U.S. General Services Administration Greater Southwest Region
PROJECT TITLE:
Chiller Project
LOCATION:
Bridge Over the Americas (BOTA) Port of Entry El Paso, Texas
ISSUE DATE:
July 16, 2015
PROPOSALS DUE:
August 21, 2015
REQUEST FOR PROPOSALS NO:
GS-07P-15-UK-C-7000
PRE PROPOSAL CONFERENCE:
Tuesday, July 28, 2015 at 1:00 pm MST BOTA Port of Entry El Paso, Texas
REQUEST FOR PROPOSALS
GSA MISSION STATEMENT: To provide policy leadership and expertly managed space, supplies, services, and solutions, at the best value, to enable Federal employees to accomplish their missions.
TABLE OF CONTENTS
Standard Form 1442 – Solicitation, Offer and Award 1 – 4
Scope of Work (SOW) 5 – 12
Exhibit A 13 - 18
Exhibit B 19 - 26
Wage Determination 27 – 32
C101 – The Agreement 33 – 59
C201 – The Solicitation 60 – 77
C301 – Offeror Representations and Certifications 78 – 83
(To be completed by contractor)
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NO.
5. REQUISITION/PURCHASE REQUEST NO.
CODE
6. PROJECT NO.
8. ADDRESS OFFER TO
4. CONTRACT NO.
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
11. The contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
NSN 7540-01-155-3212 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED PAGE OF PAGES
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 4-85) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
27. PAYMENT WILL BE MADE BY
10 U.S.C. 2304(c) ( ) 41 U.S.C. 253(c) ( )
20b. SIGNATURE 20c. OFFER DATE
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
SCHEDULE Continued
0001 Contractor shall provide all the necessary supplies, materials, equipment, labor and supervision to replace the 120 ton chiller at the Bridge Over the
America (BOTA) Port of Entry, El Paso, Texas. All work shall be done in accordance with the Scope of Work dated 05/12/15.
The following item is hereby incorporated by reference:
Scope of Work, Dated 05/12/15
Exhibit A and B
Wage Determination TX150295, Dated 03/06/15
The Agreement (C101-SB / APR 2015)
The Solicitation (C201-SB LPTA/ APR 2015)
Offerors Representations and Certifications (C301 /APR 2015)
Contractor shall provide payment bond, performance bond and insurance documents within 10 calendar days after contract award. Notice to Proceed will not be issued until all bonding and insurance are accepted.
The contractor shall be required to complete the entire work ready for use no later than 30 calendar days after Notice to Proceed is issued. Work shall be performed during normal working hours (7:00 am – 6:00 pm), Monday through Friday, excluding Federal holidays or as directed by GSA. If the contractor fails to complete the work within the time specified in the contract, the contractor shall pay liquidated damages to the Government in the amount of $296.00 for each calendar day of delay until the work is completed or accepted.
All contract employees working on premises at GSA owned and operated buildings are required to pass a security background check conducted by the
Office of Personnel Management (OPM). The contractor shall provide the
Contractor Information Worksheet (CIW) for each employee to GSA
R7Suitability at r7suitability@gsa.gov within 15 calendar days after contract award. The employee will receive detail instructions and access to the online application from accesscard@gsa.gov within a couple of days after they submit the CIW.
A Pre Proposal Conference is scheduled for Tuesday, July 28, 2015 at 1:00 pm MST at the Bridge Over the Americas (BOTA) Port of Entry, El Paso, Texas. Contractor need to verify all existing conditions at the job site prior to bidding on project. Failure to do so will not relieve contractor of his/her responsibility to properly estimate the cost of this project. This is the only opportunity contractors will get to visit the site to conduct a walk-through and ask questions. GSA will not have anyone available to accompany contractor or their representative (sub-contractors) after the scheduled pre proposal conference. Offerors need to provide the following information for each individual that will be attending the Pre Proposal Conference at least 24 hours in advance for vetting.
- Full name
- Date of birth
- Last 4 digits of SS #
Send the information to Rosalva Ramos, Contracting Officer at rosalva.ramos@gsa.gov and Frank Campagna, Project Manager at frank.campagna@gsa.gov
*CONTINUED NEXT PAGE*
RosalvaRamos Line
RosalvaRamos Line
RosalvaRamos Line
RosalvaRamos Line
RosalvaRamos Highlight
Last day to submit Request for Clarification or Interpretation should be made not less than 10 calendar days prior to the date set for receipt of proposals.
Proposals shall consist of the following documents, completed and executed in accordance with this Solicitation:
(1) Breakdown Price Proposal
(2) Technical Proposal
(3) Representations and Certifications
(4) Bid Guarantee, using Standard Form 24
Contractor shall provide a proposal with a detailed cost breakdown; cost breakdown shall be submitted in CSI Master Format 2010. The cost breakdown shall sum to the total construction cost of the proposal. The proposal acceptance period shall be 120 calendar days from the proposal due date. A lump sum proposal will not be acceptable and failure to provide cost breakdown may result in GSA rejecting the proposal and obtaining construction services elsewhere.
Proposal is due by 4:00 pm CST on Friday, August 21, 2015. Proposals may be e-mailed to rosalva.ramos@gsa.gov or mailed to the following address:
Rosalva Ramos
General Services Administration
1101 East Hackberry, Suite 200
McAllen, Texas 78501
If you have any questions, please contact Rosalva Ramos, Contracting
Officer at 956-618-8176. Frank Campagna is the Project Manager assigned for this project.
Underline
GSA Public Buildings Service Greater Southwest Region Border Service Center El Paso, TX Office
SCOPE OF WORK
Project number ePM 29635 Replacement of 120 Ton Chiller
TX0951EL
Bridge Over the Americas (BOTA) El Paso, Texas
Date: 05/12/2015 Prepared by: Dana Ulanoff/Frank Campagna
SCOPE OF WORK
The contractor shall provide all materials, supplies, labor, equipment and supervision, necessary to complete the demolition and alterations stated below.
A.Demolition
1. Remove and reclaim refrigerant from an existing 120 ton water cooled chiller.(Chiller #1)
2. Disconnect all electrical, controls, piping and associated equipment to chiller.
Remove all unused conduit/wiring back to panel boards and provide knock-out plugs at all unused openings.
3. Remove and dispose of properly one 120 ton water cooled chiller located in the mechanical room for the BOTA administration building (Bldg A).
4. Disconnect all electrical, controls, piping and associated equipment to existing cooling tower. Remove all unused conduit/wiring back to panel boards and provide knock-out plugs at all unused openings.
5. Disconnect all electrical, controls, piping and associated equipment to existing boiler.
Remove all unused conduit/wiring back to panel boards and provide knock-out plugs at all unused openings.
6. Remove and dispose properly one existing Burnham gas fired hot water boiler in the mechanical room for the BOTA administration building.
7. Remove and dispose existing air handler unit (AHU) 1A located in building A in the mezzanine.
B. Alterations
1. Provide and install two each 75 ton nominal capacity one compressor water cooled magnetic bearing chiller (see Exhibit A for references only). One chiller must be operational before the install on the second chiller begins.
2. Installation shall be/have but not limited to:
i. Equal to or better than SMARDT Frictionless Centrifugal Chillers part #
WA059.2BG04.F4AVDA.F4AVDA.0N0
ii. Evaporator EWT/LWT (F) 54/45, Evaporator GPM- 180.0, Condenser
EWT/LWT (F) 85/94, Condenser GPM- 225.0
iii. Oil free, magnetic bearing, magnetic high-speed variable speed centrifugal compressor(s).
iv. 460 volts, 3 phase
v. Compressor suction and discharge isolation valves.
vi. Step-less capacity control using multi-compressors, inlet guide vanes, and internal variable speed drives.
vii. Environmentally friendly refrigerant.
viii. Cleanable flooded evaporator providing low temperature approach and built to ASME standard.
ix. Water cooled cleanable shell and tube condenser built to ASME standard.
x. 1.5” (38mm) minimum closed cell insulation to prevent external condensation.
xi. Advanced Control System including integrated communication with compressor for precise capacity control and operational safeties.
xii. 12" color graphical interface with panel mounted touch-screen.
xiii. MODBUS RTU or BACnet interface between the chiller and the BAS.
xiv. Single point electrical entry.
xv. Full refrigerant charge.
xvi. Chilled water: IFM – Thermal Dispersion Switch
xvii. Condenser water: IFM – Thermal Dispersion Switch
xviii. Dual pressure relief valves on evaporator and condenser
xix. Factory startup by a factory authorized service technician.
xx. 5-year full chiller parts,labor and refrigerant warranty (including compressors)
xxi. 1.5 inch Insulation option kit including insulation on suction side of compressors.
xxii. Factory installed epoxy coating on the condenser tube sheets, marine water boxes and end plates. Marine water box for each condenser and evaporator The existing refrigerant monitor Wheelock Model Number MT4-115-WH- VNW will require the sensors to be replaced to monitor refrigerant R134A and programming changes.
xxiii. Provide and install all necessary piping and insulation to match existing profiles. In the event the chiller selected for this project requires additional space to meet physical clearance requirements, the existing flat plate heat exchanger can be relocated to provide this clearance. Provide and install all necessary piping hangers and/or support for new piping. Include new valve tags IAW current Valve Tag Schedule in the control room. Paint all piping to match existing color scheme. Paint color selection to be provided by GSA.
See Exhibits 2,2A, 3 and 4.
xxiv. Provide new vertical in line chilled water pump with 78’ tdh at 180 GPM GPM (see Exhibit “B” for reference only) including suction valve/strainer at the inlet connection and triple duty valve at discharge connection. Work shall completely remove the existing pumps, apparatus, and electrical back to the panelboard. Also see Exhibits1-4. The mechanical contractor shall inspect the strainer prior to activating the pump and, further, shall remove the Fine Mesh Start-up Strainer after a short running period. (24 hours maximum).
Space shall provided for removal of the strainer and include installation connection of a blow-down valve. The new pumps shall be piped in parallel so that either condenser water pump or chill water pump can provide flow to either chiller. A proposed piping diagram shall be submitted during the submittal process.
xxv. Provide new vertical in line condenser pump with 73’ tdh at 225 GPM (see Exhibit “B” for reference only) including suction valve at the inlet connection and triple duty valve at the discharge connection. Work shall completely remove the existing pumps, apparatus, and electrical back to the panelboard.
The mechanical contractor shall inspect the strainer prior to activating the pump and, further, shall remove the Fine Mesh Start-up Strainer after a short running period. (24 hours maximum). Space shall provided for removal of the strainer. The new pumps shall be piped in parallel so that either condenser water pump or chill water pump can provide flow to either chiller. A proposed piping diagram shall be submitted during the submittal process.
xxvi. Provide and install all necessary water thermowell connections and include new thermometers and pressure gauges (8 thermometers/20 gauges) with associated hardware to provide shut off and removal during gauge removal.
Pressure gauges shall be installed on the inlet and outlet of each pump and condenser and evaporator.
xxvii. Provide and install all necessary and properly sized electrical conduit and electrical wiring for new chiller. Contractor will be responsible to verify existing electrical power and/or circuit breakers will handle new chiller’s electrical voltage and amperage. Provide and install properly sized transformers, electrical panel(s) and circuit breakers for new chillers as needed. Provide new panel schedules reflecting work accomplished.
xxviii. Contractor will be responsible for installing new house keeping pads to match new chiller & pumps reconfigurations. Housekeeping concrete pad shall match existing pad and profile.
xxix. Contractor will repaint entire chiller room floor with epoxy floor paint.
Approved paint/epoxy submittals are required.
xxx. Bid documents shall include new chiller spec sheet for intended chiller manufacture that shall include intended chiller performance data.
3. Provide and install new W11H Series (or similar) boiler & two hot water pumps
4. Installation shall be/have but not limited to:
i. Water output (MBH) 1,759
ii. Water MBH 1,522
iii. Gas Input (MBH) 2,136
iv. Net Firebox Volume (cu.Ft.) 21.1
v. Pressure in Firebox (In. Wc.) 0.48
vi. Vent Diameter (in.) 10
vii. Approx. Shipping & lifting weight (Lb) 4,147
viii. Add new boiler to existing BAS matching points list & graphics for existing boiler.
ix. New hot water pumps with suction guide vain/strainer and triple duty valve shall be vertical inline pumps 125 GPM and 52 feet of head each.
x. Repaint Housekeeping pads.
5. Provide and install a new AHU to replace existing (AHU1A) in mezzanine in Building A
6. Installation shall be/have, but not limited to the following specifications:
i. Total CFM 8500 2000 CFM OA MERV 8 filters
ii. Cooling Capacity 300MBH entering AT 75 degree f DB 62 degree f WB
iii. Chilled water temp 45/55
iv. Heating Coil 266 MBH Entering Water 160 f Leaving Water 130 degrees
Entering AT 65 DB 57 DB Leaving AT 92 entering AT 66
v. Add new AHU to existing BAS matching points list & graphics for existing AHU.
vi. Install new electronic actuators on hot/chilled water valves and dampers and connect to the building BAS. The room the AHU is installed shall be a return air chamber. The return air from the pedestrian walkway shall return air from a new ducted return duct installed above the x-ray machine ceiling and ducted to the AHU mechanical room. Another return air transition duct with return air grill shall be installed between the AHU mechanical room and the pedestrian area wall. Duct and grill size shall be properly sized to handle the CFM. Any work that needs to accomplished in the pedestrian walkway must be accomplished after normal duty hours. AHU controls strategy/sequence of operation shall include an economy cycle
1. The new chiller’s control system shall communicate with existing building automated system. Contractor will be responsible to verify the existing BAS and provide all necessary wiring, controls, and/or Modbus/Bacnet cards (if needed) to integrate chiller’s controls to BAS. The BAS Integration contractor shall include any mapping and linking changes of the MagLev chiller on the graphics page of the BOTA BAS including new piping, chiller layout, pumps and cooling tower. Contractor is responsible for licensing fee and drivers to connect/communicate MODBUS or BACnet to the existing JACE.
Chiller display/ chiller history/trending shall be connected to the BAS for viewing and controlling. Provide the tonnage with the chiller graphic (ex: Smardt 75 Ton). Include links to the chiller history logs on the central plant page so that access to the trends are easily opened for analysis. The Contractor shall program the existing and any new feedback points using Modbus or BACNET protocol intergraded into the existing BAS. The new chiller’s control system shall communicate with existing building automated system.
Contractor will be responsible to verify the existing BAS and provide all necessary wiring, controls, and/or Bacnet cards (if needed) to integrate chiller’s controls to BAS.
Automated valves shall provide reporting feedback on current status, history screens, and valve icons shall be visible on the BAS central plant page. All analog histories of new Chiller points shall be recorded in 15 minute intervals and stored in the building JACE controller for 14 days. All discrete point histories shall be recorded both as 15 minute interval, 14 day FIFO history logs but also as COV histories storing 100 intervals within the JACE. All new Chiller point histories shall be exported daily from the JACE to the hosting GSA BAS Server and to the GSA AMS Application for long term archival storage.
Sequence of Operation- Chillers shall operate in a lead /lag operation rotating every seven days.(field adjustable) When the lead chiller increases to 82% of chiller full load KW for 15 consecutive mins, the lag chiller starts. When the load decreases on the lag chiller to 33% of the chiller full load KW for 15 consecutive mins, the lag chiller shuts off.
(field adjustable points from the BAS graphics page including time and KW set points)
Security Requirements: Contractor personnel performing work on the BAS under this contract must possess HSPD-12 Clearance and GAC Cards in order to access GSA secured networks and sites. The security clearance procedures and forms are listed in Part 5 of this PWS (attachments 3, 4, and 5).
Integration Technician: Integration technician performing installation shall be certified on the Niagara AX JACE for both installation and maintenance of the system and shall have a minimum of 3 years experience performing the required tasks. The contractor shall provide with their offer the integration technician’s resume and certification documentation.
a. All new equipment shall be controlled by the BAS. Please verify with GSA Equipment
Specialist for more information on the sequence of operation for this new chiller.
b. Install new automatic 2 way isolation valves with position status point fast reaction (30 sec or less from fully open to closed position) with on the condenser and chilled water line for each chiller and incorporate in the BAS (Total Four). These valves will eliminate water flowing through a chiller that is not operating.
2. Contractor will be responsible to setting the pressure drop across the evaporator and condenser water heat exchanger.
3. Once project is completed and chillers are fully operational, contractor should rebalance the water flow and provide report to GSA Project Manager.
4. Contractor shall provide at a minimum 6 hours of training to GSA maintenance personnel including both classroom and hands on training.
5. Contractor shall provide a complete commissioning report to GSA Project manager once chiller is fully operational. All adjustments and balancing to the system shall be in accordance with manufacturer’s specifications.
6. Contractor will submit a disposal/waste management plan for GSA approval prior to commencing work at the job site.
C. Specifications and Requirements
1. Valves connections, accessories and operators
i. Provide threaded ends for valves 2.5 inches and smaller
ii. Provide flanged or grooved ends for valves 3 inch and larger
iii. For butterfly valves (isolation valves) provide lever handle, infinitely adjustable with lock nut and memory stop. Provide hot dipped galvanized extension stems, valve handles and gear actuators outdoors. Provide weatherproof galvanized cast iron gear operators for valves mounted outdoors.
2. Automatic isolation valves:
i. Type of end fitting: pattern to mate with ANSI 125 flange.
ii. Cast iron GG25 with stainless steel stem and ball.
3. Pipe insulation- Match existing size/type/color scheme and labeling.
4. Pumps/Suction Guides/Triple Duty Valves: Armstrong (or equivalent) Split coupled vertical in line pumps, suction guides, triple duty valves. Ashcraft Company POC:
Gordon Sears tel:214.361.6611
5. Steel pipe and fittings:
i. Steel pipe, DN 50 (NPS 2) and smaller: ASTM A 53, type S (seamless) or type F (furnace butt welded), grade B, schedule 40, black steel, plain ends.
ii. Steel Pipe, DN 65 through DN 300 (NPS 2-1/2 through NPS 12): ASTM A 53, type E (electric-resistance welded), Grade B, Schedule 40, black steel, plain ends.
iii. Steel Pipe Nipples: ASTM A 733, made of ASTM A 53, Schedule 40, black steel; electric-resistance welded for DN 65 (NPS 2-1/2) and larger.
iv. Cast-Iron Threaded Fittings: ASME B16.4; Classes 125 and 250.
Malleable-Iron Threaded Fittings: ASME B16.3, Classes 150 and 300.
D. Final Preparations
1. Contactor shall provide two (2) sets of as-built drawings on compact disk (CD). As-built drawings shall be in Auto CAD format and shall illustrate all alterations performed under this contract. Final payment will not be authorized until all as-built drawings are provided.
2. Contractor shall provide three (3) copies of owner’s (O&M) manuals for architectural, mechanical and electrical equipment & systems. Contractor shall return all GSA Badges issued for this project. Final payment will not be authorized until all O&M manuals and badges are provided and returned.
E. Special Instructions
1. Contractors are to submit proposal with a detailed cost breakdown. Cost Breakdown shall be submitted in CSI Master Format 2010.
2. Contractor is responsible to comply with the “Buy American Act”. Buy American Act provides domestic construction material be used in performing this contract.
3. Contractor will be responsible to request and furnish all required overhead and/or road blocking permits from the City of Fort Worth and or electrical/utility providers when using a crane at this location.
F. General Construction Requirements
1. Keep work areas clean on a daily basis.
2. Remove debris from site on a daily basis.
3. Protect all existing walls and furniture from damage.
4. Contractor is responsible for all damages to government property caused by him/her and their subcontractors.
5. Contractor is responsible for all dimensions and quantities.
6. Contractor shall field verify all existing conditions prior to submitting a bid.
PRE-BID WALK-THROUGH
Contractors are required to attend a mandatory pre-bid walk-through. Contractors are encouraged to verify all existing conditions at the job site prior to bidding on project. Failure to do so will not relieve contractor of any responsibility to properly estimate the cost of this project. GSA project Manager will coordinate the pre-bid meeting/walk through once RFP is issued.
SECURITY CLEARANCE REQUIREMENT
All contractor personnel performing working on premises at GSA owned and operated buildings are required to pass a security background check conducted by the Department of Homeland Security/Federal Protective Service. No contractor employee will be allowed to perform work on the building premises until employee has been determined to be suitable for hire by the Department of Homeland Security/Federal Protective Service.
WORKING HOURS
Work not impacting normal building occupancy shall be performed during normal business hours Monday through Friday 7:00 am to 6:00 pm. Any work affecting normal building occupancy needs to be scheduled after normal business hours/weekends and approved by GSA building manager.
PERIOD OF PERFORMANACE
All work shall be completed within 30 calendar days after Chiller delivery. It is estimated that it will take 12-14 weeks to manufacture the chiller. A partial NTP will be issued to place the order on the equipment upon approved submittals.
LIQUIDATED DAMAGES
If substantial completion is not achieved by 1 April 2015, the Contracting Officer may assess liquidated damages at a rate of $198 per day.
PROJECT SCHEDULE
Contractor shall submit to the GSA Project Manager a project schedule which includes all tasks to be performed under this project, duration of each task and tentative date/s each task will be performed.
Project schedule must be approved by the GSA Project Manager prior to performing any work under this project. Microsoft Project or other similar format can be used for this schedule.
Note:
The following items will be addressed at the Pre-bid Conference and again at a Pre-work Conference:
1. On site storage.
2. Parking.
3. Use of elevators.
4. Access through secured area.
5. Contractor shall coordinate with the GSA mechanical maintenance contractor, for placing the fire alarm system in test mode prior to performing any work that may result in the activation of an alarm signal from the fire alarm system including but not limited to: connecting devices to fire alarm system, cutting, welding or other work that creates excessive dust. Contractor is responsible for all costs associated with placing the fire alarm system in test mode.
6. A GSA approved welding permit will be required before performing any cutting and welding.
Contractor shall contact the GSA Dallas/Fort Worth Service Center, TX office at least 24 hours in advance to request a permit for cutting and welding.
7. Contractor shall be responsible for all quantities, measurements, correct installation of all items and for any damages to the building, items such as parked vehicles and surrounding areas.
8. All materials, equipment and supplies to be incorporated into work under the terms of this contract shall have been “NEW” and “UNUSED” at time of award.
9. Materials of equipment containing asbestos in any form shall not be incorporated into this project.
10. All material, workmanship and equipment shall be subject to the inspection and approval by the
Contracting Officer Representative. All work unsatisfactorily performed shall be promptly corrected and made acceptable for the Government.
MATERIAL TECHNICAL SPECIFICATIONS
Where a particular manufacturer's product is specified, it is not intended to discriminate against other manufacturer's which are equal in quality of material, workmanship, appearance and function to those specified. Rather, it is intended to establish and indicate the desired standard of quality. If any tests are required to determine the equality of any substitutes, such tests shall be made by an independent authority as approved by the government. All expenses related to proposed substitutions shall to be paid by the contractor. Proposed items are to be submitted with the bid and shall be a basis for the award of the contract.
Text Box $29666
All materials and equipment shall bear evidence of the Underwriter's Laboratories Inc. Label (UL) or approval of other nationally recognized independent testing organizations adequately equipped and competent to perform such services when these standards are required and such product listing is available.
PRODUCT DATA AND SAMPLES
1. Product Data: Contractor shall submit one electronic set of chiller product data including any valves, piping, insulation, BAS hardware, refrigerant monitoring system, catalog sheets, brochures, performance charts or other standard descriptive data provided by any subcontractor, supplier or distributor. Product Data must be certified by the contractor stating that it was reviewed and approved. Product to be used must be high lighted on the data sheet by the contractor. Product Data used for construction must bear GSA’s stamp certifying final review and approval. No product shall be used that does not bear such stamp. Submittals shall be identified on a submittal register provided by the contractor and transmitted using a transmittal letter.
2. Samples: Contractor shall submit physical samples establishing standards by which completed work is judged. Samples shall indicate color range, functional characteristics and shall represent exact material to be used on the project.
3. Safety Plan: Contractor shall submit a crane safety plan (if applicable) for crane erection and use. Include preferred location for crane set up, operator certification credentials, and crane inspection/certification documentation.
PERFORMANCE REQUIREMENT
1. The contractor shall field verify existing conditions prior to any demolition.
2. The contractor shall reinstall existing access panels; etc, back to their original location and condition after all work is completed.
3. The contractor shall remove and dispose of all construction debris as it accumulates on a daily basis.
4. Upon completion of work the contactor shall leave the premised clean and free of any debris.
APPLICABLE PUBLICATIONS
A. Department of Labor:
1. Occupational and Health Standards: (29 CFR part 1926).
2. Safety and Health Regulations for Construction: (29CFR part 1518).
3. Federal Code:
All renovations shall be in accordance with the current design requirements as found in the Federal Construction & Safety Standard, and Third Party approved structure design package.
Latest Edition of the following Codes/Regulations:
4. Fire Codes: All units shall meet or exceed all required Federal, State and Local Fire Codes.
5. Housing & Urban Development (HUD 24 CFR 3280).
6. National Electrical Code (NEC).
7. International Building Code (IBC).
8. International Mechanical Code (IMC).
9. International Plumbing Code (IPC).
10. American Society of Heating, Refrigeration and Air Conditioning (ASHRA).
11. Occupational and Safety Act (OSHA).
12. National Fire Protection Association (NFPA).
13. U.S. Environmental Protection Agency (EPA), “Mold Remediation in Schools and Commercial
Buildings”.
B. Manufacture, installation and testing shall comply with manufacturer’s instructions and standards.
When more stringent requirements are call for either this S.O.W. or codes and regulations, the priority of precedence in compliance shall be:
1. Federal Requirements.
2. State Requirements.
3. Local Requirements.
4. Manufacturer’s Requirements.
5. Contractor’s Requirements.
DISCLOSURE OF INFORMATION
1. Any information made available to the contractor by the government shall be used only for the purpose of carrying out the provisions of this contract. This information shall not be divulged or made known in any manner to any persons except as may be necessary in the performance of the contract.
2. In the performance of this contract the contractor assumes responsibility for the protection of the confidentiality of government records.
3. The contractor shall adhere to the requirements found in Part 24 of the Federal Acquisition Regulation, Protection of Privacy and Freedom of Information.
WARRANTY
1. All workmanship and materials shall be warranted for a period of not less than three hundred sixty five (365) days from date of acceptance by the Government (Standard Warranty) plus extended compressor parts and labor warranty (4 years).
2. The contractor shall provide a copy of warranty of items procured. Warranty shall be in writing and shall include any conditions which may invalidate the warranty.
3. Warranty shall include procedures on how to exercise warranty rights. Provide points of contact in order to get services required.
4. Standard warranty shall be all inclusive of parts, labor and materials, related coverage and additional costs, if any.
5. Contractor shall provide all applicable manufacturers’ warranties at time of completion.
END OF SCOPE OF WORK
February 11, 2015
Smardt Inc · 1840 Trans Canada Hwy · Dorval Qc H9P 1H7 · (514) 426-8989 · Fax (514) 426-5757 ·
Customer: Customer Ref:
Quoted for: Prepared By: Marcos Awad Date: February 11, 2015
FrankECampagna
Exhibit A
PART NUMBER DESCRIPTION
WA030.1BG02.F4AHCA.F4AGCA.0C0 Water Cooled Chiller
INCLUDED BY SMARDT:
Chiller(s) to be shipped Standard - Unit shipped fully assembled
Chillers are ETL listed and certified to CSA C22.2 No.236
Conforming to ANSI/UL 1995
Power connection style: Single Point Power Connection
Nema 1 Control enclosures - indoor use only
Mechanical HP/LP switch.
ASME certified horizontal shell-and-tube heat exchangers.
Supporting baffles inside Standard EVAP and COND tubesheets
High efficiency enhanced tubes
Evaporator Insulation: Standard Thermal Insulation 3/4" (19mm)
Evaporator water boxes rated to 145psig fitted with Grooved Pipe Connection
Condenser water boxes rated to 145psig fitted with Grooved Pipe Connection
Chilled water : IFM – Thermal Dispersion Switch
Condenser water : IFM – Thermal Dispersion Switch
Dual pressure relief valves on evaporator and condenser mounted on changeover valve.
Factory Startup: Certified Startup Agent
Connectivity: Modbus RTU (RS485)
NOT INCLUDED BY SMARDT:
Vibration isolation pad (not required by manufacturer)
Rigging and providing access for equipment.
Piping from refrigerant pressure relief valves to outside.
Grooved flange couplings.
Refrigerant monitor.
Seismic certification.
Performance test.
Sound test.
Harmonic or EMI Filters
Extended warranties.
Any other item not mentioned above.
PERFORMANCE INFORMATION
Description Capacity Model
Centrifugal liquid chiller 75.0 tonsR WA030.1BG02.F4AHCA.F4AGCA.0C0
Options
W1 | E1 | C1 | XXXXXXXXXXXXX.XXXX.XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX.XXXXXXXXXXX.XXXXXXXXXXXXXXX
Evaporator Data
Fluid Type Water Fluid Concentration (%) 0%
Flow Rate 180.0 US gpm Tube Material Cu 0.025” Enhanced Surface
Entering Fluid Temp 54.0°F Tube Wall Thickness 0.025Inch
Leaving Fluid Temp 44.0°F Circuit number of passes Four(4)
Fouling Factor 0.00010 h•ft²•ºF/Btu Constant speed flow min (pressure drop at flow)
127.9 USGPM (2.11 PSI)
Pressure Drop 4.17 psi (9.63 ft H2O) Variable speed flow min (pressure drop at flow)
85.3 USGPM (0.94 PSI)
Condenser Data
Fluid Type Water Fluid Concentration (%) 0%
Flow Rate 225.0 US gpm Tube Material Cu 0.025” Enhanced Surface
Entering Fluid Temp 85.0°F Tube Wall Thickness 0.025Inch
Leaving Fluid Temp 94.4°F Circuit number of passes Four(4)
Fouling Factor 0.00025 h•ft²•ºF/Btu Constant speed flow min (pressure drop at flow)
113.3 USGPM (0.70 PSI)
Pressure Drop 6.47 psi (14.93 ft H2O) Variable speed flow min (pressure drop at flow)
75.5 USGPM (0.31 PSI)
Physical Data
Length(ft) See product drawing Weight (Empty) 4605 lbs
Width(ft) See product drawing Weight (Operating) 5258 lbs
Height(ft) See product drawing Refrigerant Charge 300 lbs
Equipment Details
Capacity(TR) 75.0 tonsR Type of compressor TT300-G2-1-ST-E-O-NC
Unit Power(kW) 46.2 kW Full load Efficiency 0.615 kW/tonsR
Number of compressors 1 Compressor Efficiency 0.614 kW/tonsR
Compressor Power (kW) each
46.2 kW HFC 134a
Unit power characteristics
Supply Power 460 V MCA 81 A
Amps 65 A MOCP 146 A
14.1.0.1 February 11, 2015
AHRI CERTFIED PER 550/590
Program Scope
1.3.1 Program Scope Inclusions.
1.3.1.1 60 Hz WCCL Product Inclusions.
All compressor types;
Chillers rated with capacities >0 and ≤3000 tons a [10,551 kW] b
Hermetic & open type, electric motor driven;
Units selected for use within the range of Application Rating Conditions as per the Standard (part-load performance no less than 25% of the rated full load capacity);
Chillers with voltages ≤15,000 volts; and
Positive Displacement Units intended for use with glycol or other secondary coolant for freeze protection with a leaving chilled fluid temperature above 32°F [0°C] are certified when tested with water at Standard Rating Conditions.
Notes:
a. Capacity refers to the capacity of Packaged Units rated at full load AHRI Standard 550/590 (I-P) Rating
Conditions and the capacity of Configurable Units rated at application full load operating conditions provided these conditions are within the scope of AHRI Standard 550/590 (I-P).
b. kW conversions provided for reference only.
1.3.1.2 50 Hz WCCL Product Inclusions
All compressor types;
Chillers rated with capacities ≥200 and ≤3000 tons a [703 and 10,551 kW] b
Optional certification for chillers rated with capacities >0 and <200 tons a [703kW] b (The Certify-All Policy does not apply to these units.);
Hermetic & open type, electric motor driven;
Units selected for use within the range of application rating conditions as per the Standard (part-load performance no less than 25% of the rated full load capacity);
Chillers with voltages ≤15,000 volts; and
Positive Displacement Units intended for use with glycol or other secondary coolant for freeze protection with a leaving chilled fluid temperature above 32°F [0°C] are certified when tested with water at Standard Rating Conditions.
Notes:
a. Capacity refers to the capacity of Packaged Units rated at full load AHRI Standard 550/590 (I-P) Rating
Conditions and the capacity of Configurable Units rated at application full load operating conditions provided these conditions are within the scope of AHRI Standard 550/590 (I-P).
b. kW conversions provided for reference only.
1.3.2 Program Scope Exclusions. The following are exclusions for 50 Hz and 60 Hz WCCL products:
Condenserless chillers;
Evaporatively-cooled chillers;
Chillers that are not electrically driven
Chillers with motors not supplied with the unit by the Participant; and
Heat recovery & heat pump ratings are not certified; however, Participants may elect to certify these chillers in the cooling mode with this option turned off.
Units with condensers intended for use with glycol or other secondary coolants.
Units with evaporators intended for use with glycol or other secondary coolants not included in Sections
1.3.1.1 and 1.3.1.2.
Certified in accordance with the AHRI Water-Cooled Water Chilling Packages Using Vapor Compression Cycle Certification Program, which is based on AHRI Standard 550/590 (I-P) and AHRI Standard 551/591 (SI). Certified units may be found in the AHRI Directory at www.ahridirectory.org
WA030.1BG02.F4AHCA.F4AGCA.0C0
14.1.0.1
IPLV : 0.343 kW/tonsR (35.0 EER)
% Load Capacity Perf kW Chw Flow
Chw In Chw Out Cw Flow Cw In Cw Out
100 75.0 0.615 46.15 180.00 53.95 44.01 225.00 84.99 94.35
75 56.2 0.436 24.51 180.00 51.46 44.01 225.00 75.02 81.74
50 37.5 0.293 10.98 180.00 48.98 44.01 225.00 64.94 69.25
25 18.7 0.299 5.61 180.00 46.49 44.01 225.00 64.94 67.10
NPLV : 0.343 kW/tonsR (35.0 EER)
% Load Capacity Perf kW Chw Flow
Chw In Chw Out Cw Flow Cw In Cw Out
100 75.0 0.613 45.94 180.00 53.95 44.01 225.00 84.99 94.35
75 56.2 0.435 24.47 180.00 51.46 44.01 225.00 74.97 81.68
25 18.7 0.299 5.62 180.00 46.49 44.01 225.00 64.94 67.10
PPLV : 0.343 kW/tonsR (35.0 EER)
% Load Capacity Perf kW Chw Flow
Chw In Chw Out Cw Flow Cw In Cw Out
100 75.0 0.613 45.94 180.00 53.95 44.01 225.00 84.99 94.35
75 56.2 0.435 24.47 180.00 51.46 44.01 225.00 74.97 81.68
25 18.7 0.299 5.62 180.00 46.49 44.01 225.00 64.94 67.10
Sound Data
Description Global 60 Hz 125 Hz 250 Hz 500 Hz 1 kHz 2 kHz 4 kHz 8 kHz
Lw dB 84.7 65.5 80 76.6 73.1 78 72.4 73.8 72.8
Lw dB(A) 81.7 39.3 63.9 68 69.9 78 73.6 74.8 71.7
Lp dB(A) at
3.3 ft
73.7 31.3 55.9 60 61.9 70 65.6 66.8 63.7
WA030.1BG02.F4AHCA.F4AGCA.0C0
14.1.0.1
DIMENSIONS
L W W/Flash Econ H
70.9 in 49.1 in 49.1 in 79.7 in
A B C D
21.6 in 27.6 in 7.3 in 11.4 in
EVAPORATOR CONDENSER
IN OUT IN OUT
4.0 in 4.0 in 4.0 in 4.0 in
Pump Data Sheet - Patterson HVAC Pumps
Company: Ashcraft Company, Inc.
Name: Taylor Sears El Paso BOTA Budget Selections Date: 3/18/2015
CW-1 & 2
Pump:
Model: V3C9A-RC Type: VIL Speed: 1760 rpm Synch speed: 1800 rpm Dia: 9.4375 in Size: 3x3x9 Impeller: D05-73118 Specific Speeds: Ns: ---
Nss: --- Dimensions: Suction: 3 in
Discharge: 3 in
Pump Limits:
Temperature: --- Power: --- Pressure: --- Eye area: --- Sphere size: ---
Search Criteria:
Flow: 225 US gpm Head: 73 ft
Fluid:
Water Temperature: 60 °F SG: 1 Vapor pressure: 0.2563 psi a Viscosity: 1.105 cP Atm pressure: 14.7 psi a NPSHa: ---
Motor:
Size: 7.5 hp Speed: 1800 Frame: See Chart
Standard: NEMA Enclosure: ODP
Sizing criteria: Max Power on Design Curve
Selected from catalog: Patterson HVAC.60 Vers: 1.3
---- Data Point ---- Flow: 225 US gpm Head: 74.4 ft Eff: 72.8% Power: 5.8 hp NPSHr: 21 ft
---- Design Curve ---- Shutoff head: 97.5 ft Shutoff dP: 42.2 psi Min flow: 50.9 US gpm BEP: 74.6% @ 204 US gpm NOL power:
6.73 hp @ 316 US gpm
-- Max Curve -- Max power:
6.9 hp @ 319 US gpm
US gpm
N
PS
H r -ft
3503002502001501000 50
H ea d
- f t
3500 300
74.6
9.4375 in9.5 in
6.75 in
2 hp
3 hp
5 hp
7.5 hp
50 50
Performance Evaluation:
Flow Speed Head Efficiency Power NPSHr US gpm rpm ft % hp ft 270 1760 61.7 66.8 6.28 24.5 225 1760 74.4 72.8 5.8 21 180 1760 82.9 73.2 5.12 18.2 135 1760 89.2 68 4.45 16.5 90 1760 93.7 55.7 3.82 16
FrankECampagna
EXHIBIT B
tsears Oval tsears Oval tsears Oval
Pump Data Sheet - Patterson HVAC Pumps
Company: Ashcraft Company, Inc.
Name: Taylor Sears El Paso BOTA Budget Selections Date: 3/18/2015
CHW-1 &2
Pump:
Model: V3C9A-RC Type: VIL Speed: 1760 rpm Synch speed: 1800 rpm Dia: 9.25 in Size: 3x3x9 Impeller: D05-73118 Specific Speeds: Ns: ---
Nss: --- Dimensions: Suction: 3 in
Discharge: 3 in
Pump Limits:
Temperature: --- Power: --- Pressure: --- Eye area: --- Sphere size: ---
Search Criteria:
Flow: 180 US gpm Head: 78 ft
Fluid:
Water Temperature: 60 °F SG: 1 Vapor pressure: 0.2563 psi a Viscosity: 1.105 cP Atm pressure: 14.7 psi a NPSHa: ---
Motor:
Size: 7.5 hp Speed: 1800 Frame: See Chart
Standard: NEMA Enclosure: ODP
Sizing criteria: Max Power on Design Curve
Selected from catalog: Patterson HVAC.60 Vers: 1.3
---- Data Point ---- Flow: 180 US gpm Head: 78.8 ft Eff: 72.9% Power: 4.89 hp NPSHr: 18.3 ft
---- Design Curve ---- Shutoff head: 93.1 ft Shutoff dP: 40.3 psi Min flow: 49.6 US gpm BEP: 73.9% @ 198 US gpm NOL power:
6.25 hp @ 308 US gpm
-- Max Curve -- Max power:
6.9 hp @ 319 US gpm
US gpm
N
PS
H r -ft
3503002502001501000 50
H ea d
- f t
3500 300
73.9
9.25 in
9.5 in
6.75 in
2 hp
3 hp
5 hp
7.5 hp
50 50
Performance Evaluation:
Flow Speed Head Efficiency Power NPSHr US gpm rpm ft % hp ft 216 1760 71.9 72.6 5.39 20.4 180 1760 78.8 72.9 4.89 18.3 144 1760 84.1 69.6 4.39 16.8 108 1760 88 61.9 3.87 16.1 72 1760 91 48.5 3.43 16
Available in sizes 2”x1 1/2” through 12”x12” with cast iron bodies and flanged inlet-outlet connections.
Standard Features Include n Direct mounting in horizontal or vertical position. Flanges are Class 125 ANSI (ASA) flat faced (For Class 300 flanges consult factory).
n Integrally cast stabilizing vanes.
n Separate fine mesh start up screen surrounds each perforated screen.
n Cast on pads for convenient mounting of standard I.D. support foot.
n Drain/purge plugs for removal of foreign particles without disassembly.
n Class 125 (175 PSI) n 250°F maximum working temperature n Magnetic Plug
The Wheatley suction diffuser is designed to reduce space and installation costs by replacing a long radius elbow, strainer and extended entry pipe on the suction side of the pump. The flow stabilizing vanes reduce turbulence and resulting stress and vibration.
In addition, the suction diffuser strainer removes foreign particles which may be hazardous to the pump and other system components. Consult factory for materials recommendation based on flow media.
Multi-function benefits saves costs and space by replacing:
n 90° Elbow n Strainer n Flow Stabilizing Piping
Applications Bulletin SDC125 9-07
1/4” pressure taps available on certain sizes (consult factory)
5454 South 103rd East Avenue Tulsa, OK 74146
Toll Free: 866-204-5229
PH: 918-592-5058
FAX: 918-622-4288
www.wheatleyhvac.com
Wheatley HVAC Suction Diffuser Class 125 e-mail: sales@globalflowproducts.com
Applications Bulletin SDC125 9-07
5 1 3 4 2 67 F
Drain G Pipe Size
Inlet
Outlet
C
A
J
B
D
E
5454 South 103rd East Avenue Tulsa, OK 74146
Toll Free: 866-204-5229 PH: 918-592-5058 FAX: 918-622-4288
Materials of Construction
Item Description Material
1 Body Cast Iron 2 Cover Cast Iron 3 Strainers Stainless Steel 4 Start up Strainer 20 Mesh Screen 5 Diffuser Cast Iron 6 Cap Screw Steel 7 Gasket/O-Ring Consult Factory 8 Plug Steel
General Dimensions Class 125 Pressure Class 125
WeightLoss Curve Model ANSI (ASA) Strainer Dimensions (In.)
(Lbs.)Reference Number Inlet Outlet Free Dia.
Area Openings A B C D E F(NPT) **G J Width
(In.)
B SD0215 2 1 1/2 27 1/8 9 3/8 4 1/2 8 13/16 4 1/2 2 3/16
3/4 1 6 1/8 6 1/2 21
C SD0202 2 2 27 1/8 9 3/8 4 1/2 8 13/16 4 1/2 2 3/16
3/4 1 6 1/8 6 1/2 23
D SD2502 2 1/2 2 37 1/8 10 3/8 5 9 3/8 5 3 1/8 3/4 1 6 9/16 7 1/2 32
E SD2525 2 1/2 2 1/2 37 1/8 10 3/8 5 9 3/8 5 3 1/8 3/4 1 6 9/16 7 1/2 34
F SD0302 3 2 37 1/8 8 1/8 4 1/4 5 4 11/16 3 1/8 3/4 1 5 5/8 7 1/2 37
G SD0325 3 2 1/2 37 1/8 8 1/4 4 3/8 5 4 11/16 3 1/8 3/4 1 5 3/4 7 1/2 49
H SD0303 3 3 50 1/8 9 3/8 4 3/4 5 1/4 4 3/4 3 5/8 3/4 1 6 5/8 7 1/2 55
I SD0403 4 3 50 1/8 9 3/8 4 3/4 5 1/4 5 5/8 3 5/8 3/4 1 6 5/8 9 57
J SD0404 4 4 82 1/8 11 1/8 5 3/4 6 3/4 5 3/4 4 1/4 3/4 1 1/4 7 5/8 9 92
K SD0504 5 4 82 1/8 11 1/8 5 3/4 6 3/4 6 5/8 4 1/4 3/4 1 1/4 7 5/8 10 97
L SD0505 5 5 104 1/8 12 5/8 6 1/2 7 1/8 6 1/2 4 7/8 1 1 1/4 8 5/8 10 101
M SD0604 6 4 82 1/8 11 1/8 5 3/4 6 3/4 7 1/2 4 1/4 3/4 1 1/4 7 3/4 11 104
N SD0605 6 5 104 1/8 12 5/8 6 1/2 7 1/8 7 3/8 4 7/8 1 1 1/4 8 5/8 11 145
O SD0606 6 6 153 1/8 13 7/8 7 7 7/8 7 5 7/8 1 2 9 1/8 11 182
P SD0806 8 6 153 1/8 13 7/8 7 7 7/8 8 3/4 5 7/8 1 2 9 1/8 13 1/2 197
Q SD0808 8 8 275 1/8 18 7/8 9 1/4 16 1/4 9 1/4 6 3/8 1 2 11 5/8 13 1/2 292
R SD1008 10 8 275 1/8 18 7/8 9 1/4 16 1/4 11 6 3/8 1 2 11 5/8 16 312
S SD1010 10 10 420 1/8 23 7/8 11 16 1/8 11 1/4 8 1 2 13 3/4 16 398
T SD1208 12 8 250 1/8 18 7/8 9 1/4 16 1/4 12 6 3/8 1 2 11 5/8 19 412
U SD1210 12 10 380 1/8 23 7/8 11 16 1/8 12 8 1 2 13 3/4 19 491
V SD1212 12 12 560 1/8 26 12 18 1/8 12 9 1/4 1 2 13 7/8 19 573
*Perforated basket includes fine mesh start-up screen. Start-up screen should removed and disposed of after 1 month operation.
** Pipe Support supplied by contractor.
www.wheatleyhvac.com e-mail: sales@globalflowproducts.com
Available in sizes 1-1/2” through 12” with cast iron bodies and threaded or flanged ends. Standard features include:
n Schrader valve metering connections n Memory stop which avoids the need for resetting after shut-down.
n Plug position indicator and calibrated scale for system balancing and flow regulation.
n Spring loaded clapper allows the valve to be installed horizontally 1-1/2” through 8” vertically.
n Dual O-ring stem seals n Non-lubricated operation n Bubble-tight shut-off n In-line serviceability The unique quarter-turn TDV/TSV design offers backflow protection throughout a wide range of system balancing settings.
Upon closing, the plug rotates to block the downstream port of the valve allowing pressure to equalize around clapper so that it closes with little resistance. Final closing is accomplished by the plug camming against the backside of the clapper. The most satisfactory closure is accomplished by turning the plug to a normal tight fit, then bumping the plug lightly.
1.001 TDV/TSV 06-10
Multi function benefits n Flow regulator valve n Positive shut-off valve n Convenient connections for gauges n Compact size reduces space requirements
Memory Stop Internal Spring-loaded Clapper Valve Clappers are internally spring-loaded for a positive check.
FLOW FLOW
Valve is shown in open position. Memory Stop has not been set.
Valve Plug is rotated to selected balance position.
Memory stop is rotated until it intercepts the stop on cover.