FWC 25.26-18 Addendum #1 QAs FINAL.pdf
PDF 145 KB Posted
- Attached to
- Orange Hammock WMA Road Repairs
- Solicitation number
- ITB-14305
- Issued by
- Leon County, Florida
About this file
This Addendum No. 1 is a Questions and Answers document issued by the Florida Fish and Wildlife Conservation Commission (FWC) for Solicitation No. FWC 25/26-18 concerning Orange Hammock WMA Road Repairs. The addendum clarifies project specifications for three road repair projects involving the supply, delivery, spreading, and grading of shell road base material on McCall Ranch Road in Sarasota County. Project 1 encompasses 1.8 miles of roadway at 14-18 feet wide requiring 4 inches of Bank Run Shell Base; Project 2 spans one mile with a finished width of approximately 10 feet and an average finished depth of 6 inches of shell base material; and Project 3 specifications were not detailed in this addendum. The addendum confirms that sod installation is not required for edge grading and that no performance bonds are required. Regarding turn-around construction, the FWC prohibits turn-arounds on Projects 1 and 3 but permits turn-arounds for Project 2 in FWC-approved locations, limited to one dump truck load of material with minimum spacing of 1,320 feet apart. All sealed bid responses must be received by 2:00 PM Eastern Time on Thursday, December 4, 2025, with a public bid opening scheduled for the same date and time.
The addendum does not address pricing terms, set-asides, incumbent information, funding sources, or other financial requirements, as these matters were addressed in the original solicitation documents. Bidders should reference the primary Invitation to Bid (ITB) document for comprehensive contract terms, including the $220,000.00 project budget, per-ton pricing structure, liquidated damages provisions of $100.00 per calendar day for delays, contract term of one year from purchase order issuance, and completion deadline of June 13, 2026, with final invoices due by June 20, 2026.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FWC 25.26 -18 FINAL.pdf | ||
| FWC 25.26 -18 FINAL.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Fish and Wildlife Conservation Commission
Commissioners
Rodney Barreto
Chairman
Coral Gables
Steven Hudson
Vice Chairman
Fort Lauderdale
Preston Farrior
Tampa
Joshua Kellam
Palm Beach Gardens
Gary Lester
Oxford
Albert Maury
Coral Gables
Sonya Rood
St. Augustine
Office of the
Executive Director
Roger A. Young
Executive Director
Charles “Rett” Boyd
Assistant Executive Director
George Warthen
Chief Conservation Officer
Jessica Crawford
Chief of Staff
850-487-3796
850-921-5786 FAX
Managing fish and wildlife resources for their long-term well-being and the benefit of people.
620 South Meridian Street
Tallahassee, Florida
32399-1600
Voice: 850-488-4676
Hearing/speech-impaired:
800-955-8771 (T)
800-955-8770 (V)
MyFWC.com
DATE: NOVEMBER 24, 2025
ADDENDUM NO.: 1
BID NO.: FWC 25/26-18
BID TITLE: ORANGE HAMMOCK WMA - ROAD REPAIRS
UPDATE: QUESTIONS AND ANSWERS
The enclosed addendum has been issued for consideration in the preparation of your response to the Florida Fish and Wildlife Conservation Commission’s
(FWC) Solicitation No. FWC 25/26-18 ORANGE HAMMOCK WMA ROAD REPAIRS.
All responses to the subject solicitation must be received no later than 2:00
PM (ET) on Thursday, December 4, 2025.
A response received after the exact time specified will not be considered.
Failure to file a protest within the time prescribed in Section 120.57(3), Florida Statutes (F.S.), or failure to post the bond or other security required by law within the time allowed for filing a bond shall constitute a waiver of proceedings under Chapter 120, Florida Statutes. Written notices, formal requests and proceedings must conform with the requirements set forth in
Chapter 28-110, Florida Administrative Code (F.A.C.). Protests must be filed with the Purchasing Office, Fish and Wildlife Conservation Commission, 1875
Orange Avenue East, Tallahassee, Florida 32311-6160 within the time prescribed in Section 120.57(3), F.S. and Chapter 28-110, F.A.C.
Sincerely, Martin Ehlen
FWC Procurement Manager
FWC SOLICITATION ADDENDUM 2
Addendum No. 1 Questions & Answers
QUESTION #1
What is the length and width of project #1 repair area?
ANSWER #1
Project 1 is 1.8 miles long. The width is 14-18 feet wide.
QUESTION #2
What is the length and width of project #2 repair area?
ANSWER #2
The length of project 2 is one mile (See Figure 3.) The finished width will be approximately 10 feet.
QUESTION #3
Is the depth of project #2 also 4 inches of Bank Run Shell Base?
ANSWER #3
The depth of project 2 will be dependent on the variable elevation of Main Grade. We anticipate the average finished depth to be approximately 6”.
QUESTION #4
Project 2 - Current width is only about 8 feet. Will it continue at that width or widened with this project?
ANSWER #4
The finished width will be approximately 10 feet.
FWC SOLICITATION ADDENDUM 3
QUESTION #5
Project 2 - Once material is pulled from the sides to elevate the new road and capped, will the awarded contractor need to account for sodding the edges not being capped with road base from pulling material up? Or just graded and compacted?
ANSWER #5
No sod just graded.
QUESTION #6
Is there a performance bond or any bonds?
ANSWER #6
No bonds are required for this project.
QUESTION #7
Will there be turn arounds?
ANSWER #7
There are no turn arounds.
QUESTION #8
Can we make turn arounds?
ANSWER #8
Turn arounds may not be constructed on projects 1 and 3. Turn arounds may be constructed for project 2 in locations approved by the FWC Contract Manager. Turn arounds for project 2 will consist of no more than one dump truck load of material and be at least 1,320’ apart.
END ADDENDUM