About this file

This document contains a First Article Requirements form and related federal contract opportunity solicitation. The First Article Requirements form outlines testing and approval requirements for an initial production sample of a Phase Noise Measurement Module with part number 94101130-01. Testing must be completed within 120 calendar days and is required to meet specific technical performance standards. The related solicitation seeks proposals for sustaining engineering services to identify a replacement Phase Noise Measurement Module for use in the Benchtop Reconfigurable Automatic Tester system. Services include technical analysis, alternative solutions analysis, integration, and first article and qualification testing. The fixed-price contract would have a 14-month period of performance. Proposals are due from Advanced Testing Technologies, Inc. as the intended sole-source awardee but other sources may submit capability statements for consideration.

View the file

Other files for this federal contract opportunity

Other files attached to Sustaining Engineering Services for Benchtop Reconfigurable Automatic Tester (BRAT) System, newest first.
File Type Posted
FA853320R0013.pdf PDF
Packaging Requirements.pdf PDF
CDRLs.pdf PDF
Performance Work Statement REV 1.pdf PDF
Transportation Requirements.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FIRST ARTICLE REQUIREMENTS 1. DATE

06 MAR 2020(AFMCI 64-110, AFMCI 23-102 and FAR Part 9, Sub Part 9.3)(Additional Instructions on Page 3)

2. PR / MIPR NUMBER 3. CAGE / REFERENCE NUMBER

0DRX9 / BRATB512

4. NSN

6625014955469KV

5. FIRST ARTICLE QUANTITY

THE FIRST ARTICLE IS 0 UNIT(S) OF LOT / ITEM 0

AND WILL BE: PART OF PRODUCTION QUANTITY X IN ADDITION TO PRODUCTION QUANTITY

6. ARTICLES

X WILL WILL NOT SERVE AS A MANUFACTURING STANDARD

7. LONG LEAD TIME ITEMS

REQUIRED X NOT REQUIRED

(See FAR 52.209-3 OR -4, alternate II)

8. SPECIAL REQUIREMENT/PRODUCTION FACILITIES (See FAR 52.209-3 OR -4 Alternate I)

REQUIRED X NOT REQUIRED

"The First Article offered must be manufactured at the facilities in which that item is to be produced under the contract, or if the First Article is a component not manufactured by the contractor, such component must be manufactured at the facilities in which the component is to be produced for the contract. A certification to this effect must accompany each First Article which is offered."

9. TEST / INSPECTION REQUIREMENTS

A. X CONTRACTOR TESTING

GOVERNMENT TESTING

Performance or other characteristics which the First Articles must meet are

In paragraph 4.3.2 of Performance Work Statement (including sub paragraphs) 4.3.2.1, 4.3.2.2, 4.3.2.3, 4.3.2.4, 4.3.2.5.

This First Article requirement is for the phase noise measurement module OEM P/n 94101130-01. A module which is part of 6625-01-495-5469KV.

B. The detailed technical requirements for First Article approval tests are contained in

In paragraph 4.3.2 of Performance Work Statement (including sub paragraphs) 4.3.2.1, 4.3.2.2, 4.3.2.3, 4.3.2.4, 4.3.2.5.

(Cite Spec and Para number)

C. X TEST PLAN REQUIRED

Number of days for government approval / disapproval 15 days.

D. Contractor's notification to ACO and

AFLCMC/WNAA

(Requesting Activity) of test time and location due 90 days prior to start of testing.

E. X TEST REPORT REQUIRED

(1) Forwarded to

AFLCMC/WNAA

AFLCMC/WNAEA

(2) Government written notice of approval / disapproval due 15 days after receipt of contractor's report.

F. FIRST ARTICLE DELIVERY

(1) Due within 120 calendar days from date contract.

(2) Notify 10 calendar days prior to shipment.

(3) Delivered to government at

ATTN: Dana Cole

235 Byron St, Suite 19A

Robins AFB, GA 31098-1813

(Set Forth Consignee and Address)

(4) Government written notice of approval / disapproval within days after receipt of first article package.

G. Estimated cost of government testing / inspection evaluation.

$0.0000

Page 1 of 2AFMC IMT 260, 20020830, V-3 Version 1Generated by PRPS using Jasper Reports on 06 Mar 2020

FIRST ARTICLE REQUIREMENTS 1. DATE

06 MAR 2020(AFMCI 64-110, AFMCI 23-102 and FAR Part 9, Sub Part 9.3)(Additional Instructions on Page 3)

10. DISPOSITION OF FIRST ARTICLES

Approved First Articles will be forwarded to

(insert quantity) First Articles will be expended in testing. Residual components of disapproved First Articles will be returned to the contractor will be retained by pending disposition instructions from the contractor.

First Articles will be installed on aircraft/equipment to determine proper fit/function. Approved article will remain on the aircraft/equipment and will not be forwarded to USAF Supply, but will be considered part of the contract quantity.

X Disapproved First Articles

X will be returned to the contractor will be retained by pending disposition instructions from the contractor.

On purchase requests designated as direct shipments the following disposition will apply. (NOTE: Always applicable on Foreign Military Sales (FMS)).

a. Approved First Articles will be returned to the contractor for shipment with production item.

b. Disposition of disapproved First Articles will remain the same as marked above.

X Other Disposition:

Asset will become part of BRAT spares pool.

11. CONDITION(S) FOR WAIVER OF FIRST ARTICLE APPROVAL

a. Offerors who have previously furnished production quantities of the same or similar article to the prime contractor for delivery to the Government, DoD, Air Force.

b. Offerors currently in production of the same or similar article for a Government, DoD, Air Force contract and who have received First Article approval under the existing contract.

c. Offerors who have previously furnished production quantities of the same or similar articles to the Government, DoD, Air Force, provided articles thus furnished, have exhibited satisfactory performance in service in the opinion of the Air Force.

d. Provided not more than months have elapsed since completion of the contract.

e. X First Article testing will not be waived.

f. See Remarks in block 12 below.

NOTE TO BUYER: UNDER CONDITIONS A AND C ABOVE, THE COGNIZANT ENGINEERING ACTIVITY WILL DECIDE WHETHER OR NOT THE ITEM HAS EXHIBITED SATISFACTORY PERFORMANCE IN SERVICE AND PREPARE AND RETAIN SUPPORTING DOCUMENTATION TO FULLY JUSTIFY THIS DECISION. THE BUYER MUST SOLICIT DUAL PRICES (That is, both with and without requirement for first article approval) AND MUST FURNISH THE COGNIZANT ENGINEERING ACTIVITY WITH THE FOLLOWING INFORMATION ON THE PREVIOUSLY SUPPLIED ARTICLE:

A. PROCURING OFFICE B. CONTRACT NUMBER C. DATE OF CONTRACT D. SPECIFICATION NUMBER AND REVISION

12. REMARKS

13. COGNIZANT ENG ORGANIZATION RESPONSIBLE FOR APPROVING TEST

(Name, Organization, Phone)

Sommer, Cassandra A

AFLCMC / WN A

478-222-2149

472-2149

14. COGNIZANT ENG ORGANIZATION RESPONSIBLE FOR CONDUCTING

TEST (Name, Organization, Phone)

Page 2 of 2AFMC IMT 260, 20020830, V-3 Version 1Generated by PRPS using Jasper Reports on 06 Mar 2020

File details come from the government source that posted it. Updated .