ADDENDUM #2

May 19, 2016

ADDENDUM #2

MAY 19, 2016

Project: Foley Lobby and Security Screening Station Upgrade Project | RWA N1054424

Solicitation Number: GS-02-P-16-PW-C-7004 Owner: GSA

Owner Point of Contact: Katie Wheeler, GSA Contracting Officer

Prepared by: N.K. BHANDARI, Architecture & Engineering, P.C.

TO ALL BIDDERS:

The following additions, deletions, and/or changes or clarifications to the drawings, specifications, and bidding documents for this project, shall become and are hereby made part of the Contract Documents. They change the original documents only in the manner and to the extent stated. Each bidder shall acknowledge receipt of this ADDENDUM in the appropriate location on the bid proposal form.

This ADDENDUM consists of two (1) pages, including this page. All requirements of the original Specifications and Drawings and previous Addendum, if applicable, shall remain in force except as noted by this ADDENDUM.

THE PURPOSE OF THIS ADDENDUM IS TO CHANGE THE FOLLOWING ITEMS:

DRAWINGS

Sheet number: Description of Change:

EY101, EY102 Revise General Floor Plan Note 1 to read as follows:

GC SHALL UTILIZE A QUALIFIED SECURITY CONTRACTOR FOR WORK IN THIS

CONTRACT. WORK IN THIS CONTRACT TO INCLUDE:

1) ALL SCHEDULED SECURITY DEVICES, PATHWAYS, WIRING FOR POWER,

EQUIPMENT, TERMINATIONS, PROGRAMMING, AND COMMISSIONING

(INCLUSIVE OF ALL COMPONENTS FOR SPECIFIED OPERATION)

WORK BY OTHERS (NIC) (TENANT SECURITY CONTRACTOR: TYCO, COORDINATE

WITH OWNER) SHALL INCLUDE:

1) CABLING (CAMERAS, DURESS, ACCESS CONTROL, ETC.)

FOR ANY INTERFACE WITH EXISTING FIRE ALARM SYSTEMS (DOOR INTERLOCKS,

ETC.), THE GC SHALL UTILIZE AN AUTHORIZED TECHNICIAN TO PERFORM THIS

WORK. COORDINATE WITH GSA PROPERTY MANAGEMENT FOR CONTACT

INFORMATION AS REQUIRED.

ATTACHMENTS

N/A

END OF Addendum #2