Geotech Survey - SOW - B772 and B718.pdf
PDF 147 KB Posted
- Attached to
- Geotechnical Survey Federal contract opportunity
- Solicitation number
- FA446025Q0322
About this file
This Statement of Work (SOW) details a geotechnical survey contract for two dormitory buildings (B772 and B718) at Little Rock Air Force Base in Arkansas. The contractor is required to perform four 20-foot deep bore samples per building to determine soil bearing capacity and shrink/swell characteristics, supporting a planned three-story porch and exterior stairwell renovation. The project requires obtaining digging permits, coordinating with utility companies, and conducting a comprehensive geotechnical analysis to provide recommendations for foundation design.
Key contract specifications include completing the work within 60 days of award, delivering core samples and analysis reports within 30 days after award date (ADC), and coordinating with the project manager Randy Shelden. The Little Rock AFB Chief of Asset Optimization will monitor and approve the contractor's performance, with payment contingent upon completion and acceptance of all work. The contractor must comply with utility location requirements, including calling Arkansas 811 48 hours prior to beginning work and being responsible for preventing damage to existing utilities.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| MFR - Ammendment.pdf | ||
| GeoTech QA.pdf | ||
| COMBOSOL - Geotech Survey - Ammended.pdf | ||
| MFR - GeoTech Amendment.pdf | ||
| COMBOSOL - Geotech Survey.pdf | ||
| COMBOSOL - Geotech Survey.pdf | ||
| Clauses.pdf | ||
| Wage Determination.pdf | ||
| Addendum - 52.212-1, Instructions to Offeror.pdf | ||
| Addendum - 52.212-2, Evaluation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11 July 2025
Statement of Work (SOW) for
Geotechnical Survey at Little Rock AFB, AR, B772 and B718
1.0 SCOPE. The purpose of this Statement of Work is to obtain Geotechnical information at the existing B772 and B718 dorms where we are adding on stair wells and porches around the entire building. The Geotechnical survey shall include four bore samples per building 20 feet deep. The contractor will provide all labor, materials and equipment needed to perform this work.
1.1 Background. The existing dorm buildings B772 and B718 are undergoing full renovation with a three-story wrap around porch and two exterior stair wells. The purpose of the geotechnical survey is to obtain data to determine bearing capacity and shrink/swell characteristics of existing material. The report shall make recommendations regarding foundation design to support the additions.
1.2 Location. The Geotechnical Surveys shall be obtained for B772 and B718 Dorms at LRAFB, AR.
1.3 Digging permits. A digging permit will have to be accomplished at each location prior to performing the soil borings. Contact Sean Calhoun two to three weeks prior to doing soil bores at
501-987-2823.
1.4 Existing Utilities:
The Contractor shall notify the utility company of proposed locations and times of excavations and other utility work to ensure smooth coordination of all operations.
1.The Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, the Contractor shall repair the utility at no additional cost to the Government.
2. The contractor must call “Arkansas 811” 48 hours prior to beginning work. Anyone that will be disturbing the ground is required to contact Arkansas 811. Examples include planting a tree, building a fence, installing a swimming pool, placing a mailbox post, concrete work, driveway work, ditch work, etc. This applies to all homeowners, government agencies, plumbers, farmers working within the ROW, and many more.
2.0 APPLICABLE DOCUMENTS
2.1 Applicable Documents. The purpose of these services is to provide information and geotechnical engineering recommendations relative to:
Demolition considerations;
Site and subgrade preparation;
Foundation design and construction;
Seismic site class (based on IBC 202)
3.0 DESCRIPTION OF WORK. The Contractor shall provide all necessary expertise, labor, transportation, equipment, materials, tools, and incidentals needed to expeditiously accomplish the following tasks.
3.1 Tasks:
Task 1/CLIN 001 Perform geotechnical survey that shall include four bore samples per building, 20 feet deep, IAW Atterburg Limits and Geotechnical survey and structural recommendations.
Task 2/CLIN 002 Provide data obtained, in a report, that determines the bearing capacity and shrink/swell characteristics of existing material. This data report shall make recommendations regarding foundation design to support any and all additions.
4.0 DELIVERABLES & SCHEDULE.
The Contractor shall provide A schedule for tracking work progress and estimated completion date.
4.1 Deliverables:
Tasks Deliverables Delivery Dates
Task 1: Geotech Survey Core Samples and Analysis
Report
30 days ADC
Task 2: Data Report Bearing Capacity and shrink swell characteristics
30 days ADC
4.2 Schedule
a. All work shall be scheduled through the Point of Contact identified in paragraph 10.0.
b. This Contractor recognizes that other Contractors may be working on the right-of-way and working schedules may have to be adjusted accordingly.
4.2 Period of Performance. The contractor shall complete the period of performance 60 days from the award date.
5.0 FINAL INSPECTION AND ACCEPTANCE
The Little Rock AFB Chief, Asset Optimization will monitor and approve the effectiveness of the contractor’s performance on any planning and execution under this Statement of Work.
Payment shall be made upon completion and acceptance of all work.
6.0 POINTS OF CONTACT
Mr. Randy Shelden
Project Manager
19 CES/CEPMD
528 Thomas Avenue
Little Rock Air Force Base, AR 72099-4987
870-365-6003
Mr. Sean Calhoun
19 CES/CEPMD
528 Thomas Avenue
Little Rock Air Force Base, AR 72099-4987
501-987-2823