RFI_and_Responses_9.22.pdf
PDF 857 KB Posted
- Attached to
- SSA 1st Floor Model Field Office Federal contract opportunity
- Solicitation number
- GS-05-P-16-FB-C-7004
About this file
RFI Responses
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Pre_Proposal_Conference_Meeting_Minutes.pdf | ||
| SSA_MODEL_FIELD_OFFICE_PREBID_SIGN_IN.pdf | ||
| Pre_Proposal_Conference_Agenda.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ GS-05-P-16-FB-C-7004
SSA 1st Floor Model Field Office Harold Washington Social Security Center 600 W. Madison Street Chicago, IL 60661 RFI & Responses
1. Is the general contractor required to provide the televisions and monitors and supports/brackets?
Yes. See the A-series, AV-services and spec 274116 Schedule A for AV equipment list.
2. Is the general contractor required to provide the sidewalk closure permits or will this be provided by the owner?
These permits are to be provided by the General Contractor.
3. Sheet A-014 indicates the existing protection layer to be repaired as required above the basement roof slab. Please provide a specification for the waterproofing/protection layer/drainage mat.
The actual material of the protection board is unknown. The design team does not have any technical data on the existing plaza waterproofing products. The first attached picture shows the filter fabric and protection layer to expose the waterproofing membrane to see how it terminated against a precast panel. The second attached picture was taken by the GC during the demolition phase and provides more context.
The previous subcontractor for plaza work is W.R. Weis Company.