Hammermill Equipment (Code 105) 2. SAP SOW.pdf

PDF 137 KB Posted

Attached to
Hammermill Material-Equipment Federal contract opportunity
Solicitation number
24-SIMACQ-BD3-0053
Issued by
Department of the Navy Naval Sea Systems Command

About this file

This document is a Statement of Work (SOW) for the procurement and installation of a new National Security Agency (NSA) approved classified material destruction system for the Naval Surface Warfare Center, Port Hueneme Division (NSWC PHD).

The key requirements include: 1) Procuring a dual stage disintegrator system capable of destroying paper and optical media at a rate of no less than 1,000 pounds per hour, 2) Providing a feed conveyor system, 3) Implementing a waste collection system, 4) Furnishing a master control panel, and 5) Installing all components, integrating with existing equipment, and providing maintenance support. The new system will replace an existing, non-functional system located at the NSWC PHD facility. The contractor must provide a minimum 5-year part warranty and 90-day labor warranty. On-site testing is required to demonstrate the 1,000 pounds per hour throughput over a 5-hour period.

View the file

Other files for this federal contract opportunity

Other files attached to Hammermill Material-Equipment, newest first.
File Type Posted
24-BD3-0048_Hammermill Equipment_Sources Sought_03252024.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOW - Classified Material Destruction System

1. INTRODUCTION

Naval Surface Warfare Center, Port Hueneme Division (NSWC PHD) Security Code 105 requires procurement of a new National Security Agency (NSA) approved complete classified material destruction system capable of destroying classified paper documents and optical media material.

The new destruction system will replace an existing, non-functional system located in Building

1462 on Naval Base Ventura County, Port Hueneme installation.

2. OBJECTIVE

The objective of this contract is to procure and install equipment to satisfy the requirement for a replacement heavy-duty, commercial destruction system located on-site that is capable of destroying large volumes of paper and optical media. To meet current and future NSWC PHD destruction demands, the new destruction system must have a throughput greater than 1000 lbs./hr. Current demand requires the average daily destruction of the contents of fourteen (14)

96-gal shred bins, each weighing approximately 350 lbs. for approximately 5-hours of personnel-supported, daily shred processing.

3. SCOPE OF WORK

The scope of work under this contract includes the following:

1. Dual Stage Disintegrator System

a. NSA Evaluated Products List (EPL) approved destruction device capable of destroying paper and optical material at a rate of no less than 1,000 pounds per hour.

b. Pre-shredder allowing for greater throughput.

c. Sound reduction for safety of personnel.

d. Size not to exceed 120” H x 80” W x 60” D.

2. Feed Conveyor

a. Configured to meet existing grey bin dump table and dual stage disintegrator system.

b. Programmed to feed dual stage disintegrator system at an effective and functional speed.

c. Cleated for material pick-up.

d. Emergency shut-off.

3. Waste Collection System

a. Air conveyed waste evacuation system capable of pulling disintegrator waste into compactor exterior to Building 1462.

b. Motorized cyclone with filter shaker.

c. Steel structure for access to exterior waste collection components including cyclone, air filter, and air lock.

4. Master Control Panel

a. Programmed for start, shutdown, and monitoring of all components, including disintegrator system, waste collection system, and feed conveyor.

5. Installation of all components

a. Engineered schematics for mechanical and electrical functionality.

b. Engineered design for existing facility size, power capability, and equipment access.

c. Delivery of all components and assembly of all components onsite.

Commented [JS1]: At NSWC PHD correct

Commented [EMD2R1]: Yes

d. Integration with existing equipment and all associated components resulting in full-functionality of the system as a whole to achieve throughput of 1,000 pounds per hour of paper material and continuous run time.

e. Pre-testing of system.

f. De-installation of existing equipment for NSWC PHD retention. De-installed equipment to be left in the parking lot immediately outside Building 1462 for

NSWC PHD disposition.

g. On-site testing. Test must show destruction system is able to maintain a throughput greater than 1000 lbs./hr. for approximately 5-hours and successfully deposit shredded material into the compactor.

h. Provide system operation manuals, as-built drawings, and electrical schematics.

i. One year of preventative maintenance beginning on installation completion date.

j. One emergency service visit within a year of installation completion date.

k. Contractor must provide a part warranty covering, at a minimum, 5 years. 5 years or more - part warranty.

l. Contractor must provide a labor warranty covering, at a minimum, 90 days. 90 days or more - labor warranty.

Commented [JS3]: Are there any additional requirements for the pre-testing?

Commented [EMD4R3]: Not that I’m aware of

Commented [JS5]: Is this different from pre-testing? Any additional specific requirements for the testing? (i.e., must pass/must demonstrate XYZ/etc.)

Commented [EMD6R5]: Pre-testing is before the equipment is transported to our building, on-site testing is after installation. Updated to include throughput requirement.

Commented [JS7]: Are the details of preventative maintenance defined somewhere?

Commented [EMD8R7]: Company determines what preventative maintenance entails.

Commented [JS9]: A pre-planned one or we can call them for an emergency service visit within 1 year?

Commented [EMD10R9]: Call them for one within the 1st year.

Commented [JS11]: Recommend using full sentences where we can to more clearly state our requirements. So “Contractor shall provide a part warranty covering, at a minimum, 5 years.” etc.