File Type Posted
GENERAL_NOTE.pdf PDF
RFI_6.30.2016.pdf PDF
Amendment_02.pdf PDF
Amendment_01.pdf PDF
Sign_in_Sheet.pdf PDF
RFP_CCC.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Contract ID Code Page of Pages

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1 2

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (if applicable)

03 July 7, 2016 EQ5P2SS1P-16-5094

6. ISSUED BY 7. ADMINISTERED BY (If other than Item 6)

General Services Administration

AMD, Chicagoland Construction Contracting Team

230 S. Dearborn St., Suite 3600

Chicago, IL 60604

Same as Block 6

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, Country, State and ZIP Code) () 9A. AMENDMENT OF SOLICITATION NO.

GS-05-P-16-GC-C-7002

X 9B. DATED (SEE ITEM 11)

June 1, 2016

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning 1 copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (if required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

() A. THIS ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINSTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN

ITEM

14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return ____ copy to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible)

Solicitation #GS-05-P-16-GC-C-7002, Amendment 03

Child Care Center Renovation for Custom House located at 610 S. Canal Street in Chicago, Illinois.

Amendment 03 is issued to 1) address the RFI’s received and 2) issue Addendum 04. The proposal due date/time of July 13, 2016 at

4:00PM CDT remains the same.

CONTINUED ON PAGE 2

Except as provided herein, all terms and conditions of the document reference in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE

SIGNED

(Signature of person authorized to sign)

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous Edition unusable

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT SOLICITATION NO. AMENDMENT NO. PAGE OF PAGES

CONTINUATION OF STANDARD FORM 30

Child Care Center Renovation for Custom House, Chicago, IL GS-05-P-16-GC-C-7002 03 2 2

Response to RFI’s

Q1. Verify the anticipated start date and completion date for this project

April ‘17 - September ‘17

Q2. Provide contact information for the fire alarm system vendor currently maintaining the building fire alarm system.

Honeywell

Q3. Please verify that work is not intended to begin until June of 2017. If so, is there an allowable contingency for escalation of prices of labor, goods, and services?

GSA typically allows for equitable adjustments to contracts once the labor rates are determined.

Q4. Per the interior elevations (A200, A201, A202 & A 303) shades are shown at all exterior windows except for the following rooms: Kitchenette: 170-J, Office: 170D, and Conference Room: 170E. Please confirm that shades are not to be provided for these rooms.

All exterior windows are to receive roller shades. This is indicated by keyed note A.25 in classroom elevations and by typical-detail callout referring to Detail 4/A-500 (Typical Ceiling Detail at Existing Exterior Window) in the RCP.

Q5. Drawing: A-101 indicates the shade head detail (A-500/4), designated in Room 170E. Please confirm that a shade is not provided for this room.

All exterior windows are to receive roller shades. This is indicated by keyed note A.25 in classroom elevations and by typical-detail callout referring to Detail 4/A-500 (Typical Ceiling Detail at Existing Exterior Window) in the RCP.

Q6. The Window Treatment Specifications indicate both Shade Pocket & Closure and Closure Mount and Closure. Which housing system is required: Pocket with Lip and closure or Closure Mount with Lip & Closure.

See Addendum 04

Q7. The window treatment specifications do not indicate a fabric or openness factor. Please indicate a fabric type (EchoVeil, ThermoVeil, Euro Veil or Equinox) and openness Factor: (0% or Blackout Fabric, 1-2%, 3%, 5% or 10%).

See Addendum 04

Q8. On the Issued for Bid Drawing Set title sheet dated 5/17/16, Mechanical, Electrical, Plumbing, and Fire Alarm drawings are listed, but not included with the bid packet or any of the amendments. Are they forthcoming?

The drawings are complete. There is one set of 38 pages. Please verify you printed the entire set.

Addendum 04 forms part of the Contract Documents for the above named project and contains the following:

Revised Drawings

The following Drawings are revised and issued herewith, dated 7/6/2016

A-100 Keyed note 24 amended for clarification

A-500 Note added to detail 2 and detail 3

Revised Specifications

The following specification sections are revised and issued herewith, dated 7/6/2016

000010 Table of Contents Updated Table of Contents

122413 Roller Window Shades Housing System 3 added Housing System 1 and 2 removed for clarification

088000 Glazing Glazing Gaskets added to Part 2.6

N.I.C.

D

W

F

F

FIRST FLOOR PLAN

TYPICAL CEILING DETAIL

@ EXISTING EXTERIOR WINDOW

CLASSROOM - CLASSROOM PARTITION

TYPICAL WALL SECTION

CLASSROOM - OFFICE/HALLWAY PARTITION

TYPICAL WALL SECTION

4' LOW WALL PARTITION

TYPICAL WALL SECTION

GSA Child Care Center for the U.S. Custom House GSA Project No. PJ4EA1326

610 South Canal Street, Chicago, IL

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice.

Properly destroy documents when no longer needed.

TABLE OF CONTENTS 000010 - 1

07/06/16

CUSTOMHOUSE - CHILDCARE RENOVATION

The following listed documents comprise the project manual for the project listed above. Where numerical sequence of sections is interrupted, such interruptions are intentional.

The complete Project Manual for this project consists of this entire Volume 1 and 2, which must not be separated for any reason. The Architect and Owner disclaim any responsibility for any assumptions made by a contractor or subcontractor who does not receive a complete Project Manual, including all sections listed in the Table of Contents.

Additions to previously issued sections have been bolded and underlined. Deletions have been struck out.

Design Issue

TABLE OF CONTENTS Firm Date

DIVISION 01 - GENERAL REQUIREMENTS

011000 Summary

012300 Alternates

012500 Substitution Procedures

012900 Payment Procedures

013100 Project Management

013200 Construction Progress Documentation

013233 Photographic Documentation

013300 Submittals Procedures

013525 Fire Protection & Protection in Construction, Alternation, KOO 05/17/16

KOO 06/27/16

KOO 05/17/16

KOO 05/17/16

KOO 05/17/16

KOO 05/17/16

KOO 05/17/16

KOO 05/17/16

KOO 05/17/16

and Demolition Projects

013526 Safety and Health KOO 05/17/16

014000 Quality Requirements KOO 05/17/16

014200 References KOO 05/17/16

015000 Temporary Facilities And Controls KOO 05/17/16

016000 Product Requirements KOO 05/17/16

017300 Execution KOO 05/17/16

017419 Construction Waste Management & Disposal KOO 05/17/16

017700 Closeout Procedures KOO 05/17/16

017823 Operation and Maintenance Data KOO 05/17/16

017839 Project Record Documents KOO 05/17/16

017900 Demonstration & Training KOO 05/17/16

DIVISION 02 - EXISTING CONDITIONS

024119 Selective Demolition KOO 05/17/16

DIVISION 03 - CONCRETE

035416 Hydraulic Cement Underlayment KOO 05/17/16

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice.

Properly destroy documents when no longer needed.

TABLE OF CONTENTS 000010 - 2

07/06/16

DIVISION 05 – METALS

055000 Metal Fabrications KOO 05/17/16

DIVISION 06 - WOOD, PLASTICS AND COMPOSITES

061053 Miscellaneous Rough Carpentry KOO 05/17/16

064116 Plastic-Laminate-Faced Architectural Cabinets KOO 05/17/16

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

078413 Through Penetration Firestop System KOO 05/17/16

079200 Joint Sealants KOO 05/17/16

DIVISION 08 – OPENINGS

081113 Hollow Metal Doors and Frames KOO 05/17/16

087100 Door Hardware KOO 05/17/16

088000 Glazing KOO 07/06/16

DIVISION 09 - FINISHES

090190.52 Maintenance Repainting KOO 05/17/16

092216 Non-Structural Metal Framing KOO 05/17/16

092900 Gypsum Board KOO 05/17/16

093013 Ceramic Tiling KOO 05/17/16

095113 Acoustical Panel Ceilings KOO 05/17/16

096513 Resilient Base and Accessories KOO 05/17/16

096519 Resilient Tile Flooring KOO 05/17/16

096543 Linoleum Flooring KOO 05/17/16

099123 Interior Painting KOO 05/17/16

DIVISION 10 - SPECIALTIES

102600 Wall and Door Protection KOO 05/17/16

102800 Toilet Accessories KOO 06/22/16

DIVISION 12 - FURNISHINGS

122413 Roller Window Shades

123661.16 Solid Surfacing Countertops and Wainscots

KOO 07/06/16

KOO 06/22/16

DIVISION 21 - FIRE SUPPRESSION

210517 Sleeves and Sleeve Seals For Fire-Suppression Piping CCJM 05/17/16

210518 Escutcheons For Fire Suppression Piping CCJM 05/17/16

210553 Identification For Fire-Suppression Piping And Equipment CCJM 05/17/16

211100 Fire Suppression Piping CCJM 05/17/16

SENSITIVE BUT UNCLASSIFIED (SBU)

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice.

Properly destroy documents when no longer needed.

TABLE OF CONTENTS 000010 - 3

07/06/16

DIVISION 22 – PLUMBING

220517 Sleeves and Sleeve Seals For Plumbing Piping CCJM 05/17/16

220518 Escutcheons for Plumbing Piping CCJM 05/17/16

220523 General-Duty Valves for Plumbing Piping CCJM 05/17/16

220529 Hangers And Supports For Plumbing Piping And Equipment CCJM 05/17/16

220553 Identification For Plumbing Piping And Equipment CCJM 05/17/16

220700 Plumbing Insulation CCJM 05/17/16

221116 Domestic Water Piping CCJM 05/17/16

221119 Domestic Water Piping Specialties CCJM 05/17/16

221316 Sanitary Waste And Vent Piping CCJM 05/17/16

221423 Drainage Piping Specialties CCJM 05/17/16

224000 Plumbing Fixtures CCJM 05/17/16

DIVISION 23 - HEATING VENTILATING AND AIR CONDITIONING

230523.12 Ball Valves for HVAC Piping CCJM 05/17/16

230593 Testing, Adjusting, And Balancing For HVAC CCJM 05/17/16

230713 Duct Insulation CCJM 05/17/16

230719 HVAC Piping Insulation CCJM 05/17/16

232113 Hydronic Piping CCJM 05/17/16

233113 Metal Ducts CCJM 05/17/16

233300 Air Duct Accessories CCJM 05/17/16

233423 HVAC Power Ventilators CCJM 05/17/16

233600 Air Terminal Units CCJM 05/17/16

233713.13 Air Diffusers CCJM 05/17/16

233713.23 Air Registers And Grilles CCJM 05/17/16

DIVISION 26 – ELECTRICAL

260500 Common Work Results For Electrical Systems CCJM 05/17/16

260503 General Requirements For Electrical Systems CCJM 05/17/16

260519 Low-Voltage Electrical Power Conductors And Cables CCJM 05/17/16

260529 Hangers And Supports For Electrical Systems CCJM 05/17/16

260533 Raceway And Boxes For Electrical Systems CCJM 05/17/16

260553 Identification For Electrical Systems CCJM 05/17/16

260813 Testing Of Electrical Systems CCJM 05/17/16

262726 Wiring Devices CCJM 05/17/16

265119 LED Interior Lighting CCJM 05/17/16

DIVISION 27 – COMMUNICATIONS

271500.19 Communications Horizontal Cabling CCJM 05/17/16

FOR OFFICIAL USE ONLY

TABLE OF CONTENTS 000010 - 4

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

281315 Access Control System CCJM 05/17/16

281600 Intrusion Detection CCJM 05/17/16

END OF TABLE OF CONTENTS

610 South Canal Street, Chicago, IL Issued for Addendum #4

FOR OFFICIAL USE ONLY

GLAZING 088000 - 1

SECTION 088000 - GLAZING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including Federal Acquisition Regulation

(FAR) and General Services Administration Acquisition Regulation (GSAR) contract clauses, and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes:

1. Glass for doors and interior borrowed lites.

1.3 DEFINITIONS

A. Glass Manufacturers: Firms that produce primary glass, fabricated glass, or both, as defined in referenced glazing publications.

B. Glass Thicknesses: Indicated by thickness designations in millimeters according to

ASTM C 1036.

C. IBC: International Building Code.

1.4 COORDINATION

A. Coordinate glazing channel dimensions to provide necessary bite on glass, minimum edge and face clearances, and adequate sealant thicknesses, with reasonable tolerances.

1.5 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1.6 ACTION SUBMITTALS

A. Product Data: For each type of product.

B. Glass Samples: For each type of glass product other than clear monolithic vision glass; 12 inches (300 mm) square.

C. Glazing Schedule: List glass types and thicknesses for each size opening and location. Use same designations indicated on Drawings.

FOR OFFICIAL USE ONLY

GLAZING 088000 - 2

D. Delegated-Design Submittal: For glass indicated to comply with performance requirements and design criteria, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation.

1.7 INFORMATIONAL SUBMITTALS

A. Qualification Data: For Installer and glass testing agency.

B. Product Certificates: For glass.

1.8 QUALITY ASSURANCE

A. Installer Qualifications: A qualified installer who employs glass installers for this Project who are certified under the National Glass Association's Certified Glass Installer Program.

B. Glass Testing Agency Qualifications: A qualified independent testing agency accredited according to the NFRC CAP 1 Certification Agency Program.

1.9 DELIVERY, STORAGE, AND HANDLING

A. Protect glazing materials according to manufacturer's written instructions. Prevent damage to glass and glazing materials from condensation, temperature changes, direct exposure to sun, or other causes.

1.10 FIELD CONDITIONS

A. Environmental Limitations: Do not proceed with glazing when ambient and substrate temperature conditions are outside limits permitted by glazing material manufacturers and when glazing channel substrates are wet from rain, frost, condensation, or other causes.

1.11 WARRANTY

A. Manufacturer's Special Warranty for Laminated Glass: Manufacturer agrees to replace laminated-glass units that deteriorate within specified warranty period. Deterioration of laminated glass is defined as defects developed from normal use that are not attributed to glass breakage or to maintaining and cleaning laminated glass contrary to manufacturer's written instructions. Defects include edge separation, delamination materially obstructing vision through glass, and blemishes exceeding those allowed by referenced laminated-glass standard.

1. Warranty Period: Five years from date of Substantial Completion.

FOR OFFICIAL USE ONLY

GLAZING 088000 - 3

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Source Limitations for Glass: Obtain from single source from single manufacturer for each glass type.

B. Source Limitations for Glazing Accessories: Obtain from single source from single manufacturer for each product and installation method.

2.2 PERFORMANCE REQUIREMENTS

A. General: Installed glazing systems shall withstand normal thermal movement and wind and impact loads (where applicable) without failure, including loss or glass breakage attributable to the following: defective manufacture, fabrication, or installation; failure of sealants or gaskets to remain watertight and airtight; deterioration of glazing materials; or other defects in construction.

B. Delegated Design: Engage a qualified professional engineer, as defined in Section 014000

"Quality Requirements," to design glazing.

C. Safety Glazing: Where safety glazing is indicated, provide glazing that complies with

16 CFR 1201, Category II.

2.3 GLASS PRODUCTS, GENERAL

A. Glazing Publications: Comply with published recommendations of glass product manufacturers and organizations below unless more stringent requirements are indicated. See these publications for glazing terms not otherwise defined in this Section or in referenced standards.

1. GANA Publications: "Laminated Glazing Reference Manual" and "Glazing Manual."

B. Safety Glazing Labeling: Where safety glazing is indicated, permanently mark glazing with certification label of the SGCC. Label shall indicate manufacturer's name, type of glass, thickness, and safety glazing standard with which glass complies.

C. Thickness: Where glass thickness is indicated, it is a minimum. Provide glass that complies with performance requirements and is not less than the thickness indicated.

1. Minimum Glass Thickness for Exterior Lites: 6 mm.

D. Strength: Where annealed float glass is indicated, provide annealed float glass, heat-strengthened float glass, or fully tempered float glass as needed to comply with "Performance

Requirements" Article. Where heat-strengthened float glass is indicated, provide heat-strengthened float glass or fully tempered float glass as needed to comply with "Performance

FOR OFFICIAL USE ONLY

GLAZING 088000 - 4

Requirements" Article. Where fully tempered float glass is indicated, provide fully tempered float glass.

2.4 GLASS PRODUCTS

A. Clear Annealed Float Glass: ASTM C 1036, Type I, Class 1 (clear), Quality-Q3.

B. Fully Tempered Float Glass: ASTM C 1048, Kind FT (fully tempered), Condition A (uncoated) unless otherwise indicated, Type I, Class 1 (clear) or Class 2 (tinted) as indicated, Quality-Q3.

1. Fabrication Process: By horizontal (roller-hearth) process with roll-wave distortion parallel to bottom edge of glass as installed unless otherwise indicated.

2.5 LAMINATED GLASS

A. Laminated Glass: ASTM C 1172. Use materials that have a proven record of no tendency to bubble, discolor, or lose physical and mechanical properties after fabrication and installation.

1. Construction: Laminate glass with polyvinyl butyral interlayer to comply with interlayer manufacturer's written instructions.

2. Interlayer Thickness: Provide thickness not less than that indicated and as needed to comply with requirements.

3. Interlayer Color: Clear unless otherwise indicated.

2.6 MISCELLANEOUS GLAZING MATERIALS

A. General: Provide products of material, size, and shape complying with referenced glazing standard, with requirements of manufacturers of glass and other glazing materials for application indicated, and with a proven record of compatibility with surfaces contacted in installation.

B. Glazing Gaskets: Sealed-corner pressure-glazing system of black, resilient elastomeric glazing gaskets, setting blocks, and shims or spacers.

C. Cleaners, Primers, and Sealers: Types recommended by sealant or gasket manufacturer.

D. Setting Blocks: Elastomeric material with a Shore, Type A durometer hardness of 85, plus or minus 5.

E. Spacers: Elastomeric blocks or continuous extrusions of hardness required by glass manufacturer to maintain glass lites in place for installation indicated.

F. Edge Blocks: Elastomeric material of hardness needed to limit glass lateral movement (side walking).

FOR OFFICIAL USE ONLY

GLAZING 088000 - 5

2.7 FABRICATION OF GLAZING UNITS

A. Fabricate glazing units in sizes required to fit openings indicated for Project, with edge and face clearances, edge and surface conditions, and bite complying with written instructions of product manufacturer and referenced glazing publications, to comply with system performance requirements.

1. Allow for thermal movements from ambient and surface temperature changes acting on glass framing members and glazing components.

a. Temperature Change: 120 deg F (67 deg C), ambient; 180 deg F (100 deg C), material surfaces.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine framing, glazing channels, and stops, with Installer present, for compliance with the following:

1. Manufacturing and installation tolerances, including those for size, squareness, and offsets at corners.

2. Presence and functioning of weep systems.

3. Minimum required face and edge clearances.

4. Effective sealing between joints of glass-framing members.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Clean glazing channels and other framing members receiving glass immediately before glazing.

Remove coatings not firmly bonded to substrates.

B. Examine glazing units to locate exterior and interior surfaces. Label or mark units as needed so that exterior and interior surfaces are readily identifiable. Do not use materials that leave visible marks in the completed Work.

3.3 GLAZING, GENERAL

A. Comply with combined written instructions of manufacturers of glass, sealants, gaskets, and other glazing materials, unless more stringent requirements are indicated, including those in referenced glazing publications.

B. Protect glass edges from damage during handling and installation. Remove damaged glass from

Project site and legally dispose of off Project site. Damaged glass includes glass with edge

FOR OFFICIAL USE ONLY

GLAZING 088000 - 6

damage or other imperfections that, when installed, could weaken glass, impair performance, or impair appearance.

C. Apply primers to joint surfaces where required for adhesion of sealants, as determined by preconstruction testing.

D. Install setting blocks in sill rabbets, sized and located to comply with referenced glazing publications, unless otherwise required by glass manufacturer. Set blocks in thin course of compatible sealant suitable for heel bead.

E. Do not exceed edge pressures stipulated by glass manufacturers for installing glass lites.

F. Provide spacers for glass lites where length plus width is larger than 50 inches (1270 mm).

1. Locate spacers directly opposite each other on both inside and outside faces of glass.

Install correct size and spacing to preserve required face clearances, unless gaskets and glazing tapes are used that have demonstrated ability to maintain required face clearances and to comply with system performance requirements.

2. Provide 1/8-inch (3-mm) minimum bite of spacers on glass and use thickness equal to sealant width. With glazing tape, use thickness slightly less than final compressed thickness of tape.

G. Provide edge blocking where indicated or needed to prevent glass lites from moving sideways in glazing channel, as recommended in writing by glass manufacturer and according to requirements in referenced glazing publications.

H. Set glass lites in each series with uniform pattern, draw, bow, and similar characteristics.

I. Set glass lites with proper orientation so that coatings face exterior or interior as specified.

J. Where wedge-shaped gaskets are driven into one side of channel to pressurize sealant or gasket on opposite side, provide adequate anchorage so gasket cannot walk out when installation is subjected to movement.

K. Square cut wedge-shaped gaskets at corners and install gaskets in a manner recommended by gasket manufacturer to prevent corners from pulling away; seal corner joints and butt joints with sealant recommended by gasket manufacturer.

3.4 GASKET GLAZING (DRY)

A. Cut compression gaskets to lengths recommended by gasket manufacturer to fit openings exactly, with allowance for stretch during installation.

B. Insert soft compression gasket between glass and frame or fixed stop so it is securely in place with joints miter cut and bonded together at corners.

FOR OFFICIAL USE ONLY

GLAZING 088000 - 7

C. Installation with Drive-in Wedge Gaskets: Center glass lites in openings on setting blocks, and press firmly against soft compression gasket by inserting dense compression gaskets formed and installed to lock in place against faces of removable stops. Start gasket applications at corners and work toward centers of openings. Compress gaskets to produce a weathertight seal without developing bending stresses in glass. Seal gasket joints with sealant recommended by gasket manufacturer.

D. Installation with Pressure-Glazing Stops: Center glass lites in openings on setting blocks, and press firmly against soft compression gasket. Install dense compression gaskets and pressure-glazing stops, applying pressure uniformly to compression gaskets. Compress gaskets to produce a weathertight seal without developing bending stresses in glass. Seal gasket joints with sealant recommended by gasket manufacturer.

E. Install gaskets so they protrude past face of glazing stops.

3.5 CLEANING AND PROTECTION

A. Immediately after installation remove nonpermanent labels and clean surfaces.

B. Protect glass from contact with contaminating substances resulting from construction operations. Examine glass surfaces adjacent to or below exterior concrete and other masonry surfaces at frequent intervals during construction, but not less than once a month, for buildup of dirt, scum, alkaline deposits, or stains.

1. If, despite such protection, contaminating substances do come into contact with glass, remove substances immediately as recommended in writing by glass manufacturer.

Remove and replace glass that cannot be cleaned without damage to coatings.

C. Remove and replace glass that is damaged during construction period.

D. Wash glass on both exposed surfaces not more than four days before date scheduled for inspections that establish date of Substantial Completion. Wash glass as recommended in writing by glass manufacturer.

3.6 MONOLITHIC GLASS SCHEDULE

A. Clear fully tempered float glass.

1. Minimum Thickness: 6 mm.

2. Safety glazing required.

B. Clear laminated glass with two plies of fully tempered float glass.

1. Minimum Thickness of Each Glass Ply: 3 mm, unless otherwise recommended by manufacturer for application indicated.

2. Interlayer Thickness: 0.060 inch (1.52 mm).

FOR OFFICIAL USE ONLY

GLAZING 088000 - 8

3. Safety glazing required.

END OF SECTION 088000

FOR OFFICIAL USE ONLY

ROLLER WINDOW SHADES 122413 - 1

05/17/16

SECTION 122413 - ROLLER WINDOW SHADES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including Federal Acquisition Regulation

(FAR) and General Services Administration Acquisition Regulation (GSAR) contract clauses, and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Manually operated roller shades with single rollers.

B. Related Requirements:

1. Section 061053 "Miscellaneous Rough Carpentry" for wood blocking and grounds for mounting roller shades and accessories.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product.

1. Include construction details, material descriptions, dimensions of individual components and profiles, features, finishes, and operating instructions for roller shades.

B. Shop Drawings: Show fabrication and installation details for roller shades, including shadeband materials, their orientation to rollers, and their seam and batten locations.

C. Samples: For each exposed product and for each color and texture specified, 250 mm (10 inches) long.

D. Product Schedule: For roller shades. Use same designations indicated on Drawings.

1.4 INFORMATIONAL SUBMITTALS

A. Qualification Data: For Installer.

B. Product Certificates: For each type of shadeband material.

C. Product Test Reports: For each type of shadeband material, for tests performed by a qualified testing agency.

FOR OFFICIAL USE ONLY

ROLLER WINDOW SHADES 122413 - 2

1.5 CLOSEOUT SUBMITTALS

A. Operation and Maintenance Data: For roller shades to include in maintenance manuals.

1.6 MAINTENANCE MATERIAL SUBMITTALS

A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.

1. Roller Shades: Full-size units equal to 5 percent of quantity installed for each size, color, and shadeband material indicated, but no fewer than two units.

1.7 QUALITY ASSURANCE

A. Installer Qualifications: Fabricator of products.

B. Mockups: Build mockups to verify selections made under Sample submittals, to demonstrate aesthetic effects, and to set quality standards for fabrication and installation.

1. Approval of mockups does not constitute approval of deviations from the Contract

Documents contained in mockups unless Architect specifically approves such deviations in writing.

2. Subject to compliance with requirements, approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion.

1.8 DELIVERY, STORAGE, AND HANDLING

A. Deliver roller shades in factory packages, marked with manufacturer, product name, and location of installation using same designations indicated on Drawings.

1.9 FIELD CONDITIONS

A. Environmental Limitations: Do not install roller shades until construction and finish work in spaces, including painting, is complete and dry and ambient temperature and humidity conditions are maintained at the levels indicated for Project when occupied for its intended use.

B. Field Measurements: Where roller shades are indicated to fit to other construction, verify dimensions of other construction by field measurements before fabrication and indicate measurements on Shop Drawings. Allow clearances for operating hardware of operable glazed units through entire operating range. Notify Architect of installation conditions that vary from

Drawings. Coordinate fabrication schedule with construction progress to avoid delaying the

Work.

FOR OFFICIAL USE ONLY

ROLLER WINDOW SHADES 122413 - 3

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Source Limitations: Obtain roller shades from single source from single manufacturer.

2.2 MANUALLY OPERATED SHADES WITH SINGLE ROLLERS

A. Basis-of-Design Product: Subject to compliance with requirements, provide products by

MechoShade Systems, Inc; or a comparable product by one of the following:

1. Draper Inc.

2. Hunter Douglas Contract.

3. Lutron Electronics Co., Inc.

4. Springs Window Fashions; SWFcontract.

B. Chain-and-Clutch Operating Mechanisms: With continuous-loop bead chain and clutch that stops shade movement when bead chain is released; permanently adjusted and lubricated.

1. Bead Chains: Manufacturer's standard.

a. Loop Length: Full length of roller shade.

b. Limit Stops: Provide upper and lower ball stops.

c. Chain-Retainer Type: As selected by Architect.

C. Rollers: Corrosion-resistant steel or extruded-aluminum tubes of diameters and wall thicknesses required to accommodate operating mechanisms and weights and widths of shadebands indicated without deflection. Provide with permanently lubricated drive-end assemblies and idle-end assemblies designed to facilitate removal of shadebands for service.

1. Roller Drive-End Location: As directed by Architect.

2. Direction of Shadeband Roll: Regular, from back (exterior face) of roller.

3. Shadeband-to-Roller Attachment: Manufacturer's standard method.

D. Mounting Hardware: Brackets or endcaps, corrosion resistant and compatible with roller assembly, operating mechanism, installation accessories, and mounting location and conditions indicated.

E. Roller-Coupling Assemblies: Coordinated with operating mechanism and designed to join up to three inline rollers into a multiband shade that is operated by one roller drive-end assembly.

F. Shadebands:

1. Shadeband Material: Light-filtering fabric.

2. Shadeband Bottom (Hem) Bar: Steel or extruded aluminum.

FOR OFFICIAL USE ONLY

ROLLER WINDOW SHADES 122413 - 4

a. Type: Enclosed in sealed pocket of shadeband material.

b. Color and Finish: As selected by Architect from manufacturer's full range.

G. Installation Accessories:

1. Recessed Shade Pocket: Rectangular, extruded-aluminum enclosure designed for recessed ceiling installation; with front, top, and back formed as one piece, end plates, and removable bottom closure panel.

a. Height: Manufacturer's standard height required to enclose roller and shadeband assembly when shade is fully open, but not less than 127 mm (5 inches).

b. Provide pocket with lip at lower edge to support acoustical ceiling panel.

2. Closure Panel and Wall Clip: Removable aluminum panel designed for installation at bottom of site-constructed ceiling recess or pocket and for snap-in attachment to wall clip without fasteners.

a. Closure-Panel Width: As indicated on Drawings.

3. Exposed Headbox: Rectangular, extruded-aluminum enclosure including front fascia, top and back covers, endcaps, and removable bottom closure.

a. Height: Manufacturer's standard height required to enclose roller and shadeband assembly when shade is fully open, but not less than 4 inches (102 mm).

4. Installation Accessories Color and Finish: As selected from manufacturer's full range.

2.3 SHADEBAND MATERIALS

A. Shadeband Material Flame-Resistance Rating: Comply with NFPA 701. Testing by a qualified testing agency. Identify products with appropriate markings of applicable testing agency.

B. Light-Filtering Fabric: Woven PVC-free fabric, stain and fade resistant.

1. Source: Roller shade manufacturer, Ecoveil Series.

2. Weave: Mesh.

3. Orientation on Shadeband: Up the bolt.

4. Openness Factor: 5 percent.

5. Color: As selected by Architect from manufacturer's full range.

2.4 ROLLER SHADE FABRICATION

A. Product Safety Standard: Fabricate roller shades to comply with WCMA A 100.1, including requirements for flexible, chain-loop devices; lead content of components; and warning labels.

FOR OFFICIAL USE ONLY

ROLLER WINDOW SHADES 122413 - 5

B. Unit Sizes: Fabricate units in sizes to fill window and other openings as follows, measured at 23 deg C (74 deg F):

1. Between (Inside) Jamb Installation: Width equal to jamb-to-jamb dimension of opening in which shade is installed less 6 mm (1/4 inch) per side or 13-mm (1/2-inch) total, plus or minus 3.1 mm (1/8 inch). Length equal to head-to-sill or -floor dimension of opening in which shade is installed less 6 mm (1/4 inch), plus or minus 3.1 mm (1/8 inch).

2. Outside of Jamb Installation: Width and length as indicated, with terminations between shades of end-to-end installations at centerlines of mullion or other defined vertical separations between openings.

C. Shadeband Fabrication: Fabricate shadebands without battens or seams to extent possible, except as follows:

1. Vertical Shades: Where width-to-length ratio of shadeband is equal to or greater than 1:4, provide battens and seams at uniform spacings along shadeband length to ensure shadeband tracking and alignment through its full range of movement without distortion of the material.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements for installation tolerances, operational clearances,and other conditions affecting performance of the Work.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 ROLLER SHADE INSTALLATION

A. Install roller shades level, plumb, and aligned with adjacent units according to manufacturer's written instructions.

1. Opaque Shadebands: Located so shadeband is not closer than 51 mm (2 inches) to interior face of glass. Allow clearances for window operation hardware.

B. Roller Shade Locations: As indicated on Drawings.

3.3 ADJUSTING

A. Adjust and balance roller shades to operate smoothly, easily, safely, and free from binding or malfunction throughout entire operational range.

FOR OFFICIAL USE ONLY

ROLLER WINDOW SHADES 122413 - 6

3.4 CLEANING AND PROTECTION

A. Clean roller shade surfaces, after installation, according to manufacturer's written instructions.

B. Provide final protection and maintain conditions, in a manner acceptable to manufacturer and

Installer, that ensure that roller shades are without damage or deterioration at time of Substantial

Completion.

C. Replace damaged roller shades that cannot be repaired, in a manner approved by Architect, before time of Substantial Completion.

END OF SECTION 122413

Addendum 04_docs.pdf
A-100
A-500
000010 TOC
SECTION 088000 - GLAZING