FWC 23.24-99C Addendum 1 QA.pdf
PDF 225 KB Posted
- Attached to
- North Florida Shop Roof Replacement
- Solicitation number
- ITB-08353
- Issued by
- Leon County, Florida
About this file
This document is an addendum to the Florida Fish and Wildlife Conservation Commission's (FWC) Solicitation No. FWC 23/24-99C for the "North Florida Shop Roof Replacement" project. The addendum provides answers to 15 questions related to the project, including clarification on which roofs are to be removed and replaced, the existing roof system, insulation requirements, roof panel specifications, work hours and days, and exclusions from the scope. The project involves replacing the existing metal roof system on the North Florida Shop, which is approximately 190' x 50' in size, in accordance with the specifications and summary of work provided. Bids are due by 3:00 PM (ET) on Tuesday, April 16, 2024.
The addendum indicates that the base bid includes 2" fiberglass insulation and stainless steel screws for the roof. No specific manufacturer or model is required for the roof panels, but they must be approved by the Commission prior to installation. The project is limited to the main part of the shop, motor room, and paint bays, and excludes the awnings and overhangs. No background checks are required, and work can be performed from 7:00 AM to 5:00 PM, Monday through Friday.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FWC 23.34-99C TC's-FINAL.pdf | ||
| FWC 23.24-99C ITB.FINAL.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Fish and Wildlife Conservation Commission
Commissioners Rodney Barreto Chairman Coral Gables
Steven Hudson Vice Chairman Fort Lauderdale
Preston Farrior Tampa
Gary Lester Oxford
Albert Maury Coral Gables
Gary Nicklaus Jupiter
Sonya Rood St. Augustine
Office of the Executive Director Roger A. Young Executive Director
Charles “Rett” Boyd Assistant Executive Director
George Warthen Chief Conservation Officer
Jessica Crawford Chief of Staff
850-487-3796
850-921-5786 FAX
Managing fish and wildlife resources for their long-term well-being and the benefit of people.
620 South Meridian Street Tallahassee, Florida 32399-1600 Voice: 850-488-4676
Hearing/speech-impaired:
800-955-8771 (T) 800-955-8770 (V)
MyFWC.com
DATE: APRIL 5, 2024
ADDENDUM NO.: 1
BID NO.: FWC 23/24-99C
BID TITLE: NORTH FLORIDA SHOP ROOF REPLACEMENT
UPDATE: QUESTIONS AND ANSWERS
The enclosed addendum has been issued for consideration in the preparation of your response to the Florida Fish and Wildlife Conservation Commission’s (FWC) Solicitation No. FWC 23/24-99C, “North Florida Shop Roof Replacement”.
All responses to the subject solicitation must be received no later than 3:00 PM (ET) on Tuesday, April 16, 2024.
A response received after the exact time specified will not be considered.
Failure to file a protest within the time prescribed in Section 120.57(3), Florida Statutes (F.S.), or failure to post the bond or other security required by law within the time allowed for filing a bond shall constitute a waiver of proceedings under Chapter 120, Florida Statutes. Written notices, formal requests and proceedings must conform with the requirements set forth in Chapter 28-110, Florida Administrative Code (F.A.C.). Protests must be filed with the Purchasing Office, Fish and Wildlife Conservation Commission, 1875 Orange Avenue East, Tallahassee, Florida 32311-6160 within the time prescribed in Section 120.57(3), F.S. and Chapter 28-110, F.A.C.
Sincerely, Joshua Stringer, FWC Procurement Manager
FWC SOLICITATION ADDENDUM 2
BEGIN ADDENDUM
QUESTION #1
Please clarify which roofs are to be removed and replaced. There are a total of five (5) roof structures listed as the following: Main Roof, Front Lean Too, Back Lean Too, Right Roof, Left Lean Too.
ANSWER #1
The main part of the shop, motor room and paint bays. No awnings are included in this bid. Please see the area outlined in red below for roof removal and installation (replacement).
QUESTION #2
If the left lean to is to be removed and replaced it is suggested that all new lumber is to be replaced.
Does this need to be in the base bid?
ANSWER #2
The left lean is not included in roof specifications. Please see answer #1 for area outlined in red for roof removal and installation.
FWC SOLICITATION ADDENDUM 3
QUESTION #3
Due to no roof access being allowed during the meeting, can you confirm that the existing roof system is an exposed fastener panel profile?
ANSWER #3
Roof access was not denied by the Commission. The “existing” roof has exposed fasteners.
Please see Summary of Work and Roof Specifications.
QUESTION #4
Is there a basis od design (manufacture & model) ridge vent you want specified in all proposals?
ANSWER #4
Ridge vent should be a direct replacement or approved equivalent.
QUESTION #5
It is very possible for the old insulation to fall apart and not be able to remain as is once old panels are removed. Is new insulation to be installed as part of the base bid? Or does this need to be an add alternate? Please keep in mind insulation can be fallen on equipment, tools, vehicles, ect.
ANSWER #5
2” fiberglass insulation is part of the base bid. Please see Summary of Work and Roof Specification.
QUESTION #6
Please provide a basis of design (manufacture & model) for the new roof panels you are wanting to have installed?
ANSWER #6
There are no specific manufacture & model requirements. However, the Commission would need to approve the roof panels prior to installation.
QUESTION #7
Would the state be interested in a roof over system using roof huggers to prevent insulation damages?
FWC SOLICITATION ADDENDUM 4
ANSWER #7
No.
QUESTION #8
What is the specific 26 GA panel profile?
ANSWER #8
Standing seam panel profile
QUESTION #9
Is there sourcing available for the skylights and vents
ANSWER #9
Vendor is responsible for sourcing the skylights and vents.
QUESTION #10
Stainless steel screws are mentioned as part of the skylights. Are stainless steel screws a requirement for the entire roof
ANSWER #10
Stainless steel screws are required for the roof.
QUESTION #11
Are we replacing any of the overhangs (front, back or sides)?
ANSWER #11
No.
QUESTION #12
Please confirm it is going to be a colored metal and not just straight silver galvanized.
ANSWER #12
Galvalume color will be light gray, which is the color of the awning located on the north side of the building, to be approved by the onsite manager prior to installation.
FWC SOLICITATION ADDENDUM 5
QUESTION #13
Are the north, south and west awnings excluded from the scope?
ANSWER #13
Yes.
QUESTION #14
Are background checks required for this project? If Yes, is there a charge for them
ANSWER #14
No, background checks will not be required for this project.
QUESTION #15
What work hours and days will be allowed for this project
ANSWER #15
Work hours are 7:00AM-5:00 PM Monday-Friday.
END ADDENDUM
| Question #1 |
| Answer #1 |
| Question #2 |
| Answer #2 |
| Question #3 |
| Answer #3 |
| Question #4 |
| Answer #4 |
| Question #5 |
| Answer #5 |
| Question #6 |
| Answer #6 |
| Question #7 |
| Answer #7 |
| Question #8 |
| Answer #8 |
| Question #9 |
| Answer #9 |
| Question #10 |
| Answer #10 |
| Question #11 |
| Answer #11 |
| Question #12 |
| Answer #12 |
| Question #13 |
| Answer #13 |
| Question #14 |
| Answer #14 |
| Question #15 |
| Answer #15 |
File details come from the government source that posted it. Updated .