certifications. Regardless whether the Bidder supplies the required documents and certifications in a timely manner, the Contract time will begin to run ten (10) calendar days from the date of the notification. Once the City receives all of the properly drafted and executed documents and certifications from the Bidder, the City shall issue a Notice to Proceed to that Bidder.
19. FILING OF BID PROTESTS
Bidders may file a “protest” of a Bid with the City’s City Engineer. In order for a Bidder’s protest to be considered valid, the protest must:
A. Be filed in writing within five (5) calendar days after the bid opening date;
B. Clearly identify the specific irregularity or accusation;
C. Clearly identify the specific City staff determination or recommendation being protested;
D. Specify, in detail, the grounds of the protest and the facts supporting the protest; and E. Include all relevant, supporting documentation with the protest at time of filing.
If the protest does not comply with each of these requirements, it will be rejected as invalid.
If the protest is valid, the City’s City Engineer, or other designated City staff member, shall review the basis of the protest and all relevant information. The City Engineer will provide a written decision to the protestor. The protestor may then appeal the decision of the City Engineer to the City Manager.
20. WORKERS COMPENSATION
Each bidder shall submit the Contractor’s Certificate Regarding Workers’ Compensation form.
21. SUBSTITUTION OF SECURITY
The Contract Documents call for monthly progress payments based upon the percentage of the work completed. The City will retain ten percent (10%) of each progress payment as provided by the Contract Documents. At the request and expense of the successful Bidder, the City will substitute securities for the amount so retained in accordance with Public Contract Code Section 22300.
22. PREVAILING WAGES
The City has obtained from the Director of the California (State) Department of Industrial Relations the general prevailing rate of per diem wages in the locality in which this work is to be performed for each craft or type of worker needed to execute the Contract. These rates are on file and available at Public Works Department or may be obtained online at http://www.dir.ca.gov/dlsr. Bidders are advised that a copy of these rates must be posted by the successful Bidder at the job site(s).
The requirements of the Davis-Bacon Act will apply to this project, and those requirements will be enforced. The prime contractor and subcontractors are required to pay their laborers and mechanics employed under this Contract, a wage not less than minimum wage classification as specified in both the Federal and State Wage Decision when the Contract amount for the Prime Contract exceeds $2,000. The higher of the two applicable wage classifications, either State Prevailing Wage or Davis-Bacon Federal Prevailing Wage, will be enforced for all work under this Contract. The prime contractor is responsible for ensuring subcontractor compliance with Davis-Bacon and related Act Requirements. The Federal Labor Standards Provisions (HUD 4010) apply to this project.”
A copy of the Davis-Bacon Federal Prevailing Wage, the date of which reflects the latest applicable modification at the time of this advertisement, is included in the Contract Documents & Specifications.
Bidders shall be notified, via Addendum, of modifications, if any, which supersede that included herein, up until a minimum of ten (10) days prior to the actual Bid Opening.
23. DEBARMENT OF CONTRACTORS AND SUBCONTRACTORS
In accordance with the provisions of the Labor Code, contractors or subcontractors may not perform work on a public works project with a subcontractor who is ineligible to perform work on a public project pursuant to Section 1777.1 or Section 1777.7 of the Labor Code. Any contract on a public works project entered into between a contractor and a debarred subcontractor is void as a matter of law. A debarred subcontractor may not receive any public money for performing work as a subcontractor on a public works contract. Any public money that is paid to a debarred subcontractor by the Contractor for the Project shall be returned to the City. The Contractor shall be responsible for the payment of wages to workers of a debarred subcontractor who has been allowed to work on the Project.
24. PERFORMANCE BOND AND PAYMENT (LABOR AND MATERIALS) BOND
REQUIREMENTS
Within the time specified in the Contract Documents, the Bidder to whom a Contract is awarded shall deliver to the City four identical counterparts of the Performance Bond and Payment (Labor and Materials) Bond in the form supplied by the City and included in the Contract Documents. Failure to do so may, in the sole discretion of City, result in the forfeiture of the Bid Guarantee. The surety supplying the bond must be an admitted surety insurer, as defined in Code of Civil Procedure Section 995.120, authorized to do business as such in the State of California and satisfactory to the City. The Performance Bond and the Payment (Labor and Materials) Bond shall be for one hundred percent (100%) of the Total Bid Price.
25. REQUEST FOR SUBSTITUTIONS
The successful bidder shall comply with the substitution request provisions set forth in the Special Conditions, including any deadlines for substitution requests which may occur prior to the bid opening date.
26. SALES AND OTHER APPLICABLE TAXES, PERMITS, LICENSES AND FEES
Contractor and its subcontractors performing work under this Contract will be required to pay California sales tax and other applicable taxes, and to pay for permits, licenses and fees required by the agencies with authority in the jurisdiction in which the work will be located, unless otherwise expressly provided by the Contract Documents.
27. EXECUTION OF CONTRACT
As required herein the Bidder to whom an award is made shall execute the Contract in the amount determined by the Contract Documents. The City may require appropriate evidence that the persons executing the Contract are duly empowered to do so.
END OF INSTRUCTIONS TO BIDDERS
BID FORM
BID FORM
NAME OF BIDDER:
The undersigned, hereby declare that we have carefully examined the location of the proposed Work, and have read and examined the Contract Documents, including all plans, specifications, and all addenda, if any, for the following Project:
Highway Safety Improvement Program (HSIP) Crosswalk Improvement Project - HSIPSL-5065(035)
We hereby propose to furnish all labor, materials, equipment, tools, transportation, and services, and to discharge all duties and obligations necessary and required to perform and complete the Project for the following TOTAL BID PRICE:
BASE
BID
BASE BID PRICE ( ITEM NO. 1 TO 12)
(IN WRITTEN FORM)
BID PRICE
(IN NUMBERS)
TOTAL
BID PRICE
In case of discrepancy between the written price and the numerical price, the written price shall prevail.
BID SCHEDULE
BID SCHEDULE
Highway Safety Improvement Program (HSIP) Crosswalk Improvement Project -
HSIPSL-5065(035)
TIME OF COMPLETION: 90 WORKING DAYS
Item Item Description Unit Quantity Unit Price Amount
1 Mobilization (3% of Total) LS 1 $ $ 2 Water Pollution Control LS 1 $ $ 3 Temporary Traffic Control LS 1 $ $ 4 Construction Survey and Staking LS 1 $ $ 5 Clearing, Grubbing and Removal LS 1 $ $ 6 Removal of Existing Striping and Signs (2,000 LF, 41 EA.) LS 1 $ $ 7 LaCadena Drive & Hanna Street (Sheet 2)
7a-1. Installation of RRFB & Signs on new Type 1A Pole EA 1 $ $ 7a-2. Installation of RRFB & Signs on Existing Light Pole EA 1 $ $ 7b. Install Thermoplastic Markings (57 LF) LS 1 $ $ 7c. Installation of Signs EA 5 $ $ 7d. Installation of Truncated Domes EA 1 $ $
8 LaCadena Drive & B Street (Sheet 2) 8a-1. Installation of RRFB & Signs on new Type 1A Pole EA 1 $ $ 8a-2. Installation of RRFB & Signs on Existing Light Pole EA 1 $ $ 8b. Install Thermoplastic Markings (57 LF) LS 1 $ $ 8c. Installation of Signs EA 5 $ $ 8e. Installation of ADA Ramp (complete) EA 1 $ $
9 LaCadena Drive & D Street (Sheet 3) 9a-1. Installation of RRFB & Signs on new Type 1A Pole EA 1 $ $ 9a-2. Installation of RRFB & Signs on Existing Light Pole EA 1 $ $ 9b. Install Thermoplastic Markings (57 LF) LS 1 $ $ 9c. Installation of Signs EA 5 $ $ 9d. Installation of Truncated Domes EA 1 $ $ 9e. Installation of ADA Ramp (complete) EA 1 $ $
10 LaCadena Drive & E Street (Sheet 3) 10a-1. Installation of RRFB & Signs on new Type 1A Pole EA 1 $ $ 10a-2. Installation of RRFB & Signs on Existing Light Pole EA 1 $ $ 10b. Install Thermoplastic Markings (57 LF) LS 1 $ $ 10c. Installation of Signs EA 5 $ $ 10d. Installation of Truncated Domes EA 2 $ $
11 Ninth Street & D Street (Sheet 4) 11a-1. Installation of RRFB & Signs on new Type 1A Pole EA 2 $ $ 11c. Installation of Signs EA 4 $ $ 11d. Installation of Truncated Domes EA 2 $ $
12 Washington Street & RV Center Drive (West) (Sheet 4) 12a-1. Installation of RRFB & Signs on new Type 1A Pole EA 2 $ $
12b. Install Thermoplastic Markings (739 LF) LS 1 $ $ 12c. Installation of Signs EA 6 $ $ 12e. Installation of ADA Ramp (complete) EA 2 $ $
Total = $
Total Bid Price in Numbers
Total Bid Price in Written Form
In case of discrepancy between the unit price and the item cost set forth for a unit basis item, the unit price shall prevail and, shall be utilized as the basis for determining the lowest responsive, responsible bidder.
However, if the amount set forth as a unit price is ambiguous, unintelligible or uncertain for any cause, or is omitted, or is the same amount as the entry in the “Item Cost” column, then the amount set forth in the “Item Cost” column for the item shall prevail and shall be divided by the estimated quantity for the item and the price thus obtained shall be the unit price. Final payment shall be determined by the Engineer from measured quantities of work performed based upon the unit price. In case of discrepancy between the written price and the numerical price, the written price shall prevail.
The undersigned agrees that this Bid Form constitutes a firm offer to the City which cannot be withdrawn for the number of calendar days indicated in the Notice Inviting Bids from and after the bid opening, or until a Contract for the Work is fully executed by the City and a third party, whichever is earlier.
The Contract duration shall commence on the date stated in the City’s Notice to Proceed, and shall be completed by the Contractor in the time specified in the Contract Documents. In no case shall the Contractor commence construction prior to the date stated in the City’s Notice to Proceed.
Bidder certifies that it is licensed in accordance with the law providing for the registration of Contractors, License No. _________, Expiration Date _______, class of license _____. If the bidder is a joint venture, each member of the joint venture must include the above information.
The undersigned acknowledges receipt, understanding and full consideration of the following addenda to the Contract Documents.
1. Addenda No. __________thru _____________ (If applicable)
2. Attached is the required bid security in the amount of not less than 10% of the Total Bid Price.
3. Attached is the fully executed Non-Collusion Affidavit form.
4. Attached is the completed Designation of Subcontractors form.
5. Attached is the completed Bidder Information Form.
6. Attached is the completed Contractor’s Certificate Regarding Workers’ Compensation form.
7. Bidder acknowledges and understands that, pursuant to Public Contract Code Section 20676, sellers of "mined material" must be on an approved list of sellers published pursuant to Public Resources Code Section 2717(b) in order to supply mined material for this Contract.
I hereby certify under penalty of perjury under the laws of the State of California that all of the information submitted in connection with this Bid and all of the representations made herein are true and correct.
Name of Bidder
Signature
Name and Title
Dated
BID BOND
BID BOND
The makers of this bond are, __________________________________________________________, as Principal, and __________________________________________________________, as Surety and are held and firmly bound unto the City of Colton, hereinafter called the City, in the penal sum of TEN PERCENT (10%) OF THE TOTAL BID PRICE of the Principal submitted to CITY for the work described below, for the payment of which sum in lawful money of the United States, well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH that whereas the Principal has submitted the accompanying bid dated ____________ , 20 ____, for
Highway Safety Improvement Program (HSIP) Crosswalk Improvement
Project - HSIPSL-5065(035)
If the Principal does not withdraw its bid within the time specified in the Contract Documents; and if the Principal is awarded the Contract and provides all documents to the City as required by the Contract Documents; then this obligation shall be null and void. Otherwise, this bond will remain in full force and effect.
Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract Documents shall in affect its obligation under this bond, and Surety does hereby waive notice of any such changes.
In the event a lawsuit is brought upon this bond by the City and judgment is recovered, the Surety shall pay all litigation expenses incurred by the City in such suit, including reasonable attorneys’ fees, court costs, expert witness fees and expenses.
IN WITNESS WHEREOF, the above-bound parties have executed this instrument under their several seals this _______ day of ________________, 20____, the name and corporate seal of each corporation.
(Corporate Seal)
Principal
By Title
(Corporate Seal) Surety
By Attorney-in-Fact
(Attach Attorney-in-Fact Certificate) Title
BID BOND
STATE OF CALIFORNIA )
) ss.
CITY OF ___________ )
On this ________ day of ___________________, in the year 20____, before me, ___________________________, a Notary Public in and for said state, personally appeared _________________________________, known to me to be the person whose name is subscribed to the within instrument as the Attorney-In-Fact of the (Surety) acknowledged to me that he subscribed the name of the ___________________________ (Surety) thereto and his own name as Attorney-In-Fact.
Notary Public in and for said State
(SEAL)
Commission expires: _______________
NOTE: A copy of the Power-of-Attorney to local representatives of the bonding company must be attached hereto.
DESIGNATION OF SUBCONTRACTORS
DESIGNATION OF SUBCONTRACTORS
In compliance with the Subletting and Subcontracting Fair Practices Act of the Public Contract Code of the State of California, each bidder shall set forth below: (a) the name and the location of the place of business and (b) the portion of the work which will be done by each subcontractor who will perform work or labor or render service to the Contractor in or about the construction of the work in an amount in excess of one-half of one percent (1/2%) of the Contractor’s Total Bid Price.
Notwithstanding the foregoing, if the work involves streets and highways, then the Contractor shall list each subcontractor who will perform work or labor or render service to Contractor in or about the work in an amount in excess of one-half of one percent (1/2%) of the Contractor’s Total Bid Price or $10,000, whichever is greater. No additional time shall be granted to provide the below requested information.
If no subcontractor is specified, for a portion of the work, or if more than one subcontractor is specified for the same portion of Work, to be performed under the Contract in excess of one-half of one percent (1/2%) of the Contractor’s Total Bid Price or $10,000, whichever is greater if the work involves streets or highways, then the Contractor shall be deemed to have agreed that it is fully qualified to perform that Work, and that it shall perform that portion itself.
Portion of the Work Subcontractor Location of Business % of the Work
DESIGNATION OF SUBCONTRACTORS
Portion of the Work Subcontractor Location of Business % of the Work
Name of Bidder
Signature
Name and Title
INFORMATION REQUIRED OF BIDDERS
INFORMATION REQUIRED OF BIDDERS
A. INFORMATION ABOUT BIDDER
[**Indicate not applicable (“N/A”) where appropriate.**]
NOTE: Where Bidder is a joint venture, pages shall be duplicated and information provided for all parties to the joint venture.
1.0 Name of Bidder: ___________________________________________
2.0 Type, if Entity: ___________________________________________
3.0 Bidder Address: ___________________________________________
Facsimile Number Telephone Number
4.0 How many years has Bidder’s organization been in business as a Contractor?
5.0 How many years has Bidder’s organization been in business under its present name?
5.1 Under what other or former names has Bidder’s organization operated?:______________________________________________
6.0 If Bidder’s organization is a corporation, answer the following:
6.1 Date of Incorporation: ________________________________
6.2 State of Incorporation: ________________________________
6.3 President’s Name: ________________________________
6.4 Vice-President’s Name(s): ________________________________
6.5 Secretary’s Name: ________________________________
6.6 Treasurer’s Name: ________________________________
7.0 If an individual or a partnership, answer the following:
7.1 Date of Organization: ______________________________________
7.2 Name and address of all partners (state whether general or limited partnership):
8.0 If other than a corporation or partnership, describe organization and name principals:
9.0 List other states in which Bidder’s organization is legally qualified to do business.
10.0 What type of work does the Bidder normally perform with its own forces?
11.0 Has Bidder ever failed to complete any work awarded to it? If so, note when, where, and why:
12.0 Within the last five years, has any officer or partner of Bidder’s organization ever been an officer or partner of another organization when it failed to complete a contract? If so, attach a separate sheet of explanation:
14.0 List Trade References:
15.0 List Bank References (Bank and Branch Address):
16.0 Name of Bonding Company and Name and Address of Agent:
B. LIST OF CURRENT PROJECTS (Backlog)
[**Duplicate Page if needed for listing additional current projects.**]
Project Description of Bidder’s Work
Completion Date
Cost of Bidder’s Work
Contact Name & Phone
C. LIST OF COMPLETED PROJECTS - LAST THREE YEARS
[**Duplicate Page if needed for listing additional completed projects.**]
Please include only those projects which are similar enough to demonstrate Bidder’s ability to perform the required Work.
Project Client Description of Bidder’s Work
Period of Performance
Cost of Bidder’s Work
Contact Name & Phone
D. EXPERIENCE AND TECHNICAL QUALIFICATIONS QUESTIONNAIRE
Personnel:
The Bidder shall identify the key personnel to be assigned to this project in a management, construction supervision or engineering capacity.
1. List each person’s job title, name and percent of time to be allocated to this project:
2. Summarize each person’s specialized education:
3. List each person’s years of construction experience relevant to the project:
4. Summarize such experience:
Bidder agrees that personnel named in this Bid will remain on this Project until completion of all relevant Work, unless substituted by personnel of equivalent experience and qualifications approved in advance by the City.
Additional Bidder’s Statements:
If the Bidder feels that there is additional information which has not been included in the questionnaire above, and which would contribute to the qualification review, it may add that information in a statement here or on an attached sheet, appropriately marked:
E. VERIFICATION AND EXECUTION
These Bid Forms shall be executed only by a duly authorized official of the Bidder:
I declare under penalty of perjury under the laws of the State of California that the foregoing information is true and correct:
Name of Bidder
Signature
Name
NON-COLLUSION AFFIDAVIT
NON-COLLUSION AFFIDAVIT
I, , being first duly sworn, deposes and says that he is of ______________________ the party making the attached bid; that the bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation; that the bid is genuine and not collusive or sham; that the bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid, and has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or that anyone shall refrain from bidding; that the bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder, or to secure any advantage against the public body awarding the contract of anyone interested in the proposed contract; that all statements contained in the bid are true; and, further, that the bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, or paid, and will not pay, any fee to any corporation, partnership, company association, organization, bid depository, or to any member or agent thereof to effectuate a collusive or sham bid.
I certify (or declare) under penalty of perjury under the laws of the State of California that the foregoing is true and correct.
Name of Bidder
Signature
Name
CONTRACT
CITY OF COLTON
SHORT FORM CONSTRUCTION CONTRACT
HIGHWAY SAFETY IMPROVEMENT PROGRAM (HSIP)
CROSSWALK IMPROVEMENT PROJECT - HSIPSL-5065(035)
1. PARTIES AND DATE.
This Contract is made and entered into this ____ day of ______________, 20___ by and between the City of Colton, a municipal corporation organized under the laws of the State of California with its principal place of business at 650 North La Cadena Drive, Colton, California 92324, County of San Bernardino, State of California (“City”) and [***INSERT NAME***], a [***INSERT TYPE OF ENTITY - CORPORATION, PARTNERSHIP, SOLE PROPRIETORSHIP OR OTHER LEGAL ENTITY***] with its principal place of business at [***INSERT ADDRESS***] (“Contractor”). City and Contractor are sometimes individually referred to as “Party” and collectively as “Parties” in this Contract.
2. RECITALS.
2.1 City. City is a public agency organized under the laws of the State of California, with power to contract for services necessary to achieve its purpose.
2.2 Contractor. Contractor desires to perform and assume responsibility for the provision of certain construction services required by the City on the terms and conditions set forth in this Contract.
Contractor represents that it is duly licensed and experienced in providing concrete removal and replacing related construction services to public clients, that it and its employees or subcontractors have all necessary licenses and permits to perform the services in the State of California, and that it is familiar with the plans of City. The following license classifications are required for this Project: Class A
2.3 Project. City desires to engage Contractor to render such services for the Highway Safety Improvement Program (HSIP) Crosswalk Improvement Project - HSIPSL-5065(035) (“Project”) as set forth in this Contract.
2.4 Project Documents & Certifications. Contractor has obtained, and delivers concurrently herewith, performance bond, payment bond, insurance documents and other certifications as required by the Contract.
3. TERMS
3.1 Incorporation of Documents. This Contract includes and hereby incorporates in full by reference the following documents, including all exhibits, drawings, specifications and documents therein, and attachments and addenda thereto:
• Services/Schedule (Exhibit “A”)
• Plans and Specifications (Exhibit “B”)
• Special Conditions (Exhibit “C”)
• Contractor’s Certificate Regarding Workers’ Compensation (Exhibit “D”)
• Public Works Contractor Registration Certification (Exhibit “E”)
• Payment and Performance Bonds (Exhibit “F”)
• Addenda
• Change Orders executed by the City
• 2024 Edition of the Standard Specifications for Public Works Construction (The
Greenbook), Excluding Sections 1-9
• Notice Inviting Bids
• Instructions to Bidders
• Contractor’s Bid
3.1.1 Precedence. To the extent there is a conflict between any portions of this Contract, the order of precedence shall be as follows: change orders, special conditions, technical specifications, plans/construction drawings, general contract terms, scope of work, standard plans, advertisements for bid/proposals, bids/proposals or other documents submitted by Contractor.
3.2 Contractor’s Basic Obligation; Scope of Work. Contractor promises and agrees, at its own cost and expense, to furnish to the City all labor, materials, tools, equipment, services, and incidental and customary work necessary to fully and adequately complete the Project, including all structures and facilities necessary for the Project or described in the Contract (hereinafter sometimes referred to as the “Work”), for a Total Contract Price as specified pursuant to this Contract. All Work shall be subject to, and performed in accordance with the above referenced documents, as well as the exhibits attached hereto and incorporated herein by reference. The plans and specifications for the Work are further described in Exhibit “B” attached hereto and incorporated herein by this reference. Special Conditions, if any, relating to the Work are described in Exhibit “C” attached hereto and incorporated herein by this reference.
3.2.1 Change in Scope of Work. Any change in the scope of the Work, method of performance, nature of materials or price thereof, or any other matter materially affecting the performance or nature of the Work shall not be paid for or accepted unless such change, addition or deletion is approved in advance and in writing by a valid change order executed by the City.
3.2.1.1 Change Orders. Changes to the Contract Time (as defined in Section 3.3) or Total Contract Price shall be in the form of a written Change Order, either signed by both parties or issued unilaterally by the City. No adjustment shall be made to the Contract Time unless the delay impacts the critical path to completion and the delay was not caused in whole or in part by the Contractor.
Failure to timely request a Change Order shall constitute a waiver of any right to adjust the Contract Time or the Total Contract Price. All requests for Change Orders shall be accompanied by detailed supporting documentation, including but not limited to payroll records, invoices, schedules, and any other documentation requested by the City for the purpose of determining the additional costs or the impact of any delay. If the change involves Work bid at a unit price, then the Total Contract Price shall be increased at the unit price.