RFP GS05P13SVD0010 - OFFEROR QUESTIONS

Q1: Do you want bidders to prepare their quotes using the existing wage and benefit pricing?

A1: Offers should be prepared using the most current wage determination in the solicitation.

(See Amendment 001 for the most current wage determination.)

Q2: On award, when a new CBA is negotiated, will the contract be immediately modified to reflect any price escalation resulting from the new CBA?

A2: If a new CBA is not added during the solicitation phase and provided after the contract is awarded, then a modification will be issued when it received by GSA.

Q3: In Reference To (IRT) C.1 B, the prior contract required on-site presence between 05:30 AM and 7:30 PM and the new minimum is 05:30 AM to 11:00 PM. Please confirm this change.

A3: Yes, the on-site requirement for this solicitation and the subsequent contract is 5:30AM to

11:00PM.

Q4: IRT C.5 Startup Phase/Transition Phase – How is a bidder to account for the cost of transition prior to start of the contract as there is no separate CLIN?

A4: The startup phase/transition phase should be included in the monthly pricing for preventative maintenance for each building.

Q5: IRT C.23.4 – Reserved – What is the reserved topic?

A5: Section C.23.4 is a reserved section in all of the master specifications, thus the topic is unknown.

Q6: IRT C.24.6 Non-Destructive Chiller Tube Eddy Current Analysis (Additional Service) - This location has no chillers and there is no CLIN to price in the schedule B. Should this section be rescinded?

A6: Section 24.6 has been removed from the solicitation. See Amendment 001.

Q7: Can we receive or review the most current and complete "punch list" on the current contract?

A7: No. This information is not available for release.

Q8: Can we review the previous complete contract?

A8: No. This information is not available for release.