SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
0040208976
USGS OAG RESTON ACQUISITION BRANCH
205 NATIONAL CENTER
12201 SUNRISE VALLEY DRIVE
RESTON VA 20192
GRB
kmurray@usgs.gov
Kris Murray 608-381-3451
106/12/2015
G15PS00507
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Items 00010 and 00020 as described in the statement of work.
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
14 60 calendar days and complete it within ________________ ________________ calendar days after receiving
52.211-10
07/10/2015
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
USGS OAG RESTON ACQUISITION BRANCH
205 NATIONAL CENTER
12201 SUNRISE VALLEY DRIVE
RESTON VA 20192
GRB
Kris Murray
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 29
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
G15PS00507
Replace roof and siding at S.O. Conte Anadramous
Fish Research Laboratory, Turners Falls, Massachusetts.
Refer to the provision at L.5, Instructions to
Offerors for specific guidance on the submission of quotes.
Site Visit - Attendance is MANDATORY for contractors interested in submitting a quotes.
Refer to provision 52.236-27 at L.3 for site visit date, time, and instructions for confirming attendance.
DUNS ________________________________
Suggested COR: ROWENS
Delivery: 10/02/2015
Delivery Location Code: 0006608990
Conte Anadromous Fish Lab
One Migratory Way P O Box 796
Turners Falls MA 01376-0796 US
FOB: Destination
Period of Performance: 08/03/2015 to 10/02/2015
00010 Provide all labor, equipment, materials, and supervision to replace roof on Fish Passage
Building. Work must be performed in accordance with the statement of work, wage decision, clauses, and all applicable federal, state, and local regulations.
00020 Provide all labor, equipment, materials, and supervision to replace siding on Fish Passage
Building. Work must be performed in accordance with the statement of work, wage decision, clauses, and all applicable federal, state, and local regulations.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
G15PS00507 Page 4 of 29
SECTION A. SOLICITATION/CONTRACT FORM
SECTION B. SUPPLIES OR SERVICES AND PRICES/COSTS
SECTION C. DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1. Green Acquisition C.2. GS0340 Environmentally Preferable Building Products and Materials C.3. GS0343 Energy Efficient Products C.4. GS0346 Construction Waste Management C.5. GS0348 Environmental Requirements – Selected Construction Materials
SECTION D. PACKAGING AND MARKING
SECTION E. INSPECTION AND ACCEPTANCE
E.1. 52.246-12 Inspection of Construction. (AUG 1996) E.2. 52.246-13 Inspection - Dismantling, Demolition, or Removal of Improvements. (AUG 1996)
SECTION F. DELIVERIES OR PERFORMANCE
F.1. Performance Location F.2. 52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984) F.1. 52.242-14 Suspension of Work. (APR 1984) F.2. GS0919 Legal Holidays F.3. Deliverables
SECTION G. CONTRACT ADMINISTRATION DATA
G.1. 1452.201-70 Authorities and Delegations (SEP 2011) G.2. DOI ELECTRONIC INVOICING Electronic Invoicing and Payment Requirements - Internet Payment Platform (IPP) (September 2011) G.3. GS1126 Invoicing and Performance Statement Instructions G.4. Unilateral Deobligation of Unexpended Funds
SECTION H. SPECIAL CONTRACT REQUIREMENTS
H.1. GS1125 Schedule Of Prices (Construction) H.2. GS1338 Notice to the Government of Delays H.3. GS1348 Accident Reporting H.4. GS1354 List of Subcontractors (Construction) H.5. GS1366 Nondiscrimination Notice To U.S. Department of the Interior Contractors, Subcontractors, and Lessors (January 2000) H.6. GS1414 Contractor Personnel Clearance and Identity Credentials H.7. GS1440 Wage Decision Incorporation H.8. GS2116 Distortions in Drawings
SECTION I. CONTRACT CLAUSES
I.1. 52.204-13 System for Award Management Maintenance. (JUL 2013) I.2. 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) I.3. 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations. (DEC 2014) I.4. 52.213-4 Terms and Conditions - Simplified Acquisitions (Other Than Commercial Items). (MAY 2015) I.5. 52.215-8 Order of Precedence—Uniform Contract Format. (OCT 1997) I.6. 52.219-6 Notice of Total Small Business Set-Aside. (NOV 2011) I.7. 52.219-28 Post-Award Small Business Program Rerepresentation. (JUL 2013) I.8. 52.222-6 Construction Wage Rate Requirements (MAY 2014) I.9. 52.222-7 Withholding of Funds. (MAY 2014) I.10. 52.222-8 Payrolls and Basic Records. (MAY 2014) I.11. 52.222-9 Apprentices and Trainees. (JUL 2005) I.12. 52.222-10 Compliance with Copeland Act Requirements. (FEB 1988) I.13. 52.222-11 Subcontracts (Labor Standards). (MAY 2014) I.14. 52.222-12 Contract Termination - Debarment. (MAY 2014) I.15. 52.222-13 Compliance with Davis-Bacon and Related Act Regulations. (MAY 2014) I.16. 52.222-14 Disputes Concerning Labor Standards. (FEB 1988) I.17. 52.222-15 Certification of Eligibility. (MAY 2014) I.18. 52.222-27 Affirmative Action Compliance Requirements for Construction. (APR 2015) I.19. 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts. (SEP 2013) I.20. 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts. (MAY 2008) I.21. 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving. (AUG 2011) I.22. 52.225-9 Buy American - Construction Materials. (MAY 2014) I.23. 52.227-4 Patent Indemnity--Construction Contracts. (DEC 2007) I.24. 52.228-5 Insurance - Work on a Government Installation. (JAN 1997) I.25. 52.228-12 Prospective Subcontractor Requests for Bonds. (MAY 2014) I.26. 52.228-13 Alternative Payment Protections. (July 2000) I.27. 52.228-14 Irrevocable Letter of Credit. (MAY 2014) I.28. 52.232-5 Payments under Fixed-Price Construction Contracts. (MAY 2014) I.29. 52.232-23 Assignment of Claims. (MAY 2014) I.30. 52.232-27 Prompt Payment For Construction Contracts. (MAY 2014) I.31. 52.236-2 Differing Site Conditions. (APR 1984) I.32. 52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984) I.33. 52.236-5 Material and Workmanship. (APR 1984) I.34. 52.236-6 Superintendence by the Contractor. (APR 1984)
G15PS00507 Page 5 of 29
I.35. 52.236-7 Permits and Responsibilities. (NOV 1991) I.36. 52.236-8 Other Contracts. (APR 1984) I.37. 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (APR 1984) I.38. 52.236-10 Operations and Storage Areas. (APR 1984) I.39. 52.236-11 Use and Possession Prior to Completion. (APR 1984) I.40. 52.236-12 Cleaning Up. (APR 1984) I.41. 52.236-13 Accident Prevention. (NOV 1991) I.42. 52.236-14 Availability and Use of Utility Services. (APR 1984) I.43. 52.236-15 Schedules for Construction Contracts. (APR 1984) I.44. 52.236-17 Layout of Work. (APR 1984) I.45. 52.236-21 Specifications and Drawings for Construction. (FEB 1997) I.46. 52.236-26 Preconstruction Conference. (FEB 1995) I.47. 52.243-5 Changes and Changed Conditions. (APR 1984) I.48. 52.246-21 Warranty of Construction. (MAR 1994) I.49. 52.249-4 Termination for Convenience of the Government (Services) (Short Form). (APR 1984) I.50. 52.249-10 Default (Fixed-Price Construction). (APR 1984) - Alternate I (APR 1984) I.51. 1452.228-70 Liability Insurance (JUL 1996)
SECTION J. List of Documents, Exhibits and Other Attachments
SECTION K. REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF BIDDERS
K.1. 52.204-8 Annual Representations and Certifications. (DEC 2014) K.2. 52.225-10 Notice of Buy American Requirement - Construction Materials. (MAY 2014)
SECTION L. INSTRUCTIONS,CONDITIONS, AND NOTICES TO BIDDERS
L.1. 52.204-7 System for Award Management. (JUL 2013) L.2. 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction. (FEB 1999) L.3. 52.236-27 Site Visit (Construction). (FEB 1995) - Alternate I (FEB 1995) L.4. 52.236-28 Preparation of Proposals - Construction. (OCT 1997) L.5. Instructions to Offerors L.6. GS2320 Evaluation Factors
SECTION M. EVALUATION FACTORS FOR AWARD
M.1. GS2335 Evaluation and Award--Negotiated
G15PS00507 Page 6 of 29
SECTION A. SOLICITATION/CONTRACT FORM
See SF1442.
SECTION B. SUPPLIES OR SERVICES AND PRICES/COSTS
Section intentionally left blank
SECTION C. DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
STATEMENT OF WORK – ENVIRONMENTAL REQUIREMENTS
C.1. Green Acquisition
The USGS is committed to promoting the natural environment and protecting the health and well-being of people. In the performance of work under this contract, the Contractor shall exert its best efforts to provide services in a manner that will promote the natural environment and protect health and wellbeing. Green purchasing or environmentally preferable contracting includes the initiatives described below:
Alternative Fuels and Vehicles are described at http://www.afdc.energy.gov/afdc/ Biobased Products are described at http://www.biopreferred.gov/ Energy efficient products are described at http://energystar.gov/products for Energy Star products and at http://www.eere.energy.gov/femp/procurement for FEMP designated products Environmentally Preferable Computers are described at http://www.epeat.net Non-Ozone Depleting Products are described at http://www.epa.gov/Ozone/snap/index.html Recycled Products are described at http://epa.gov/cpg Water efficient products are described at http://epa.gov/watersense/
C.2. GS0340 Environmentally Preferable Building Products and Materials
(a) The contractor shall use environmentally preferable products and materials where economically feasible. Environmentally preferable products have a lesser or reduced effect on human health and the environment when compared to other products and services that serve the same purpose.
(b) Refer to EPA's environmentally preferable products web site, www.epa.gov/opptintr/epp. In general, environmentally preferable products and materials do one or more of the following -
(1) Contain recycled material, are biobased, or have other positive environmental attributes;
(2) Minimize the consumption of resources, energy, or water;
(3) Prevent the creation of solid waste, air pollution, or water pollution;
(4) Promote the use of non-toxic substances and avoid toxic materials or processes.
(c) See FAR 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts, for related bio-based product requirements.
(d) See FAR 52.223-17, Affirmative Procurement of EPA-designated Items in Service and Construction Contracts, for related recycled content requirements.
(e) If this contract includes janitorial services, the contractor specifically must -
(1) use the following recycled content products - towels, tissue products, and plastic trash can liners, and
(2) use biobased and/or environmentally preferable cleaning products.
C.3. GS0343 Energy Efficient Products
(a) When acquiring energy-using products, the contractor shall purchase ENERGY STAR® or other energy-efficient items listed on the Department of Energy’s Federal Energy Management Program (FEMP) Product Energy Efficiency Recommendations product list. This clause applies to any power-consuming equipment to be installed or used in USGS facilities, whether title to the equipment will pass to the Government or be retained by the Contractor.
(b) For products that consume power in a standby mode (as listed on FEMP’s Standby Power Devices product listing), the contractor shall -
(1) Purchase items which meet FEMP’s standby power wattage recommendation or document the reason for not purchasing such items; or
(2) If FEMP has listed a product without a corresponding wattage recommendation, purchase items which use no more than one watt in their standby power consuming mode. When it is impracticable to meet the one watt requirement, purchase items with the lowest standby wattage practicable.
http://www.afdc.energy.gov/afdc/ http://www.biopreferred.gov/ http://energystar.gov/products http://www.eere.energy.gov/femp/procurement http://www.epeat.net/ http://www.epa.gov/Ozone/snap/index.html http://epa.gov/cpg http://epa.gov/watersense/
G15PS00507 Page 7 of 29
(c) The requirements of this clause do not apply if (1) no compliant product’s utility and performance can meet the contractor’s need or contract specifications, (2) compliance would not be life-cycle cost-effective, or (3) compliant solutions are otherwise not available.
(d) Information is available via the Internet about - ENERGY STAR® at http://www.energystar.gov/; and FEMP at http://www.eere.energy.gov/femp/procurement .
C.4. GS0346 Construction Waste Management
(a) Items and material existing in the space or to be removed from the space during the demolition phase are eligible for reuse in the construction phase of the project. The reuse of items and materials is preferable to recycling them; however, items considered for reuse must be in refurbishable condition, and must meet the quality standards set forth by the Government in this solicitation/contract. In the absence of definitive quality standards, the contractor is to ensure that the quality of the item(s) in question will meet or exceed accepted industry or trade standards for first quality commercial grade applications. Before use, the contractor shall submit a reuse plan to the Contracting Officer. The Government will not pay for existing fixtures and other existing improvements accepted in place.
(b) Recycling construction waste means providing all services necessary to furnish construction materials or wastes to organizations which will employ these materials or wastes in the production of new materials. Recycling includes required labor and equipment necessary to separate individual materials from the assemblies of which they form a part.
(c) The Offeror shall maintain a recycling program to dispose of or recycle construction waste in compliance with this clause.
The program must cover the following requirements.
(1) The contractor will provide continuous facilities for the recycling of incidental construction waste during initial construction.
(2) Products may be excluded from the recycling program when the small quantity of material involved, the extraordinarily complex nature of the waste disposal method, or prohibitive expense for recycling would represent a genuine hardship.
(3) Records of construction materials recycled shall be maintained and accessible to the Contracting Officer. Records shall include materials recycled or landfilled, quantity, date, and identification of hazardous wastes.
(d) As a minimum, the contractor will recycle lighting and associated support system, carpet and carpet pad, hardware, drywall, and electrical components during both the demolition and construction phases of the project, subject to economic evaluation and feasibility.
(e) If any waste materials encountered during the demolition or construction phase are found to contain lead, asbestos, PCBs (such as fluorescent lamp ballasts), or other harmful substances, they are to be handled and removed in accordance with State and Federal laws and requirements concerning hazardous waste.
(f) The requirements of paragraphs (b) through (d) of this clause do not apply when no construction recycling and salvage operation is reasonably available in the locality where work is to be performed.
C.5. GS0348 Environmental Requirements – Selected Construction Materials
Asbestos - No asbestos-containing fireproofing or insulation on building structures, acoustical treatment, molded or wet-applied ceiling or wall finishes/decorations, or pipe and boiler insulation (including duct, tank, etc.) is permitted in new materials provided by the contractor.
New installations of wood products used under this contract must not contain wood from endangered wood species, as listed by the Convention on International Trade and Endangered Species (CITES). The list of species can be found at www.certifiedwood.org/Resources/CITES/ CITESContent.html.
Particle board, strawboard and plywood materials shall comply with HUD Standards for VOC emissions (particleboard: 0.2 ppm of formaldehyde, plywood: 0.3 ppm of formaldehyde).
Adhesives and Sealants - All adhesives employed on this project (including, but not limited to, adhesives for carpet, carpet tile, plastic laminate, wall coverings, wood adhesive, or sealants) shall be those with the lowest possible Volatile Organic Compound (VOC) content below 20 g/L. and which meet the requirements of the manufacturer of the products adhered or involved. The contractor shall use adhesives and sealants with no formaldehyde or heavy metals.
Insulation - Thermal, Acoustic, and HVAC - All insulation products shall contain recovered materials as required by EPA's Comprehensive Procurement Guideline and related recycled content recommendations. No insulation installed with this project shall be material manufactured using chlorofluorocarbons (CFCs), nor shall CFCs be used in the installation of the product.
G15PS00507 Page 8 of 29
SECTION D. PACKAGING AND MARKING
Section intentionally left blank
SECTION E. INSPECTION AND ACCEPTANCE
E.1. 52.246-12 Inspection of Construction. (AUG 1996)
E.2. 52.246-13 Inspection - Dismantling, Demolition, or Removal of Improvements. (AUG 1996)
SECTION F. DELIVERIES OR PERFORMANCE
F.1. Performance Location
USGS Conte Anadromous Fish Research Laboratory One Migratory Way Turners Falls, MA 01376-0796
F.2. 52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 14 calendar days after notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 60 calendar days after notice to proceed. The time stated for completion shall include final cleanup of the premises.
(End of clause)
F.1. 52.242-14 Suspension of Work. (APR 1984)
F.2. GS0919 Legal Holidays
The following legal holidays are observed by this Government agency:
New Year's Day January 01 Martin Luther King's Birthday 3rd Monday in January Presidents Day 3rd Monday in February Memorial Day Last Monday in May Independence Day July 04 Labor Day 1st Monday in September Columbus Day 2nd Monday in October Veterans Day November 11 Thanksgiving Day 4th Thursday in November Christmas Day December 25 When a holiday falls on Saturday or Sunday, it is observed on the adjacent Friday or Monday, respectively.
In addition to the holidays listed above, the contractor agrees to observe leave days or closures designated by Federal Statute, Executive Order, or Presidential Proclamation.
(End of clause)
F.3. Deliverables
Deliverable Reference Due Deliver To All supervision, labor, materials and equipment necessary to construct all items described in contract documents.
Contract Documents NTP + 60 days USGS
Payment Protection Section I: 52.228-13 Within 10 days after receipt of contract award
CO
Proof of Liability Insurance
Section I: 1452.228-70 Within 10 days after receipt of contract
CO
G15PS00507 Page 9 of 29 award Schedule of Prices Section H: GS1125 Within 10 days after receipt of contract award
CO
List of Subcontractors Section H: GS1354 Within 10 days after receipt of award
CO
SF-1413 Statement and Acknowledgment (including the subcontractor’s signed and dated acknowledgment that the clauses set forth in paragraph (b) of FAR 52.222-11 have been included in the subcontract)
Section I: 52.222-11
The contractor is required to submit statement and acknowledgement to the Contracting Officer on the Standard Form (SF) 1413 available at http://www.gsa.gov/portal/forms/download/115794
Within 10 days after award of this contract and within 10 days after the award of each subcontract therearefer
CO
Schedule for Construction
Section I: 52.236-15 Within 5 days after work commences
COR and
CO
Weekly Payrolls for contractor and each subcontractor
Section I: 52.222-8
The contractor is required to submit copies of all payrolls. The prime contractor is responsible for the submission of copies of payrolls by all subcontractors. This information may be submitted in any form. The optional form WH- 347 from the Department of Labor may be used and is available at:
http://www.dol.gov/whd/forms/wh347.pdf
Within 7 days after regular payment date of the payroll week covered
CO
Ref: FAR 22.406-6(c) for examination of payrolls and statements.
Further compliance checking may be done IAW
FAR 22.406-7.
Invoices Section G: DOI Electronic Invoicing Section G: GS1126
No more often than monthly
IPP Web Page and copy to
COR
Monthly Contract Performance Statement
Section G: GS1126, paragraph (c) Submit at same time as invoice for progress payment
COR
Certification of Progress Payment (if requesting progress payment)
Section I: 52.232-5 As work proceeds – no more often than monthly
COR
SECTION G. CONTRACT ADMINISTRATION DATA
G.1. 1452.201-70 Authorities and Delegations (SEP 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
http://www.dol.gov/whd/forms/wh347.pdf
G15PS00507 Page 10 of 29
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
(End of clause)
G.2. DOI ELECTRONIC INVOICING Electronic Invoicing and Payment Requirements - Internet Payment Platform (IPP) (September 2011)
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Internet Payment Platform System (IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
None
The Contractor must use the IPP website to register, access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in CCR) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of clause)
G.3. GS1126 Invoicing and Performance Statement Instructions
(a) A copy of each invoice submitted with an IPP payment request must be submitted to:
USGS Conte Anadromous Fish Research Laboratory One Migratory Way Turners Falls, MA 01376-0796
(b) Invoices for progress payments may be submitted no more frequently than monthly.
(c) Invoices for progress payments must be accompanied by a contract Performance Statement, which shall show in detail the estimated percentage of completion and value of completed performance for each separately priced line item or, if
G15PS00507 Page 11 of 29 applicable, each of the significant construction categories contained in the approved Schedule of Prices.
(d) See clause 52.232-5 for certification requirements.
(End of clause)
G.4. Unilateral Deobligation of Unexpended Funds
The contractor shall submit all invoices under the award no later than 90 calendar days after the period of performance has expired, unless a request for extension has been submitted to the Contracting Officer. After 120 days has passed since the expiration of the performance period, the government reserves the right to issue a unilateral modification deobligating any unexpended funds, and to initiate closeout procedures.
(End of clause)
SECTION H. SPECIAL CONTRACT REQUIREMENTS
H.1. GS1125 Schedule Of Prices (Construction)
In accordance with the clause FAR 52.232-5, Payments under Fixed-Price Construction Contracts, the contractor shall, within 10 days after receipt of notice of award, submit to the Contracting Officer for approval, a Schedule of Prices. This schedule shall consist of a detailed breakdown of the contract price, segregated under each of the significant construction categories. It shall state the quantities for each of the various types of work, the unit prices, and extended totals.
Subcontractors who may be involved in more than one category of work must provide the same breakout data for each category. The submission of the required data shall not otherwise affect the contract terms.
H.2. GS1338 Notice to the Government of Delays
In the event the contractor encounters difficulty in meeting performance requirements, or when it anticipates difficulty in complying with the contract delivery schedule or date, or whenever the contractor has knowledge that any actual or potential situation is delaying or threatens to delay the timely performance of this contract, the contractor shall immediately notify the contracting officer and the COR, in writing, giving pertinent details. This data shall be informational only in character.
Notice under this provision shall not be construed as a waiver by the Government of any delivery schedule or date or of any rights or remedies provided by law or under this contract.
H.3. GS1348 Accident Reporting
If an accident occurs on Government-controlled facilities, a report must be provided to the Contracting Officer's Representative and the Contracting Officer within 48 hours. An accident is defined as an event which causes injury, illness, or loss or damage to Government-owned or private property. The contractor will cooperate with any ensuing Government accident investigation.
H.4. GS1354 List of Subcontractors (Construction)
For purposes of monitoring compliance with the insurance and payroll reporting requirements of this contract, the contractor shall furnish a listing of all subcontractors to the Contracting Officer within 10 calendars days after contract award.
H.5. GS1366 Nondiscrimination Notice To U.S. Department of the Interior Contractors, Subcontractors, and Lessors (January 2000)
Based upon law, Executive Order, or internal policy, the Department of the Interior prohibits discrimination in the workplace, including sexual harassment, based on race, color, national origin, sex, religion, disability, age, or sexual orientation. The Department urges its contractors, subcontractors, and lessors to develop and enforce comprehensive anti-discrimination policies for their places of work.
H.6. GS1414 Contractor Personnel Clearance and Identity Credentials
(a) During all operations on Government premises, contractor personnel shall comply with the rules and regulations governing the conduct of personnel and the operation of the facility.
(b) USGS rules regarding physical security and personnel security apply to all personnel in USGS facilities. The rules are contained in the following directives, available at http://www.usgs.gov/usgs-manual/handbook/index.html:
G15PS00507 Page 12 of 29
Physical Security Handbook 440-2-H National Security Position Handbook (440-7-H)
(c) Each contractor (or subcontractor) employee requiring recurring access to USGS facilities will be required to obtain a USGS-issued identification badge. Government-issued identity credentials must be worn upon entry and displayed at all times while on federally controlled property, unless otherwise instructed by the COR. Prior to obtaining the badge, the contractor is required to initiate a background suitability check on each such employee in accordance with USGS National Security Position Handbook. The type of background investigation required is based on the risk/sensitivity level designation, as described in the Statement of Work. This clearance/credential requirement does not apply if the contractor does not have any unsupervised IT system access and will only need building access for less than 6 months or only occasional building access (such as for periodic equipment maintenance). In those cases, building procedures for visitors will be applied.
(d) At least 2 weeks before starting work, the contractor will provide a listing to the COR/technical liaison identifying contractor and subcontractor employees requiring access to USGS facilities or systems for performance of work hereunder.
(e) The contractor employees are required to complete the applicable clearance request forms provided by the COR. The following forms, or their equivalent may be used to initiate the credentialing process: SF 85 or SF 85-P (which includes authorization for credit check), SF 86, OF-306, and/or other forms designated for this purpose by the Office of Personnel Management (OPM), Federal Protective Service, or other federal agency in whose space work will be performed under this contract. The SF 86 must be completed on-line at http://www.opm.gov/e-qip/ and printed out by the employee. Contractor employees must present themselves for fingerprinting, together with the printed SF 86, other completed forms, at least 14 calendar days before starting work under this contract. If fewer than 14 days remain before the scheduled start of contract performance, the contractor employee may be allowed temporary, supervised access but must complete this application process as soon as practicable, normally within a day of his or her first arrival at the facility. An employee's refusal to provide or authorize provision of information may constitute grounds for denial or revocation of credentials. Government personnel may contact the contractor/subcontractor employee being screened or investigated in person, by telephone or in writing, and the contractor agrees to make them available for such contact. If a contractor a employee already holds a credential issued by a federal agency after clearance through OPM, provide documentation supporting this status to the COR.
USGS security officials will determine if the existing clearance can be accepted without further investigation.
(f) Badges/credentials issued upon satisfactory completion of a preliminary National Agency Check (NAC) may be revoked if the subsequent NAC with Inquiries (NACI) investigation produces an unfavorable determination. Individuals who do not pass the background investigation cannot be permitted to hold a building pass, allowed entry into the building for contract work, or permitted access to USGS systems (whether remote or on-site). In such cases, the Contractor will be required to sign (or have their subcontractor sign) a notification form indicating that their employee has been informed of the results of the background check. The Government will be the final authority in determining access privileges. The Government's exercise of its right to grant and revoke the access of particular individual(s) to its facilities, systems, or parts thereof shall not constitute a breach or change to the Contract, regardless of it impact on any individual's ability to perform work under the Contract.
(g) The Government reserves the right to require a re-submission of clearance forms and a new background investigation at any time. Failure to provide the documents within the specified time period will result in removal of the employee until such time that the documents are submitted and clearance granted. Should removal be necessary, salary/wages and other costs associated with the removed employee are not allowable or allocable under this contract. If removal would result in understaffing or non-performance of contract requirements, the Contractor shall provide a qualified and cleared replacement.
Failure to do so will entitle to Government to a downward adjustment in price reflecting the reduced level of performance.
(h) When any of their personnel leaves the company's employ, is reassigned to other work, or otherwise no longer requires access to USGS facilities or USGS computer systems, the contractor shall immediately advise the USGS COR so that those user accounts and credentials can be cancelled. The contractor will ensure that the ID badge and keys (if any) are retrieved and promptly returned to the COR, who will forward them to the issuing USGS security official. The COR must be notified in advance of any potentially unfriendly termination of an employee or subcontractor.
(i) The contractor will report any lost keys or badges to the COR within 24 hours. The COR will relay the information to the responsible building security officials. All badges and keys shall be returned to the COR at the completion of this contract.
(j) The requirements of this clause must be included in any subcontracts in which subcontract workers will need building or unsupervised system access as described in paragraph (b).
G15PS00507 Page 13 of 29
(k) For awards with no designated COR, that function will be performed by the employee designated as "Technical Liaison" (if any), or by the employee named as the "ship to" addressee.
H.7. GS1440 Wage Decision Incorporation
In the performance of this contract the contractor shall comply with the requirements of U.S. Department of Labor wage determination number MA3 dated 05/08/2015. The wage determination is incorporated and made a part of this order.
H.8. GS2116 Distortions in Drawings
Offerors are cautioned that accurate scales may not be obtainable from maps or drawings contained in this solicitation, due to reduction of drawings and/or distortions which occur in the xerographic reproduction process. Offerors should rely on actual dimensions or distances shown and should request clarification or additional measurement data where information on maps or drawings is contradictory, inaccurate or incomplete.
SECTION I. CONTRACT CLAUSES
I.1. 52.204-13 System for Award Management Maintenance. (JUL 2013).
I.2. 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014)
I.3. 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations. (DEC 2014)
I.4. 52.213-4 Terms and Conditions - Simplified Acquisitions (Other Than Commercial Items). (MAY 2015)
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses that are incorporated by reference:
(1) The clauses listed below implement provisions of law or Executive order:
(i) 52.222-3, Convict Labor (Jun 2003) (E.O. 11755).
(ii) 52.222-21, Prohibition of Segregated Facilities (Apr 2015).
(iii) 52.222-26, Equal Opportunity (Apr 2015) (E.O. 11246).
(iv) 52.225-13, Restrictions on Certain Foreign Purchases (Jun 2008) (E.O.s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).
(v) 52.233-3, Protest After Award (Aug 1996) (31 U.S.C. 3553).
(vi) 52.233-4, Applicable Law for Breach of Contract Claim (Oct 2004) (Pub. L. 108-77, 108-78 (19 U.S.C. 3805 note)).
(2) Listed below are additional clauses that apply:
(i) 52.232-1, Payments (Apr 1984).
(ii) 52.232-8, Discounts for Prompt Payment (Feb 2002).
(iii) 52.232-11, Extras (Apr 1984).
(iv) 52.232-25, Prompt Payment (Jul 2013).
(v) 52.232-39, Unenforceability of Unauthorized Obligations (Jun 2013).
(vi) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (Dec 2013)
G15PS00507 Page 14 of 29
(vii) 52.233-1, Disputes (May 2014).
(viii) 52.244-6, Subcontracts for Commercial Items (Apr 2015).
(ix) 52.253-1, Computer Generated Forms (Jan 1991).
(b) The Contractor shall comply with the following FAR clauses, incorporated by reference, unless the circumstances do not apply:
(1) The clauses listed below implement provisions of law or Executive order:
(i) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (Jul 2013) (Pub. L. 109-282) (31 U.S.C. 6101 note) (Applies to contracts valued at $25,000 or more).
(ii) 52.222-19, Child Labor-Cooperation with Authorities and Remedies (Jan 2014) (E.O. 13126) (Applies to contracts for supplies exceeding the micro-purchase threshold.)
(iii) 52.222-20, Contracts for Materials, Supplies, Articles, and Equipment Exceeding $15,000 (May 2014) (41 U.S.C. chapter 65) (Applies to supply contracts over $15,000 in the United States, Puerto Rico, or the U.S. Virgin Islands).
(iv) 52.222-35, Equal Opportunity for Veterans (Jul 2014) (38 U.S.C. 4212) (Applies to contracts of $100,000 or more).
(v) 52.222-36, Equal Employment for Workers with Disabilities (Jul 2014) (29 U.S.C. 793) (Applies to contracts over $15,000, unless the work is to be performed outside the United States by employees recruited outside the United States.) (For purposes of this clause, “United States” includes the 50 States, the District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, and Wake Island.)
(vi) 52.222-37, Employment Reports on Veterans (Jul 2014) (38 U.S.C. 4212) (Applies to contracts of $100,000 or more).
(vii) 52.222-41, Service Contract Labor Standards (May 2014) (41 U.S.C. chapter 67) (Applies to service contracts over $2,500 that are subject to the Service Contract Labor Standards statute and will be performed in the United States, District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, Johnston Island, Wake Island, or the outer Continental Shelf).
(viii)(A) 52.222-50, Combating Trafficking in Persons (Mar 2015) (22 U.S.C. chapter 78 and E.O 13627) (Applies to all solicitations and contracts).
(B) Alternate I (Mar 2015) (Applies if the Contracting Officer has filled in the following information with regard to applicable directives or notices: Document title(s), source for obtaining document(s), and contract performance location outside the United States to which the document applies).
(ix) 52.222-55, Minimum Wages Under Executive Order 13658 (Dec 2014) (Executive Order 13658) (Applies when 52.222-6 or 52.222-41 are in the contract and performance in whole or in part is in the United States the 50 States and the District of Columbia).
(x) 52.223-5, Pollution Prevention and Right-to-Know Information (May 2011) (E.O. 13423) (Applies to services performed on Federal facilities).
(xi) 52.223-15, Energy Efficiency in Energy-Consuming Products (Dec 2007) (42 U.S.C. 8259b) (Unless exempt pursuant to 23.204, applies to contracts when energy-consuming products listed in the ENERGY STAR® Program or Federal Energy Management Program (FEMP)) will be-
(A) Delivered;
(B) Acquired by the Contractor for use in performing services at a Federally-controlled facility;
G15PS00507 Page 15 of 29
(C) Furnished by the Contractor for use by the Government; or
(D) Specified in the design of a building or work, or incorporated during its construction, renovation, or maintenance).
(xii) 52.225-1, Buy American-Supplies (May 2014) (41 U.S.C. chapter 67) (Applies to contracts for supplies, and to contracts for services involving the furnishing of supplies, for use in the United States or its outlying areas, if the value of the supply contract or supply portion of a service contract exceeds the micro-purchase threshold and the acquisition-
(A) Is set aside for small business concerns; or
(B) Cannot be set aside for small business concerns (see 19.502-2), and does not exceed $25,000).
(xiii) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations (May 2014) (42 U.S.C. 1792) (Applies to contracts greater than $25,000 that provide for the provision, the service, or the sale of food in the United States).
(xiv) 52.232-33, Payment by Electronic Funds Transfer-System for Award Management (Jul 2013) (Applies when the payment will be made by electronic funds transfer (EFT) and the payment office uses the System for Award Management (SAM) database as its source of EFT information).
(xv) 52.232-34, Payment by Electronic Funds Transfer-Other than System for Award Management (Jul 2013) (Applies when the payment will be made by EFT and the payment office does not use the SAM database as its source of EFT information).
(xvi) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (Feb 2006) (46 U.S.C. App. 1241) (Applies to supplies transported by ocean vessels (except for the types of subcontracts listed at 47.504(d)).
(2) Listed below are additional clauses that may apply:
(i) 52.209-6, Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Aug 2013) (Applies to contracts over $30,000).
(ii) 52.211-17, Delivery of Excess Quantities (Sept 1989) (Applies to fixed-price supplies).
(iii) 52.247-29, F.o.b. Origin (Feb 2006) (Applies to supplies if delivery is f.o.b. origin).
(iv) 52.247-34, F.o.b. Destination (Nov 1991) (Applies to supplies if delivery is f.o.b. destination).
(c) FAR 52.252-2, Clauses Incorporated by Reference (Feb 1998). This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
https://www.acquisition.gov/far/ http://farsite.hill.af.mil/VFDIARA.HTM
(d) Inspection/Acceptance. The Contractor shall tender for acceptance only those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. The Government must exercise its postacceptance rights-
(1) Within a reasonable period of time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(e) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence https://www.acquisition.gov/far/ http://farsite.hill.af.mil/VFDIARA.HTM
G15PS00507 Page 16 of 29 beyond the reasonable control of the Contractor and without its fault or negligence, such as acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.
(f) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work.