Golf Club Road at Eager Road Roundabout Construction.pdf
PDF 9 MB Posted
- Solicitation number
- 459.0077AT
- Issued by
- Kent County, Michigan
About this file
This is a sealed bid proposal document issued by the Livingston County Road Commission for the Golf Club Road at Eager Road Roundabout Construction project (Project No. 459.0077AT) in Oceola Township, Livingston County, Michigan. The project encompasses 0.5 miles of modern roundabout construction including concrete pavement, hot mix asphalt, drainage improvements, and pavement markings in Sections 31 and 32. Specific project quantities include 1,258 tons of HMA surface, 4,033 square yards of HMA surface milling, 1,725 square yards of concrete pavement, 2,245 feet of curb and gutter placement, 3,364 cubic yards of earth excavation, 2,919 tons of aggregate base, and 2,526 cubic yards of subbase CIP. Sealed proposals must be received by 10:00 A.M. on Tuesday, June 23, 2026, at the Livingston County Road Commission office located at 3535 Grand Oaks Drive, Howell, Michigan 48843, at which time bids will be publicly opened and read aloud. A mandatory preconstruction meeting will be held after project award. Construction is anticipated to begin no earlier than July 1, 2026, with an open-to-traffic date of October 16, 2026, and a final completion date of November 6, 2026. Plans and specifications are available at the LCRC office for a non-refundable fee of $25.00, or $30.00 with mail delivery, or electronically through the Michigan Intergovernmental Trade Network (MITN).
Bidders must submit a certified or cashier's check in the amount of $10,000.00 as a proposal guarantee payable to the Livingston County Road Commission. The successful bidder must furnish performance and lien bonds equal to 100 percent of the contract price and provide evidence of insurance coverage including workers compensation at statutory limits, bodily injury liability of $500,000 per person and $1,000,000 aggregate, and property damage of $500,000 per occurrence. Prequalification with MDOT as a Prime Contractor is required. Liquidated damages of $1,500.00 per day will be assessed for failure to meet interim completion, open-to-traffic, and final completion dates. Monthly payments will be made based on estimates prepared by the Engineer, with payments approved at the Board's second regular meeting of each month. The project must comply with the 2020 Standard Specifications for Highway Construction from the Michigan Department of Transportation, including special provisions for maintaining traffic, which prohibit work on Sundays without permission and establish specific lane closure restrictions and work hour limitations based on holiday periods and day of week.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROPOSAL
FOR
PROJECT
PROJECT:
Item No. 1 – Golf Club Road at Eager Road Roundabout Construction
Project Number – 459.0077AT Golf Club Road at Eager Road Roundabout construction in Sections 31 & 32 in Oceola Township, Livingston County, Michigan
Includes: 0.5 mi construction of a Modern Roundabout, concrete pavement, hot mix asphalt, drainage improvements and pavement markings; altogether with the necessary other related work.
Proposals may be obtained at the Livingston County Road Commission office at 3535 Grand Oaks Drive, Howell Michigan 48843. To request an electronic copy to be sent, email: mail@livingstonroads.org
Bids will be publicly opened and read aloud at 10:00 A.M., Tuesday, June 23, 2026, at the above-mentioned location.
THE RIGHT IS RESERVED TO REJECT ANY OR ALL PROPOSALS
Advertisement For Bid
LIVINGSTON COUNTY ROAD COMMISSION
HOWELL MICHIGAN, 48843
Sealed proposals will be received by the Board of County Road Commissioners, of the County of Livingston at 3535 Grand Oaks Drive, Howell, Michigan, 48843 until, 10:00 A.M., Tuesday June 23, 2026, at which time and place proposals will be publicly opened and read aloud for the following project:
Item No. 1 – Golf Club Road at Eager Road Roundabout Construction
Project No. – 459.0077AT Golf Club Road at Eager Road Roundabout construction in Sections 31 & 32 in Oceola Township, Livingston County, Michigan
Includes: 0.5 mi construction of a Modern Roundabout, concrete pavement, hot mix asphalt, drainage improvements and pavement markings; altogether with the necessary other related work.
Project Quantities: HMA surface 1258 Tons, HMA surface milling 4033 Syd, Concrete Pavement 1725 Syd, Curb & Gutter placement 2245 Ft, Earth Excavation 3364 Cyd, Aggregate Base 2919 Tons, Subbase CIP 2526 Cyd ; along with other necessary related work.
Plans and specifications may be obtained at the Livingston County Road Commission (LCRC) office, 3535 Grand Oaks Drive, Howell, Michigan for a non-refundable fee of $25.00, by mail for an additional $5.00 postage and handling, or electronically via the Bidnet Direct Michigan Inter-Governmental Trade Network (MITN). All proposals must be physically submitted in sealed envelopes bearing the name of the bidder and a notation indicating the project on which bid is submitted. All proposals must be submitted in their entirety. A certified or cashier’s check on an open, solvent bank shall be submitted with each individual bid in the amount of $10,000.00 payable to the Livingston County Road Commission for Item No.1.
The LCRC officially distributes bid documents through the Michigan Intergovernmental Trade Network (MITN). Copies of documents obtained from any other source are not considered official copies. Only those vendors who obtain documents from the MITN system are guaranteed access to receive addendum information if such information is issued. If you obtained this document from a source other than MITN, it is recommended that you register on the MITN site, www.mitn.info and obtain an official copy and any addenda. The LCRC reserves the right to use any other method of distributing bid information; however, any additional method of distribution will also direct vendors to MITN.
Prequalification with MDOT as a Prime Contractor is required.
The Board reserves the right to accept or reject any or all bids, to waive any informality in bids and to accept the bid which is in the best interest of the County of Livingston.
THE BOARD OF COUNTY ROAD COMMISSIONERS
OF THE
COUNTY OF LIVINGSTON, MICHIGAN
PAUL S. FUNK – CHAIR
THOMAS W. ECONOM – VICE CHAIR
STEPHEN F. CRANE – MEMBER
Advertisement For Bid Proposal Instructions to Bidders Supplemental Specifications
Limitations of Operations and Competence of Workers
Public Act 278 of 1980:
Prohibition of Discrimination in State Contracts:
Unavoidable Delays and Extension of Time
Furnishing Right of Way
Protection and Restoration of Property
Contractor - Furnished - Borrow & Spoil Areas
Prosecution and Progress
Liquidated Damages
Taxes
Insurance Requirements
Bonding Requirements
Written or Oral Explanation General Requirements and Covenants
Pre-Qualification of Contractors and Sub-contractors
Subletting of Contract Work
Scope of Work
Control of Work
Control of Materials
Authority and Duties of the Inspector Supplemental Specifications
Liability of Livingston County Road Commission Employees
Rights and responsibilities of Contractors and Sub-contractors:
Partial Payments
Final Payment
No Waiver of Legal Rights
Changes in Quantities, Plans or Character of Work
Progress Clause MDOT Special Provisions
Maintaining Traffic
Aggregate Base Course
Decorative Concrete Pavement
Use of Crushed Concrete for Dense & Open Graded Agg ..84
Mobile Attenuator
Slope Restoration , Non-Freeway
Vertical Exploratory Excavation for Relocation
Quality Index for Portland Cement Concrete (For Local Agency Projects Only)
Portland Cement Concrete Prices for Adj
Maintenance Gravel, Driveway Maintenance and Intersection Maintenance Measurement and Payment
Erosion Control Silt Fence
Non-Compliance with Soil Erosion and Sedimentation Control Requirements
Acceptance of Hot Mix Asphalt Mixture on Local Agency Projects
Hot Mix Asphalt Prices for Adjustments
Sampling Asphalt Binder on Local Agency Projects
Backfill for Concrete Curb, Gutter and Dividers
Decorative Stone, (Type)
Landscape Fabric
Water Main Materials and Construction
Temporary Water Main Materials and Construction
Video Inspection of Underdrain
Curb and Gutter, Conc, Detail _, Modified Utility Coordination
ERRATA
Itemized bid sheet
PROPOSAL
PROJECT:
Item No. 1 - Golf Club Road at Eager Road Roundabout Construction
Project Number – 459.0077AT
Golf Club Road at Eager Road Roundabout construction in Sections 31 & 32 in Oceola Township, Livingston County, Michigan
Includes: 0.5 mi construction of a Modern Roundabout, concrete pavement, hot mix asphalt, drainage improvements and pavement markings; altogether with the necessary other related work.
To the Board of County Road Commissioners of the County of Livingston, State of Michigan:
Commissioners, The undersigned has examined the plans, specifications and the location of the work described herein and is fully informed as to the nature of the work and the conditions relating to its performance and understands that the quantities shown are approximate only and are subject to either increases or decrease.
The undersigned hereby proposes to furnish all necessary machinery, tools, apparatus, and other means of construction, to complete all the work, furnish all the materials, except as otherwise specified herein, and, for the unit prices named in the itemized bid, to complete the work herein described in strict accordance with the plans therefore and in strict conformity with the requirements of the Livingston County Road Commission, the 2020 Standard Specifications for Highway Construction, Michigan Department of Transportation (MDOT) and such other special provisions and supplemental specifications as may be a part of this proposal.
The undersigned further proposes to do such extra work as may be authorized by the Board of County Road Commissioners of the County of Livingston, prices for which are not included in the itemized bid.
Compensation shall be made on the basis agreed upon before such extra work is begun.
The undersigned has enclosed a certified check, cashier's check or bank money order as a proposal guarantee in the amount of $10,000.00 payable to the Board of County Road Commissioners of the County of Livingston, Michigan. If the undersigned is the successful bidder and fails to enter into contract or to furnish satisfactory bonds to the Board of County Road Commissioners of the County of Livingston, Michigan, within 21 days, said check shall be forfeited to the Board of County Road Commissioners of the County of Livingston, Michigan, as liquidated damages. It is understood that the check of the lowest bidder will not be returned until the contract has been executed. The proposal guarantees bid deposits of all except the lowest bidder will be returned within a reasonable time after the accuracy of all bids have been determined.
CONTRACTOR:_____________________________________________
SIGNED BY: _______________________________________________
ADDRESS:_________________________________________________
CITY ________________________________________ ZIP _________
TELEPHONE: ______________________________________________
EMAIL: ____________________________________________________
INSTRUCTIONS TO BIDDERS
Proposal Submission
Notice to Bidders.
Preparation of Proposal.
The proposal shall be legibly prepared in ink, or typed, on the form provided. The Bidder shall specify a unit price for each item, except where a lump sum item is called for. Prices for lump sum items shall be entered only in the Amount column. The proposal shall be signed by an authorized representative of the Bidder and include the complete address of the Bidder. The entire signed proposal must be submitted with the Project Bid.
A Bidder may alter a unit or lump sum item price entered on the Proposal. To make an alteration, the Bidder shall cross out the entry and enter the new figure above or below the deleted entry. An authorized representative of the Bidder must initial on the line of the change. Any alterations and initials shall be handwritten in ink. An authorized representative of the Bidder must sign the proposal.
Irregular Proposals.
By submitting a proposal, a Bidder agrees to the Michigan Department of Transportation’s procedures and standards for accepting or rejecting irregular proposals. Unless this section is expressly modified by the County in the Proposal Form, a statement that a proposal may or will be rejected for a specified reason will be acted upon pursuant to the following:
A. Proposals will be considered irregular and will be rejected for any of the following reasons:
1. The proposal does not contain a unit price for each pay item listed in the Unit Prices column or Lump Sum price in the Amounts column, as applicable. While a blank space is unacceptable, the explicit quotation of zero does constitute a price and, if awarded the contract, the Bidder would be bound to perform that item of work for zero payment and to do so to the same extent as if a positive numeric price had been quoted.
2. A unit price under the Unit Price column of Lump Sum price in the Amounts column is not capable of being read or deciphered by the Department. In attempting to read or deciphered a price, the County may consider other information in the proposal which tends to confirm what the digit(s) in question represent.
3. The proposal is not signed by an authorized representative of the Bidder, who has been designated in writing in accordance with subsection 102., and/or the entire signed proposal is not submitted with the Bid.
4. The Bidder, except as otherwise provided in the Subsection 102, is not prequalified or has insufficient prequalification to complete the project in accordance with the project plan and proposal as determined by the Engineer.
Proposal Submission
B. Proposals will be considered irregular and may be rejected for any of the following reasons:
1. A Unit Price or a Lump Sum item has been altered and has not been revised as provided under subsection 102.06.
2. The form is altered or any part of the form is detached.
3. There is an unauthorized addition, deletion, or alteration to the proposal.
4. There is an unauthorized alternate proposal or conditional proposal.
5. There is an irregularity of any kind which tends to make the proposal incomplete, indefinite, or ambiguous as to its meaning.
6. The proposal fails to comply with any other proposal requirement.
7. Any provision is added to the proposal reserving the right, for the Bidder, to accept or reject an award of the contract.
C. It is the intention of the County to waive irregularities under Subsection 102.06.C of the Michigan Department of Transportation 2020 Standard Specifications for Construction and accept the lowest qualified proposal whenever the considerations set forth in this subsection do not justify rejection of the proposal. In determining whether to waive an irregularity and accept a proposal, the County will consider whether the nature or extent of the irregularity is such that acceptance of the proposal might confer on the Bidder an unfair advantage or possibility for proposal manipulation; jeopardize funding for the project, impose unreasonable administrative burdens on the County; or, otherwise undermine the integrity of a fair, open and honest competitive bidding process. Where to do so would not be contrary to those considerations, the County may allow a Bidder to remedy a proposal irregularity but in no event will a Bidder be permitted to do so by increasing or decreasing its proposal price for the project as specified in the proposal documents. The authority to waive irregularities is not intended to allow the County to choose among multiple prices improperly quoted for the same item of work where only one of those choices would make that proposal the lowest accepted proposal.
D. Only a Bidder whose proposal has been rejected pursuant to Subsection 102.06 and who would otherwise be the lowest Bidder has an opportunity to appeal a proposed rejection under Subsections
102.12 and 102.13. Once all under the above named subsections, the decision of the County Board of Road Commissioners is final and binding on all Bidders.
SUPPLEMENTAL SPECIFICATIONS
Limitations of Operations and Competence of Workers
The Contractor shall not carry out the construction operations on Sunday, unless otherwise specified in the proposal, without permission from the Engineer except for the purpose of making emergency repairs and for the proper protection of the work such as the curing of concrete.
The Engineer reserves the right to require the Contractor to cease construction operations during holiday periods, or at such other times as may be determined to be in the interest of the general public.
In case of a dispute arising between two or more Contractors or others as to the respective rights of each under these specifications, the Engineer shall determine the matters at issue and shall define the respective rights of the various interests involved, in order to secure the completion of all parts of the work in general harmony and with satisfactory results. The Engineer's decision shall be final and binding on all parties concerned and shall not in any way be cause for a claim for extra compensation by any of the parties.
The Contractor shall at all times employ sufficient labor for prosecuting the several classes of work to full completion in the manner and time required by the specifications.
Workers shall have sufficient skill and experience to perform properly the work assigned to them. Workers engaged in special work or skilled work shall have sufficient experience in such work and in the operation of the equipment required to perform all work properly and satisfactorily.
Public Act 278 of 1980:
No Contractor will be awarded a contract to perform work on this project who is listed in the register maintained by the state of Michigan, department of labor, of employees who have been found in contempt of court by a federal court of appeals, on not less than three (3) occasions involving different violations during the preceding seven (7) years, for failure to correct an unfair labor practice, as prohibited by Section 8 of Chapter 372 of the National Labor Relations Act, 29 U.S,C. 158, and in accordance with P.A. 278 of 1980.
The above statement applies to material suppliers and manufacturers.
Prohibition of Discrimination in State Contracts:
Contractors or their Sub-contractors performing work on this project hereto agree to comply with the state of Michigan provisions for "prohibition of discrimination of state contracts" as it applies to local government contracts.
Unavoidable Delays and Extension of Time
Unavoidable delays of the successful Contractor in the commencement, prosecution, or completion of this work resulting from:
A. Any act of omission by the Livingston County Road Commission or its agents.
B. Injunctions or acts of public authorities in consequence of acts or omissions of the Livingston County Road Commission or its agents.
C. Reasons of any cause of circumstances, weather conditions being specifically excepted, which the Livingston County Road Commission may decide is absolutely and clearly beyond the control of the Contractor.
D. Strike, riots, war, insurrection or acts of God.
E. Failure of other government Contractors work in the specified area of the project to perform to their timetable.
May entitle the successful Contractor to an extension of time. The Livingston County Road Commission Highway Engineer will make this determination.
Legal Relations and Responsibilities to the Public Furnishing Right of Way
The Livingston County Road Commission will be responsible for securing all necessary right-of-way;
these rights-of-way may or may not be shown on the plans.
Protection and Restoration of Property The Contractor’s attention is directed to the notes on Page 6 of the plans.
Contractor - Furnished - Borrow & Spoil Areas Unless otherwise indicated on the plans or in the proposal, the Contractor shall be responsible for furnishing all borrow areas and spoil areas for disposal of surplus or unsuitable materials. Where the Contractor must accomplish this outside right-of-way or outside the grading limits defined on the plans, he shall first obtain and file with this department written permission to do so from the affected property owner.
Prosecution and Progress The Livingston County Road Commission County Highway Engineer may require, as protection to the welfare, health and safety of the public, units of work to be performed by the Livingston County Road Commission force. Said units of work being the responsibility of the Contractor; said units of work to be performed with or without notification to the Contractor or the surety.
Contractor will be charged equipment rental rates as listed in the current edition of rental rates for construction equipment prepared by associated equipment distributor; and for labor at the rate of one and one half (1.5) x hourly rate per hour per man plus overtime charges of one and one half times (1.5) the base hourly labor rate for all time outside the normal road commission shift.
The time charged to the Contractor shall be from the time that the men and equipment leave the road commission yard to the time that it returns to the road commission yard.
Liquidated Damages For failure on the part of the Contractor to complete the entire project on or before any of the dates designated in the progress schedule, the Contractor shall pay the Livingston County Road Commission an additional $1,500.00 per day as and for liquidated damages not as a penalty. Assessment of liquidated damages shall be in accordance with section 108.11 of the Michigan Department of Transportation Standard Specifications. The Livingston County Road Commission will have the right to deduct such amount from moneys due or which may become due under the contract.
SPECIAL PROVISIONS
Taxes
The Contractor shall include and be deemed to have included in his bid and contract price, all Michigan sales and use taxes currently approved by legislative enactment and as administered by the Michigan Department of Revenue on the bid date.
If the Contractor is not required to pay or bear the burden, or obtains a refund or drawback, in whole or in part, of any Michigan sales or use tax, interest or penalty thereon, which was required to be and was deemed to have been included in the bid and contract price, the contract price shall be reduced as a refund or otherwise shall ensure solely to the benefit of the Livingston County Road Commission
Insurance Requirements The bidder to whom the contract is awarded will be required to furnish evidence of insurance coverage in the following types and amounts showing the Livingston County Road Commission as additional insured.
Certified copies of the policies shall be supplied to the Livingston County Road Commission.
INSURANCE REQUIREMENTS:
TYPE LIMITS NOT LESS THAN
a. Workers Compensation Statutory Limit
b. Bodily Injury Liability $500,000 - each person / $1,000,000 - aggregate
c. Property Damage $500,000 - each occurrence
Bonding Requirements The bidder to whom the contract is awarded shall furnish two (2) surety company bonds, in the amount of 100% of the contract price, as follows:
A. Performance bond, to Livingston County Road Commission for the faithful fulfillment of the terms of the contract.
B. Lien bond, to Livingston County Road Commission for the payment of all labor and material used in the work.
SPECIAL PROVISION
Written or Oral Explanation
Should a bidder find discrepancy in or omissions from the contract documents, or should he be in doubt as to their meaning, he should at once notify the Engineer and request an interpretation thereof. The County Engineer will thereupon promptly send written instructions in an addendum to all bidders. The Livingston County Road Commission will not be responsible for any oral instructions.
GENERAL REQUIREMENTS AND COVENANTS
The general requirements and covenants shall be in accordance with the 2020 Standard Specifications for Highway Construction, Michigan Department of Transportation, except as herein provided:
Pre-Qualification of Contractors and Sub-contractors It is the intent of the Board to award this contract to a competent contractor. Therefore, when obtaining plans and proposal for the work, the Board reserves the right to ask for a statement from the Contractor of the work previously completed or under contract at this time similar to the work covered by this proposal. This will include work under contract to the Michigan Department of Transportation.
The Board reserves the right to obtain a similar statement from all or any sub-contractors as designated by the prime contractor and to determine their qualifications in the best interest to the Board.
Subletting of Contract Work The term subletting shall be understood to mean the arrangement with any party or parties to execute a part of the contract work. Subletting of contract work shall be in accordance with section 108.01 of the Michigan Department of Transportation 2020 Standard Specifications for Construction except as herein provided:
Approval of the subletting of any portion of the contract will not be given unless and until the Contractor shall have filed with the Livingston County Road Commission a true copy of the subcontract, bearing the written consent of the surety thereto. It is understood and agreed that the Livingston County Road Commission's acceptance of a Sub-contractor or approval of a subcontract is for the benefit of the Livingston County Road Commission and is not for the benefit of the Contractor or any other person, firm, or organization nor is it a guarantee or warranty of the Sub-contractor's ability to perform or complete the work contained therein.
The Contractor remains fully responsible to the Livingston County Road Commission for completion of the work in accordance with the contract as if no portion of it had been subcontracted.
Scope of Work The Contractor shall furnish all labor, materials, equipment, tools, transportation and necessary supplies, and shall perform all operations required to complete the work in accordance with the specifications, and the lines, grades and cross sections provided for on the plans or by authorization.
Control of Work All work to be accomplished shall be under the direct supervision of the County Engineer or his authorized representative. It is expressly understood that any approvals, reviews, and inspections of any nature by the Livingston County Road Commission, its agents, officers, and employees, shall not be construed as a warranty or assumption of liability on the part of the Livingston County Road Commission. Any such approvals are for the sole and exclusive purposes of the Livingston County Road Commission, which is acting in a governmental capacity under this contract. Any approvals, reviews, and inspections by the Livingston County Road Commission will not relieve the Contractor of the Contractor’s obligations hereunder, nor are such approvals, reviews, and inspections to be construed as a warranty as to the propriety of the Contractor’s performance, but are undertaken for the sole use and information of the Livingston County Road Commission
Control of Materials Testing of all materials used in the construction of this project will be performed by the Livingston County Road Commission, by commercial testing concerns, or other testing laboratories as designated by the Engineer. Where a material is to be accepted by certification, the Contractor shall furnish the Engineer with a copy of the certification of quality as provided by the producer, which shall identify the materials by name and specification designation and shall name the source of the material. The Livingston County Road Commission shall have complete access as required to all parts of the work to be incorporated into this project.
Authority and Duties of the Inspector Inspectors may be appointed and directed to inspect all materials used and all work done. The inspection may extend to all parts of the work and to the preparation or manufacture of the materials for use in the work. The Inspector will not be authorized to revoke, alter, enlarge, or relax any of the provisions of these specifications, or to change the plans in any particular. In case of any dispute between the Contractor and the Inspector as to the materials furnished or the manner of performing the work, the Inspector shall have the authority to reject materials or suspend the work until the question at issue can be referred to and decided by the Engineer. Work done contrary to the Inspector's direction or while suspended by the Inspector will be considered unauthorized and may have to be removed at the Contractors expense in accordance with section
104.05 of the Michigan Department of Transportation Standard Specifications for Construction. In no instance shall any act or omission on the part of the Inspector relieve the Contractor of the responsibility of completing the work in accordance with the plans and specifications.
SUPPLEMENTAL SPECIFICATIONS
Liability of Livingston County Road Commission Employees
It is expressly understood and agreed that inspections made by employees or agents of the Livingston County Road Commission are for the benefit of the government owner and do not create any duty to provide a safe working area for either the Contractor or any of the Contractor's agents or employees. However, if the Engineer is aware of some noncompliance with health, safety, or pollution control requirements and issues a notice of noncompliance accompanied by a statement of the corrective action to be taken, the Contractor, upon receipt of such notice, shall promptly correct the condition. In the event the Contractor fails or refuses to promptly take the necessary corrective action, the Engineer may stop any or all work on the project until satisfactory corrective action has been taken. Loss of time resulting from such stop orders shall not be the subject of any claims for damages or extension of time by the Contractor.
Prior to commencement of construction activities on the project, the Contractor shall comply with the following provisions:
1. Safety Supervisor - The Contractor shall designate a person in his organization with authority and responsibility to administer the accident and fire prevention program on the work to be performed under the contract who will be known as the safety supervisor. An alternate safety supervisor shall be named, who shall perform these functions in the absence of the safety supervisor. The person designated as safety supervisor, or alternate, shall be able to devote as much time as is necessary for this responsibility.
2. Construction safety program - Prior to any on-site work, the Contractor shall submit, in writing, a construction safety program, outlining specifically the Contractor's plan for accident and fire prevention, or mitigation, on the work to be done under the contract, and for carrying out the provisions of these specifications. The Contractor shall meet in conference with the Engineer to discuss the construction safety program and to develop mutual understanding to govern the administration of the program.
Final Inspection, Acceptance and Final Payment
Rights and responsibilities of Contractors and Sub-contractors:
All obligations and claims made pursuant to labor or material furnished in performing work in conformance with the agreed understanding of the contracting parties shall be governed by 1963 P.A. 213, being sections
129.201 through 129.211 of the 1970 Compiled Laws of Michigan.
Partial Payments Payments will be made monthly on the basis of the value of the work performed and accepted having been earned during the estimate period. Said payments will be based upon estimates prepared by the Engineer of the value of the work performed and materials complete in place in accordance with the contract. Such estimates are subject to final balancing at the time of the final estimate as provided in section 109.07 of the Michigan Department of Transportation 2020 Standard Specifications for construction. The pay period for contract items shall end on the Saturday prior to the third Thursday of each month. Payments to contractors shall be approved at the Board’s second regular meeting (fourth Thursday) of each month.
Final Payment Final payment will not be made until the Contractor has filed with the Livingston County Road Commission the consent of the Surety to payment of the final estimate and satisfactory evidence by affidavit or otherwise that all indebtedness by reason of the contract has been secured. In case such evidence is not furnished, the Livingston County Road Commission may retain out of any money due said Contractor sums sufficient to cover all lien able claims unpaid.
The Livingston County Road Commission will be able to recover, in the final estimate, from the Contractor all overpayments made as a result of the Engineers estimates unless the final estimate is issued more than 6 months after the acceptance of the project and the overpayment was paid to a Sub-contractor not in existence at the time of the final estimate.
Any claim for additional compensation that has not been approved on or before the date that the Contractor signs the final estimate, shall be considered as denied by the Livingston County Road Commission as of that date.
* * * * * * * * * * * * * * * * * * * * * * * N O T E * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
CONTRACTOR PAYMENTS WILL BE MADE ON THE FRIDAY FOLLOWING THE FOURTH THURSDAY
OF THE MONTH.
No Waiver of Legal Rights.
The Livingston County Road Commission shall not be precluded or estopped by any measurement, estimate or certificate made either before or after the completion and acceptance of the work and payment therefore, from showing the true amount and character of the work performed and the materials furnished by the Contractor, nor from showing that any such measurement, estimate or certificate is untrue or incorrectly made, nor that the work or materials do not conform to the contract. The Livingston County Road Commission shall not be precluded or estopped, notwithstanding any such measurement, estimate or certificate and payment in accordance therewith from recovering from the Contractor and the Surety such overpayment as may have caused by the erroneous measurement, estimate, or certification and such damages as it may have sustained by reason of the Contractor's failure to comply with the terms of the contract. Neither the acceptance by the Engineer nor the Board of Road Commissioners of the County of Livingston, nor any payment for or acceptance of the whole or any part of the work, nor any extension of time nor any possession taken by the Livingston County Road Commission shall operate as a waiver of any portion the contract or of any power herein reserved, or any right to damages herein provided. A waiver of any breach of the contract shall not be held to be a waiver of any other subsequent breach.
Changes in Quantities, Plans or Character of Work The Engineer reserves the right to make, by work order or authorization, at any time during the work such changes in quantities and such alterations in the work as may be necessary to satisfactorily complete the project. Such changes in quantities and alterations shall not invalidate the contract nor release the surety, and by signing a work order or authorization, the Contractor agrees to perform the work as altered, and agrees to accept, as payment in full for such work, the monetary amounts set forth in such work order or authorization as balanced by the Engineer. In addition, by signing an authorization, the Contractor releases the County from any and all claims for compensation with regard to the items of work specified in the authorization;
including but not limited to, any and all claims for delay and overhead, unless the engineer is notified in writing at the time of signing the authorization that the Contractor refuses to release the County from such claims. All increases in quantities of work which appear in the contract as pay items shall be paid for at contract unit prices. Decreases in quantities included in the contract shall be deducted from the contract at contract unit prices.
PROGRESS CLAUSE
The Engineer anticipates that construction can begin no earlier than July 1, 2026, or as directed by the Engineer.
In no case shall any work be commenced prior to receipt of formal notice of award by the Department.
The Contractor shall prepare and submit a complete, detailed, signed Progress Schedule to the Engineer.
The project must be completely open to traffic by the open to traffic date of October 16, 2026.
The entire project must be completed by the final completion date of November 6, 2026.
After award and prior to the start of work, the Contractor must attend a preconstruction meeting with the Engineer. The Engineer will determine the day, time and place for the preconstruction meeting. The meeting will be conducted after project award and may be rescheduled if there are delays in the award of the project.
The named subcontractor(s) for Designated and/or Specialty Items, as shown in the Proposal, should attend the preconstruction meeting if such items materially affect the work schedule.
Failure by the Contractor to meet interim completion, open to traffic, and/or final completion dates will result in the assessment of liquidated damages in accordance with subsection 108.10 of the Standard Specifications for Construction.
V4.0
LIVINGSTON COUNTY ROAD COMMISSION
SPECIAL PROVISION
FOR
MAINTAINING TRAFFIC
LCRC 1 of 5 5/15/2026
a. Description. This special provision consists of requirements and restrictions to maintain traffic on Golf Club Road and Eager Road in Oceola Township, Livingston County.
b. General. Maintain traffic throughout the project in accordance with the standard specifications, typicals, and supplemental specifications in the contract and as described on the plans for this project.
c. Construction Influence Area (CIA). The CIA includes the right-of-way of the following roadways, within the approximate limits described below:
1. On Eager Road from Golf Club Road to approximately ½ mile north of Golf Club Road.
2. On Golf Club Road from approximately ½ mile west of Eager Road to ½ mile east of
Eager Road.
3. In addition, the CIA includes the right-of-way of any designated detour route or alternate route, intersecting roads and ramps adjacent to the work zone for a distance of approximately ¼ mile in advance of the work zone or as far as the construction or detour signing extends.
d. Traffic Restrictions. Maintain traffic in accordance with the Maintaining Traffic Typicals contained herein, except as noted below. Changes or adjustments to the Maintaining Traffic Typicals may be necessary to fit field conditions, subject to approval of the Engineer or as determined by the Engineer.
1. Utilize the following Maintaining Traffic Typicals:
A. 100-GEN-KEY
B. 101-GEN-SPACING-CHARTS
C. 102-GEN-NOTES
D. 103-GEN-SIGN
E. 104-GEN-AB
F. 106-GEN-SPEED-NFW
G. 107-GEN-SPEED
LCRC 2 of 5 5/15/2026
H. WZD-100-A
I. WZD-125-E
2. Do not deliver material, or close lanes (other than approved stage closures) during the holiday periods as defined in Table 1.
Table 1: 2026 Holiday Periods
Holiday Start Date and Time End Date and Time
Independence Day 3:00 pm, Thursday, 07/02/26 6:00 am, Monday, 07/07/26
Labor Day 3:00 pm, Friday, 09/04/26 6:00 am, Tuesday, 09/08/26
3. Perform work and lane closures within the allowable time frames as shown in Table 2, unless otherwise approved by the Engineer.
Table 2: Work Hour Restrictions
Closure Type Start Time
End Time
M Tu W Th F Sa Su
Work Hours
00:00 07:00 0 0 0 0 0 0 0
07:00 19:00 ∞ ∞ ∞ ∞ ∞ ∞ 0
19:00 24:00 0 0 0 0 0 0 0 ∞ = Closure is allowed, and the frequency is not limited during the project timeframe # = The number of times closures can take place during the project timeframe.
4. Close any dedicated lanes (exit, ramp, turn, etc.) prior to the location under construction.
5. When a lane is closed, place channelizing devices at cross streets and major drives to form a radius that clearly defines the approaches to the through and turning traffic.
6. Maintain access to all driveways as directed by the Engineer unless prior agreements are made with the respective property owners. The cost of constructing driveways part width will not be paid for separately but will be considered included in the cost of other driveway pay items.
e. Traffic General.
1. For any lane open to traffic, provide a minimum lane width of 11 feet with 2 feet of shy distance on both sides unless identified otherwise on plans.
2. Do not close lanes or utilize traffic regulation sequences where work can be accomplished with a shoulder closure. Do not occupy any part of the active traffic lane with personnel or equipment when utilizing a shoulder closure. Place lane closures and traffic regulation operations only in areas as show on the plans unless otherwise directed by the Engineer.
LCRC 3 of 5 5/15/2026
3. Prior to shifting traffic onto shoulders or opening any lanes/shoulders and/or ramps, remove, by sweeping all accumulated debris that has collected within the shoulder and/or within the closed lane/shoulder.
4. Develop and submit to the Engineer an Internal Traffic Control Plan (ITCP) per subsection 104.11.B of the Standard Specifications for Construction. Submit the ITCP at the preconstruction meeting. The Engineer will have 7 calendar days to review the ITCP for approval or provide comments for revisions required to obtain approval. Include in the ITCP, at a minimum, the proposed ingress/egress locations for construction equipment and vehicles, traffic control devices that will be utilized to warn the motoring public of ingress/egress locations, and measures that will be taken to ensure compliance with the ITCP. Ensure that the ITCP minimizes conflicts between construction vehicles and motorists and maintains overall safety and mobility within the work zone. No work may begin prior to approval of the ITCP. Additional time required to obtain an approved ITCP will not be cause for delay or impact claims. All costs associated with obtaining an approved ITCP, providing and executing all parts of the approved ITCP including required traffic control devices, or resolving an incomplete or unacceptable ITCP will be borne by the Contractor.
5. Protect the work area at the end of each day. Close all open access points on the project to traffic with Type III barricades or other devices approved by the Engineer.
6. The Engineer will be responsible for notifying emergency services, transit agencies, law enforcement and schools prior to any lane closures, detours or major traffic shifts. In addition, the Contractor will be responsible for working with and complying with any coordination that is necessary with the Department and emergency services, transit agencies, law enforcement and schools. All costs associated with these coordination efforts will be considered included in the pay item “Minor Traf Devices”.
f. Stage Construction. Maintain traffic in accordance with the restrictions listed in section
d. Traffic Restrictions and the sequence of operations contained herein. Use of an alternate traffic control plan is subject to review and approval by the Engineer.
1. Stage 1.
A. Construct roundabout including traffic legs along Golf Club Road and Eager Road
B. Close and detour traffic as shown in the plans. Local traffic must be maintained.
g. Detours.
1. Signs should be on both sides of the roadway when the work is taking place on the freeway or a boulevard section.
2. Cover all detour signs installed prior to closing a road. Do not uncover detour signing until just before the closure is in effect. Immediately remove or cover all detour signing upon opening the road to traffic.
h. Traffic Control Devices. Ensure all traffic control devices are in accordance with the
MMUTCD and must meet the “acceptable” criteria as defined in the ATSSA publication entitled “Quality Guidelines for Temporary Traffic Control Devices and Features” at the time of initial deployment and after each major stage change.
LCRC 4 of 5 5/15/2026
1. During non-working periods, place applicable advance signs and channelizing devices at specific locations, as directed by the Engineer, at no additional cost to the Department.
2. Notify the Engineer 24 hours in advance of when traffic control devices are being delivered to the project site, to allow for initial inspection of devices to take place.
3. Remove from the project site all traffic control devices (including detour signing) no longer needed for a particular operation and equipment for construction within 14 calendar days of reopening the shoulder/lane/roadway.
4. Channelizing Devices.
A. Ensure all devices have sufficient ballast to prevent moving or tipping. If moving or tipping occurs, place additional ballast, as directed by the Engineer, at no additional cost to the Department. No more than two ballasts are allowed on each channelizing device.
B. Do not use caution tape on channelizing devices for traffic control and/or pedestrian traffic control on this project.
5. Portable Changeable Message Signs (PCMS’s). Use PCMS’s to warn traffic of upcoming and changing traffic control during the life of the project. Obtain approval from the Engineer for all sign locations.
A. Install PCMS’s and make them operational a minimum of 7 calendar days prior to the start of work, unless otherwise directed by the Engineer. Messages displayed on the PCMS’s must conform to MDOT’s policy on PCMS’s. Notify the Engineer if displaying a different message than those listed below for the project.
B. Do not leave PCMS’s with a blank screen within the clear zone of any roadway at any time. Remove the PCMS or display flashing dots in each corner of the screen when there is no message to display. Update the PCMS messages at the end of each work period to reflect current traffic lane restrictions.
C. Display the following two messages greater than 6 days prior to work.
EAGER
TO CLOSE
AT GOLF
CLUB
XX-XX-XX
XXXXXXXX
GOLF
CLUB
TO CLOSE
AT
EAGER
XX-XX-XX
LCRC 5 of 5 5/15/2026
D. Display the following two messages during work.
v. Measurement and Payment. Payment will be in accordance with the standard specifications unless otherwise specified. No additional payment will be made for the following activities:
1. Transporting traffic control items from site to site.
2. Providing sufficient vehicles and staff to make changes as-needed on site during work.
3. Providing sufficient vehicles and staff to remove closures from the roadway.
EAGER
CLOSED
AT
GOLF
CLUB
AT EAGER
FOLLOW
DETOUR
GOLF CLUB
FOLLOW
DETOUR
NOT TO SCALE
FILE:
Michigan Department of Transportation
MAY 2021
A DOUBLE LANE SHIFT
ON A 7-LANE UNDIVIDED ROADWAY
1 BOUND AND CLTL CLOSURE WITH DATE:
SHEET:
NO:
100-GEN-KEY.dgn 3(1R+2L)LC-2(L)SHIFT
152-CLT(7)-
MAINTAINING TRAFFIC TYPICAL
FILE:
Michigan Department of Transportation
DECEMBER 2021
TYPICAL NUMBERING KEY
DATE:
100-GEN-KEY.dgn
MAINTAINING TRAFFIC TYPICAL
100-GEN-KEY
NO:
TYPICAL NUMBER KEY
CODES
ZIP = ZIPPER MERGE
TS = TEMPORARY SIGNAL
TR = TRAFFIC REGULATOR
STA = STOPPED TRAFFIC ADVISORY
SPEED = SPEED
SP = SPECIAL
SIGN = SIGN
SHL = SHOULDER CLOSURE
SD = SHORT DURATION
RUM = RUMBLE STRIP
ROLL = ROLLING ROADBLOCK
(R) = RIGHT
PCMS = PORTABLE CHANGEABLE MESSAGE SIGN
PARK = PARKING LANE
NFW = NON-FREEWAY
MID = MIDDLE OF INTERSECTION OR ROAD
OUT = OUTSIDE OF SHOULDER
O = OUTSIDE (LANE CLOSURE)
LO = LANE OPEN
LD = LONG DURATION
LC = LANE CLOSURE
(L) = LEFT
L = LANE
INT = INTERSECTION
IN = INSIDE
GORE = FREEWAY GORE AREA
GEN = GENERAL INFORMATION
FW = FREEWAY
ExR = EXIT RAMP
EnR = ENTRANCE RAMP
EM = EARLY MERGE
CruSha = CRUSH AND SHAPE
CROSS = CROSSOVER
CLT = CENTER LEFT TURN LANE
C = CLOSURE
AW = ADVANCE WARNING
AB = ARROW BOARD
2(L)SHIFT = 2 LANES SHIFTED TO THE LEFT.
3(1R+2L)LC = 3 LANES CLOSED, (1 RIGHT LANE AND 2 LEFT LANES).
CTL(7) = CENTER LEFT TURN LANE, 7 LANES TOTAL.
152 - TYPICAL NUMBER
CODE: 152-CTL(7)-3(1R+2L)LC-2(L)SHIFT
EXAMPLE TYPICAL
5000 - SURVEY
4000 - MAINTENANCE
360 - ROLLING ROADBLOCK
350 - GORE LOCATIONS
340 - MERGE SYSTEMS
320 - CRUSH AND SHAPE
310 - CROSSOVER CLOSURE
300 - ADVANCE WARNINGS
230 - FREEWAY EXIT RAMPS
220 - FREEWAY ENTRANCE RAMPS
210 - FREEWAY LANE SHIFTS
200 - FREEWAY CLOSURES
160 - SIGNAL WORK
150 - CLT 7 LANE SECTIONS
140 - PARKING LANES
130 - CENTER LEFT TURN (CLT) LANES
120 - NON-FREEWAY
110 - TRAFFIC REGULATORS
100 - GENERAL NOTES
Michigan Department of Transportation
MAY 2021
"B", "D" AND "L" TABLES
CHANNELIZING DEVICE SPACING,
SIGN BORDER KEY, AND ROLL-AHEAD SPACING
101-GEN-SPACING-CHARTS.dgn
SPACING-CHARTS
101-GEN-
NO:
DISTANCE BETWEEN TRAFFIC SIGNS, "D"
POSTED SPEED LIMIT, MPH (PRIOR TO WORK AREA)
D (FEET)
DISTANCES
"D"
B (FEET)
GUIDELINES FOR LENGTH OF LONGITUDINAL BUFFER SPACE, "B"
LENGTHS
"B"
30 35 40 45 50 55 60 65 70
25 30 35 40 45 50 55 60 65 70
250 300 350 400 450 500 550 600 650 700
SPEED, MPH (PRIOR TO WORK AREA)
132 181 230 279 329 411 476 542 625
OPERATING SPEED.
* POSTED SPEED, OFF-PEAK 85TH PERCENTILE SPEED PRIOR TO WORK STARTING, OR THE ANTICIPATED
POSTED SPEED LIMIT, MPH (PRIOR TO WORK AREA)
25 30 35 40 45 50 55 60 65 70
1 11
2 100 110 120 130 140
3 135 150 165 180 195 210
4 107 180 200 220 240 260 280
5 103 134 225 250 300 325 350
6 123 160 270 300 330 360 390 420
7 143 187 315 350 385 420 455 490
8 164 214 360 400 440 480 520 560
(FEET)
OFFSET
MINIMUM MERGING TAPER LENGTH, "L" (FEET)
9 184 240 405 450 495 540 585 630
10 205 267 450 500 550 600 650 700
11 225 294 495 550 605 660 715 770
12 180 245 320 540 600 660 720 780 840
13 266 347 585 650 715 780 845 910
14 286 374 630 700 770 840 910 980
15 307 400 675 750 825 900 975 1050
15 21 27 45 50 55 60 65 70 75
90544130
32 45 62 80
42 60 82
53 75 275
63 90
33 83
Michigan Department of Transportation
MAY 2021
"B", "D" AND "L" TABLES
CHANNELIZING DEVICE SPACING
SIGN BORDER KEY AND ROLL-AHEAD SPACING
SPACING-CHARTS
101-GEN-
NO:
SHOWN IN THE ABOVE TABLES ARE AS FOLLOWS:
MERGING TAPER IN DERIVING THE "L" VALUES
THE FORMULAS FOR THE MINIMUM LENGTH OF A
60 THE WORK AREA IS 40 MPH OR LESS
WHERE POSTED SPEED PRIOR TO "L" = W X S
THE WORK AREA IS 45 MPH OR GREATER
WHERE POSTED SPEED PRIOR TO "L" = W X S
W = WIDTH OF OFFSET
S = POSTED SPEED LIMIT IN MPH PRIOR TO WORK AREA
L = MINIMUM LENGTH OF MERGING TAPER
UPSTREAM TAPERS
DOWNSTREAM TAPERS
TAPER LENGTHTYPES OF TAPERS
100' - MAXIMUM2 TO 1 LANE ROAD TAPER
1/3 L - MINIMUMSHOULDER TAPER
1/2 L - MINIMUMSHIFTING TAPER
L - MINIMUMMERGING TAPER
MAXIMUM SPACING FOR CHANNELIZING DEVICES
SPEED LIMIT
WORK ZONE
TAPERTAPER TANGENT TANGENT
< 45 MPH
> 45 MPH 25 FEET100 FEET50 FEET
1 x SPEED LIMIT 2 x SPEED LIMIT
100' (PER LANE)(USE IS RECOMMENDED)
DRUM AND 42" DEVICE SPACING (FT) NIGHTTIME 42" DEVICE SPACING (FT)
25 FEET 50 FEET
50 FEET
EXITEXIT
IS TO BE PLACED ON THE PROJECT
SOLID OUTLINES INDICATE A SIGN THAT
EXISTS ON SITE, AND NEEDS TO BE COVERED.
DASHED OUTLINES INDICATE A SIGN THAT
SIGN OUTLINE KEY
Michigan Department of Transportation
MAY 2021
"B", "D" AND "L" TABLES
CHANNELIZING DEVICE SPACING
SIGN BORDER KEY AND ROLL AHEAD SPACING
SPACING-CHARTS
101-GEN-
NO:
TO WORK ZONE)
(POSTED SPEED PRIOR
PREVAILING SPEED
25 FT
GUIDELINES FOR ROLL-AHEAD DISTANCES FOR TMA VEHICLES - TEST LEVEL 2
VEHICLE
TMA
WEIGHT OF
40 MPH OR LESS
(STATIONARY)
5.5 TONS
TO WORK ZONE)
(POSTED SPEED PRIOR
PREVAILING SPEED
50-55 MPH
100 FT
150 FT
175 FT
VEHICLE
TMA
WEIGHT OF
* ROLL-AHEAD DISTANCES ARE CALCULATED USING A 4,410 POUND IMPACT VEHICLE WEIGHT.
25 FT
25 FT
50 FT
(STATIONARY)
12 TONS
(MOBILE)
5 TONS
45 MPH
60-75 MPH
45 MPH
50-55 MPH
60-75 MPH
TMA VEHICLE TO WORK AREA)
(DISTANCE FROM FRONT OF
ROLL-AHEAD DISTANCE*
TMA VEHICLE TO WORK AREA)
(DISTANCE FROM FRONT OF
ROLL-AHEAD DISTANCE*
* ROLL-AHEAD DISTANCES ARE CALCULATED USING A 10,000 POUND IMPACT VEHICLE WEIGHT.
GUIDELINES FOR ROLL-AHEAD DISTANCES FOR TMA VEHICLES - TEST LEVEL 3
MAY 2022
TRAFFIC TYPICALS
NOTE SHEET
102-GEN-NOTES.dgn
102-GEN-NOTES
NO:
GENERAL NOTES
BUFFER AREAS.
DO NOT STORE EQUIPMENT, MATERIALS OR PERFORM WORK IN ESTABLISHEDG4:
BY MDOT WILL BE ALLOWED.
APPLICABLE SPECIAL PROVISIONS. ONLY DESIGNS AND MATERIALS APPROVED
STANDARD SPECIFICATIONS FOR CONSTRUCTION, THE STANDARD PLANS AND
MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES, THE CURRENT EDITION OF THE
HARDWARE (MASH) TL-3 AS WELL AS THE CURRENT EDITION OF THE MICHIGAN
REPORT 350 (NCHRP 350) TEST LEVEL 3, OR MANUAL FOR ASSESSING SAFETY
LIGHTING MUST MEET NATIONAL COOPERATIVE HIGHWAY RESEARCH PROGRAM
ALL TEMPORARY SIGNS, TYPE III BARRICADES, THEIR SUPPORT SYSTEMS ANDG3:
ARE ADEQUATELY DELINEATED BY OTHER TRAFFIC CONTROL DEVICES.
WILL BE MADE FOR TRAFFIC PATTERNS FOR WORK LESS THAN THREE DAYS THAT
BE REMOVED BEFORE ANY CHANGE IS MADE IN THE TRAFFIC PATTERN. EXCEPTION
CHANGES IN TRAFFIC PATTERNS OR PROPOSED TEMPORARY TRAFFIC MARKINGS SHALL
ALL EXISTING PAVEMENT MARKINGS WHICH ARE IN CONFLICT WITH EITHER PROPOSED…