Ft Meade WTN Crane PWS 2024 (002).docx

DOCX document 712 KB Posted

Attached to
Crane & operator at Ft Meade, MD
Solicitation number
W25G1V413600QX
Issued by

About this file

This document is a Performance Work Statement (PWS) for a contract to provide a crane and operator to support the de-installation and removal of an AN/FSC-78 Satellite Antenna at Fort Meade Army Base, Maryland.

The contractor shall provide a 300-ton crane for 10 non-consecutive days, a 110-ton crane for 15 non-consecutive days, and a 60-ton crane for 4 non-consecutive days between September 3 and October 25, 2024. The largest lift is a 53,000-pound parabolic reflector 85 feet in the air. The contractor must also provide logistical support, a lift plan, and a certified crane operator for the duration of the project. All work will be performed at the SATCOM facility on Fort Meade. The government will award a firm-fixed-price service contract under NAICS code 532310.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT (PWS)

Performance Work Statement For Crane Services for the De-Installation of Legacy Terminal (WTN) at Fort Meade Army Base, MD 03 Sept 2024

General Information

1. Introduction: This is a non-personnel services contract to provide a crane with operator. The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.

1.1 Background: The contractor shall provide a crane and operator described herein this Performance Work Statement (PWS). In addition, the contractor shall also provide logistical support for that crane during the entire duration of this project. Tobyhanna Army Depot (TYAD) has been task with the de-installation and removal of an AN/FSC-78 Satellite Antenna located on Fort Meade Army Base, MD. All work will be performed at and all deliveries will be made to:

SATCOM

ATTN: WTN Removal 8901 Love Road Fort Meade, MD 20755

1.2 Responsibilities: The Contractor shall assume total responsibility for all requirements stated herein on the commencement date of the performance period. The Contractor shall perform as specified in this Contract and under the direction of the Contracting Officer (KO). See also Paragraph 1.1 Introduction.

1.2.1 Work Responsibility: The Contractor shall perform all work and assume responsibility for planning, programming, administering, managing, and executing all functions necessary to provide the services specified in this PWS. The Contractor shall conduct work in accordance with this PWS and all applicable United States (U.S.), and local laws, regulations, standards, provisions, and directives to include applicable publications in Section C-6. The Contractor shall ensure that all work meets the level of service, performance standards, or tolerances specified in the PWS or in applicable referenced documents. Some services under this Contract may be performed at designated facilities, or portions of installations, by in-house Government personnel or by other contractors.

1.2.2 Administrative Responsibility: The Contractor shall perform all related administrative actions required to provide services or perform work such as material requisitioning, quality control (QC), financial control, meetings, and correspondence. The Contractor shall also maintain accurate and complete records, files, and libraries of documents to include all U.S. and local regulations, standards, provisions, codes, laws, technical manuals, and manufacturers’ instructions and recommendations that are necessary and related to the functions being performed. The Contractor shall compile historical data, prepare required reports, and submit information as specified by the Deliverable List presented in this PWS.

1.3 Objective: De-install and remove an AN/FSC-78 Satellite Antenna for Army Signal Activity - Meade. The contractor shall provide crane support for the mission.

1.4 Functional Areas: Not Applicable.

1.5 Period of Performance:

The period of performance for the 300T crane will be 10 non-consecutive days between:

9 Sept 2024 – 20 Sept 2024 The period of performance for the 110T crane will be 15 non-consecutive days between:

30 Sept 2024 – 18 Oct 2024

The period of performance for the 60T crane will be 4 non-consecutive days between:

03 Sept 2024 – 25 Oct 2024

The period of performance for the 60T or equivalent to Offload/Load 20 foot shipping containers. The crane will be needed for offload on or about 2 Sept 2024 and again on or about the week ending 25 Oct 2024. A minimum 48 hour notice will be given to the crane contractor once delivery and pick up dates are provided from transportation.

1.6 Management and Administration:

1.6.1 Phase in/Phase Out Period: Not Applicable

1.6.2 Contractor Management: The Contractor shall perform continual management of the functional areas contained in this PWS and shall provide a Project Manager readily available during normal duty hours. The Project Manager shall conduct overall management coordination and shall be the central point of contact (POC) with the Government for performance of all work under the PWS. At the Post Award conference, the Contractor shall submit to the TYAD site lead, in writing, the name, title, office, home and mobile telephone number of the Project Manager A Contractor employee shall be designated to act for the Project Manager when work is being performed outside of duty hours, or during the Project Manager’s absence. Both the Project Manager and the Contractor employee filling in for the Project Manager, shall have full authority to act for the contractor on all Contract matters relating to daily operation of this Contract.

1.6.3 Contractor Responsiveness: The Project Manager or designated alternate shall be available for telephone communication or site attendance, with the site lead, as required by the site lead, 24 hours a day, 7 days a week during the contract period of performance. The Project Manager and any individuals designated to act in that capacity shall have full authority to contractually bind the Contractor for prompt action on matters pertaining to execution of the PWS.

1.6.4 Meetings, Conferences, and Briefings: The Contractor shall attend, participate in, and furnish input to scheduled and unscheduled meetings, conferences, and briefings that relate to the functions and services herein as required by the Government to provide effective communication and impart necessary information. The Project Manager or designated representative shall attend meetings as requested by the Government. Meeting attendees shall at times include Contractor managerial, supervisory, and other personnel knowledgeable of the subject matter. Meetings may start or end outside of regular duty hours.

1.6.5 Hours of Operation: The contractor is responsible for conducting business, between the hours of 0700-1700 Monday thru Friday including Federal holidays, but not when the Government facility is closed due to local or national emergencies, or similar Government directed facility closings. For other than firm fixed price contracts, the contractor will not be reimbursed when the government facility is closed for the above reasons. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.

1.6.6 Recognized Holidays: The contractor shall work any of the holidays if it is determined by the TYAD site lead.

New Year’s DayLabor Day
Martin Luther King Jr.’s BirthdayColumbus Day
President’s DayVeteran’s Day
Memorial DayThanksgiving Day
Independence DayChristmas Day

1.6.7 Training Holidays: U.S. Army Signal Command has historically granted military personnel Training Holidays as compensation for time that they spent in field training. These are typically combined with regular holiday leave schedules (for example, Christmas half days or day on day off schedules). Training Holidays may affect access to military operated facilities. If scheduled work or access to facilities is required, coordination with occupants will be necessary or the work in affected facilities shall be rescheduled after the training holiday. However, announced training holidays or exodus of military personnel may provide the Contractor with an opportunity for unrestricted access to facilities and areas. The Contractor shall take full advantage of such opportunities by planning maintenance or actions that are better accomplished when such areas are vacant.

1.6.8 Quality Control: Not Applicable:

1.6.9 Quality Assurance: Inspection and acceptance with be IAW with FAR Clause 52.212-4(a).

1.6.10 Place of Performance: SATCOM, WTN Removal, 8901 Love Road, Fort Meade, MD 20755

1.6.11 Type of Contract: The government will award a firm fixed priced service contract.

1.6.12 Security Requirements: Contractor personnel performing work under this contract are not required to possess a security clearance. However, contractor personnel entering onto Fort Meade and the Fort Meade SATCOM facility will be required to provide to the contract Point of Contact (POC) the following information not less than 2 days in advance of their arrival at Fort Meade. The information being, (1) Last Name, (2) First Name, (3) Middle Initial, (4) Name Suffix if any, (5) Social Security Number, (6) Date of Birth including year, (7) Citizenship, and (8) Place of Birth City and State. This information will be provided to Security Personnel at Fort Meade, MD and the security personnel at the SATCOM facility on Fort Meade who may use it to conduct a criminal background check. The contract POC will not maintain copies of this information after the information has been provided to Security Personnel at Fort Meade and the SATCOM facility on Fort Meade.

1.6.12a AT Level 1 Training: All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 60 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: https://jkodirect.jten.mil/ for CAC holders. Non-CAC-holders may go to: http://jko.jten.mil/courses/atl1/launch.html.

1.6.13 Physical Security: The contractor shall be responsible for safeguarding all government equipment, information and property provided for contractor use. At the close of each work period, government facilities, equipment, and materials shall be secured.

1.6.14 Key Control: Not Applicable:

1.6.15 Special Qualifications: Contractor is to provide certified/qualified crane operator for the duration of the crane tasks.

1.6.16 Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5. The contracting officer, Contracting Officers Representative (COR), and other Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings the contracting officer will apprise the contractor of how the government views the contractor's performance and the contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government.

1.6.17 Contracting Officer Representative (COR): Inspection and acceptance will be IAW with FAR Clause 52.212-4(a).

1.6.18 Key Personnel: The follow personnel are considered key personnel by the government: Crane Operator. The contractor shall provide a contract manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the contractor when the manager is absent shall be designated in writing to the contracting officer. The contract manager or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The contract manager or alternate shall be available between 8:00 a.m. to 4:30p.m, Monday thru Friday except Federal holidays or when the government facility is closed for administrative reasons.

1.6.19 Identification of Contractor Employees: All contract personnel attending meetings, answering Government telephones, and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. They must also ensure that all documents or reports produced by contractors are suitably marked as contractor products or that contractor participation is appropriately disclosed. Contractor personnel will be required to obtain and wear badges in the performance of this service.

1.6.20 Contractor Travel Not Applicable

1.6.21 Other Direct Costs: Not Applicable

1.6.22 Data Rights: The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the contractor without written permission from the Contracting Officer. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.

1.6.23 Organizational Conflict of Interest: Contractor and subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent Organizational Conflict of Interests (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the Contracting Officer immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the Contracting Officer to avoid or mitigate any such OCI. The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the Contracting Officer and in the event the Contracting Officer unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the Contracting Officer may affect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.

1.6.24 Safety: In performing work under this contract, the contractor shall:

1. Conform to the safety requirements contained in the contract for all activities related to the accomplishment of the work.

2. Develop and provide at the start of the orientation period or the start of the first operational performance period (if there is no orientation period) a safety plan for the protection of government facilities and property and to provide a safe work environment for contractor personnel.

3. Provide protection to government property to prevent damage during the period of time the property is under the control or in possession of the contractor.

4. Include a clause in all subcontracts to require subcontractors to comply with the safety provisions of this contract as applicable.

5. Record and report promptly (within one hour) to the contracting officer or designate government representative (GR), all available facts relating to each instance of damage to government property or injury to either contractor or government personnel.

6. In the event of an accident/mishap, take reasonable and prudent action to establish control of the accident/mishap scene, prevent further damage to persons or property, and preserve evidence until released by the accident/mishap investigative authority through the CO.

7. If the government elects to conduct an investigation of the accident/mishap, the contractor shall cooperate fully and assist government personnel in the conduct of investigation until the investigation is completed.

Include a clause in each applicable subcontract requiring the subcontractor's cooperation and assistance in accident reporting and investigation.

1.6.24.1 Safety Plan and Program: Contractor shall submit a lift plan and safety plan to Tobyhanna Army Depot Personal on site.

1.6.25 Environmental Compliance: Contractor will comply with all Federal and Local environmental compliance requirements.

1.6.25.1 Environmental Compliance Plan and Program: This Environmental Compliance Plan (ECP) has been created specifically for the Tobyhanna Army Depot (TYAD), Modernization of Enterprise Terminal (MET) antenna installation and de-installation procedures. The MET projects executed by TYAD are minimally invasive in that there is typically no disturbance of earth, modification of existing stormwater features, or use of any procedures that have the potential to cause air pollution. Throughout the installation and de-installation processes work crews will utilize hand tools, battery operated tools, corded power tools, gas powered saws and generators, welding equipment, and oxyacetylene torches. All tools are to be utilized in accordance with manufacturer’s specifications. Torch cutting will be performed in accordance with site specific requirements for burn permits, fire watch, etc. Power generating equipment may either be diesel or gasoline fueled. When powered equipment of this nature is utilized, no more than 5 gallons of fuel will be stored onsite (separate from the equipment’s onboard tank) in order to minimize spill potential. In the event of a spill, the site specific POC will be notified immediately in addition to any onsite emergency personnel. The appropriate names and methods of contact (phone numbers/email addresses) will be determined for each site prior to deployment and will be posted in the job trailer onsite.

De-Installation Procedures:

· Disconnect power and signal cabling from de-energized source at control building interface using hand tools

· Disconnect all antenna internal wiring and signal cable and remove from structure using hand tools

· Disconnect all electronics hardware and cabinetry from antenna hub/pedestal using hand tools

· Remove quadra pod, feed horn and reflector using crane, hand tools and battery/air operated tools

· Remove E Room, Counterweights, Ring Girder, Decks, Stairs and Yoke using crane, hand tools and battery/air operated tools

· Remove king post and cone tower using crane, hand tools and battery/air operated tools

· Remove concrete panels when cut using crane

Typical construction chemicals such as WD-40, Loctite, Anti-seize, etc. are used in limited quantities (1 gallon or less) for projects of this nature. When limited quantities of these typical construction items are present, special environmental regulations are not required. Site surveys are performed prior to installation/de-installation in which environmentally sensitive areas such as storm water inlets, drainage swales, etc. are located. In the event these items are located in close proximity to our work areas specialized precautions will be utilized to prevent any jobsite runoff from entering these elements. TYAD may perform (in concert with site specific authority having jurisdiction) diking, damming, and filtering accordingly to maintain appropriate level of protection as deemed necessary on a site specific basis.

PART 2

DEFINITIONS & ACRONYMS

2. Definitions And Acronyms:

2.1 Definitions:

Contractor - A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.

Contracting Officer - A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.

Defective Service - A service output that does not meet the standard of performance associated with the Performance Work Statement.

Deliverable - Anything that can be physically delivered, but may include non-manufactured things such as meeting minutes or reports.

Key Personnel - Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

Physical Security - Actions that prevent the loss or damage of Government property.

Quality Assurance - The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

Quality Assurance Surveillance Plan (QASP) - An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

Quality Control - All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

Subcontractor - One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

Work Day - The number of hours per day the Contractor provides services in accordance with the contract.

Work Week - Monday through Friday, unless specified otherwise.

2.2 Acronyms:

ACORAlternate Contracting Officer's Representative
AFARSArmy Federal Acquisition Regulation Supplement
ARArmy Regulation
CCEContracting Center of Excellence
CFRCode of Federal Regulations
CONUSContinental United States (excludes Alaska and Hawaii)
CORContracting Officer Representative
COTRContracting Officer's Technical Representative
COTSCommercial-Off-the-Shelf
DADepartment of the Army
DD250Department of Defense Form 250 (Receiving Report)
DD254Department of Defense Contract Security Requirement List
DFARSDefense Federal Acquisition Regulation Supplement
DMDCDefense Manpower Data Center
DODDepartment of Defense
FARFederal Acquisition Regulation
HIPAAHealth Insurance Portability and Accountability Act of 1996
KOContracting Officer
OCIOrganizational Conflict of Interest
OCONUSOutside Continental United States (includes Alaska and Hawaii)
ODCOther Direct Costs
PIPOPhase In/Phase Out
POCPoint of Contact
PRSPerformance Requirements Summary
PWSPerformance Work Statement
QAQuality Assurance
QAPQuality Assurance Program
QASPQuality Assurance Surveillance Plan
QCQuality Control
QCPQuality Control Program
TETechnical Exhibit

PART 3

GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES

3. Government Furnished Items and Services - The Government will not provide any equipment to the contractor for this contract.

3.1 Services: Not Applicable:

3.2 Facilities: Not Applicable:

3.3 Utilities: Not Applicable

3.4 Equipment: Not Applicable:

3.5 Materials: Not Applicable:

PART 4

CONTRACTOR FURNISHED ITEMS AND SERVICES

4. Contractor Furnished Items And Responsibilities:

4.1 General: The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this contract that are not listed under Part 5 of this PWS.

4.2 Secret Facility Clearance: Not Applicable:

4.3 Materials: Not Applicable:

4.4 Equipment: The Contractor shall provide a 300T crane, 110T crane and a 60T crane for the mission with licensed operators.

PART 5

SPECIFIC TASKS

5.1 Basic Services: The contractor shall provide services for:

1. The contractor will provide the recommended crane which is the Demag AC250, the Liebherr LTM1250-6.1 or equivalent capacity with 2 hoist gears. The largest pick is the 60ft diameter parabolic reflector weighing 53,000 lbs., 85 feet in the air and a radius of approximately 58ft. The heaviest pick is 56,000 lbs. ring girder 60ft in the air. Two hoist gears and 18 foot jib will be needed to flip the Ring Girder. This crane will be needed for 10 working days. Follow-on work will require a 110T crane with a minimum of 100ft boom to further disassemble large components, concrete base sections and to load concrete panels onto flatbed trucks. This crane will be needed for 15 working days. The 300T crane will be required at the project site when needed by the TYAD Lead approximately on day 7 (09 Sep 2024) through approximately day 16 (20 Sept 2024). The biggest object that this crane will have to lift is of weight 53,000 pounds, reference Technical Exhibit 1, Antenna Parabolic. The 75T crane will be required at the project site when needed by the TYAD Lead on approximately 30 Sept 2024 through approximately 18 Oct 2024. A 60T crane or equivalent will be needed to Offload/Load 20 foot shipping containers. The crane will be needed for offload on or about 3 Sept 2024 and again on or about the week ending 25 Oct 2024. A minimum 48 hour notice will be given to the crane contractor once delivery and pick up dates are provided from transportation.

2. Contractor will provide lift plans to the TYAD Team Lead

3. Contractor shall provide certified/licensed crane operator for the duration of the tasks.

5.2 Recurring Services: Not Applicable.

5.3 On-Demand Services: The contractor shall provide services for fuel service for cranes.

5.4 Functional Areas: Not Applicable.

5.5 Task Heading: Not Applicable.

5.6 Enterprise-Wide Contractor Manpower Reporting Application (eCMRA): The contractor shall ensure ALL contractor labor hours (including subcontractor labor hours) required for the performance of services provided under this contract are reported via a secure data collection site.

The contractor (and all subcontractors providing direct labor under this contract) shall report complete and accurate data for the labor executed during the period of performance during each Government fiscal year (FY), which runs from October 1 to September 30. The Contractor shall input the data into the appropriate eCMRA reporting tool, which can be accessed via a secure web site at http://www.ecmra.mil/. There are four separate eCMRA tools: Army, Air Force, Navy and All Other Defense Components. The appropriate eCMRA reporting tool to use is determined by the requiring activity being supported (e.g., if DISA awards a contract for an Air Force requiring activity, the contractor shall load the required reporting data in the “Department of Air Force CMRA” tool). While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. The contractor shall completely fill in all required data fields. The contractor shall enter initial data into the appropriate eCMRA tool to establish the basic contract record no later than 15 working days after receipt of contract award or contract modification incorporating this clause. The contractor shall notify the COR when the basic contract record has been established in the appropriate eCMRA tool.

eCMRA User Manuals and Frequently Asked Questions (FAQs) are available at http://www.ecmra.mil/ Contractors may direct technical questions to the eCMRA help desk at dodcmra@pentagon.af.mil

PART 6

APPLICABLE PUBLICATIONS

6. Applicable Publications (Current Editions): Not Applicable.

6.1 Contractor Adherence: The contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures.

PART 7

ATTACHMENT/TECHNICAL EXHIBIT LISTING

7. Attachment/Technical Exhibit List:

7.1 Technical Exhibit 1- Physical Characteristics of items to be lifted

7.2 Technical Exhibit 2- Deliverable Schedule

7.3 Estimated Workload Data

7.1 Attachment 1/Technical Exhibit 1 – Physical characteristics of items to be lifted

TECHNICAL EXHIBIT 1

Lift
Item name
weight/ lbs
Notes
1
Reflector
53,000
58ft dish, Item is at approximately 80ft in the air
2
Ring Girder
56,000
Approximately 60ft in the air
3
Yoke
45,000
Approximately 40ft in the air
4
King Post
27,000
Approximately 30ft in the air
6
Cone Tower
33,000
Approximately 21ft in the air
7
Pedestal Base (concrete)
22,000
Per section to be lifted

.2 Attachment 2/Technical Exhibit 2 – Deliverables Schedule

TECHNICAL EXHIBIT 2

DELIVERABLES SCHEDULE

Deliverable
Frequency
# of Copies
Medium/Format
Submit To
Lift Plan
Once

PDF file

Tobyhanna Army Depot site lead

7.3 Attachment 3/Technical Exhibit 3 –

TECHNICAL EXHIBIT 3

ESTIMATED WORKLOAD DATA

ITEM

NAME

ESTIMATED QUANTITY

1
Crane Operator
1
240 hrs

image1.jpeg image2.jpeg image3.jpeg image4.jpeg image5.jpeg