Fire_Station_Location_and_Space_Analysis.pdf
PDF 336 KB Posted
- Attached to
- Fire Station Location and Space Analysis State and local contract opportunity
- Solicitation number
- 2025-RFP-036
- Issued by
- Cook County, Illinois
About this file
This is a Request for Proposal (RFP) document from the Village of Schaumburg, Illinois, soliciting proposals for a Fire Station Location and Space Analysis (Project #2025-RFP-036). The Village seeks an innovative fire service consulting firm to conduct a comprehensive study evaluating current and future fire station facilities and deployment strategies. The project involves performing a Community Risk Analysis/Standards of Cover (SOC) analysis to formulate recommendations for appropriate staffing, apparatus deployment, and potential facility modifications or new construction. Proposals must be submitted electronically through the Village's OpenGov e-Procurement Portal by June 20, 2025, at 1:00 pm, with questions due by June 13, 2025. The selected consultant will be expected to complete the project within six months of contract award, including biweekly meetings, facility inspections, and a final presentation to village stakeholders.
The RFP outlines specific evaluation criteria, with proposals weighted across three key areas: firm's project history (33%), demonstration of project understanding (33%), and fee schedule (34%). While a specific budget is not disclosed, proposers must submit a lump sum price for the complete fire station location study and space analysis. The project scope requires extensive data gathering and analysis, including examining land use, population density, future development, transportation infrastructure, current response times, and existing station conditions. The Village will require comprehensive insurance coverage, including general liability, automobile liability, and workers' compensation, with the Village named as an additional insured. Proposers must also comply with various state regulations, including equal employment opportunity requirements and provisions of the Illinois Human Rights Act.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT REQUEST
2025-RFP-036
FIRE STATION LOCATION AND SPACE ANALYSIS
Village of Schaumburg
Atcher Municipal Center
Schaumburg, IL 60193
RELEASE DATE: May 16, 2025
DEADLINE FOR QUESTIONS: June 13, 2025
RESPONSE DEADLINE: June 20, 2025, 1:00 pm
RESPONSES MUST BE SUBMITTED ELECTRONICALLY TO:
https://procurement.opengov.com/portal/villageofschaumburg
PROJECT REQUEST
Fire Station Location and Space Analysis
I. Legal Notice II. Introduction
III. Instruction to Proposers IV. Scope of Work V. Evaluation Criteria
VI. Insurance Requirements VII. Pricing Sheet(s)
VIII. Terms and Conditions IX. Supplemental Conditions X. Vendor Questionnaire
Project Request #2025-RFP-036 Title: Fire Station Location and Space Analysis
1. Legal Notice
1.1. Village of Schaumburg - Request for Proposal
The Village of Schaumburg, IL will accept electronic proposals via the Village's e-Procurement Portal, OpenGov (https://procurement.opengov.com/portal/villageofschaumburg) for 2025-RFP-036, Fire
Station Location and Space Analysis.
Specifications and all Contract Documents are available via the Village’s e-Procurement Portal, OpenGov. Prices quoted must be valid for a minimum of 90 days from the date of the bid opening.
Proposals will be received until 1:00 pm on Friday, June 20, 2025. All proposals will be made publicly available after submission deadline.
The Village of Schaumburg reserves the right to reject any and all proposals or to waive any technicalities, discrepancies, or information in the bids. The Village of Schaumburg does not discriminate in admission, access to, treatment, or employment in its programs and activities.
All questions regarding this Legal Notice and the actual proposal specifications shall be submitted in writing through the OpenGov Question/Answer Tab via the Village's e-Procurement portal, on or before, Friday, June 13, 2025 by 12:00 pm. Please include the section title for each question, if applicable, in order to ensure that questions asked are responded to correctly. All questions submitted and answers provided shall be electronically distributed to firms following this solicitation on the Village's e-
Procurement Portal.
Purchasing Division
2. Introduction
2.1. Summary
The Village of Schaumburg, IL is seeking an innovative fire service consulting firm with experience in proposing long-range solutions for fire station facilities. The Village would like to establish a contract through competitive negotiation for consulting services to assist in effectively assessing the current and future needs relating to new or modified fire stations through a Fire Station Location and Space Analysis.
The purpose of this feasibility study is to assess renovation and building addition options. Formal design, permitting, and engineering of any improvements/modifications are not included in this scope of work.
The Village of Schaumburg, IL will accept proposals via the Village's e-Procurement Portal, OpenGov https://procurement.opengov.com/portal/villageofschaumburg for 2025-RFP-036, Fire Station Location and Space Analysis to be received no later than Friday, June 20, 2025, 1:00 pm. Proposals submitted after the specified time will not be accepted.
2.2. Background
Schaumburg is the largest center of economic development in the State of Illinois, outside the City of
Chicago. In addition to the 9.5 million square feet of retail and restaurant space, the village has over 12 million square feet of office space and 13.5 million square feet of industrial space.
With a daytime population of 150,000, thousands of businesses, 30 hotels, over 200 restaurants, highly educated workforce, superb location and high quality of life, Schaumburg is 'The Place for Business’.
The Village of Schaumburg is currently experiencing a great deal of growth in the residential and entertainment industries in two major locations within the corporate limits. Additionally, the relocation of the Police Headquarters is planned to be completed by the end of 2028 calendar year, resulting in the station being located in a different response district. These changes are expected to impact fire department services over the long term, hence the need for a thorough study of resource allocation and station location evaluation.
The Fire Department is a full service agency providing fire suppression, emergency medical services treatment and transport, hazardous materials mitigation, underwater rescue and recovery, high angle, structural collapse and below grade rescue. Additionally, the department is responsible for fire prevention services which include compliance and enforcement, public education, and community risk reduction. The Fire Department provides services to the municipal boundaries of the Village of
Schaumburg from five fire stations. During calendar year 2024, the fire department responded to over
11,000 incidents. The Department's minimum daily staffing is twenty eight (28) full-time personnel which staff four (4) engines, four (4) Advanced Life Support ambulances, two (2) aerial apparatus, one
(1) heavy rescue squad, and one (1) battalion chief. Shift rotations are 24 hours on and 48 hours off.
Additionally, headquarters is home to the fire chief, two deputy chiefs, 8 civilian support staff which includes the fire marshal, EMS coordinator, training analyst, EMA/Accreditation manager, administrative assistants, and fire inspectors. Lastly, three part time employees (two fire inspectors and one public education coordinator) utilize space at headquarters.
2.3. Contact Information
Fabio Puccini
Deputy Chief
1601 N. Roselle Rd
Schaumburg, IL 60195
Email: fpuccini@schaumburg.com
Phone: (847) 923-6749
Department:
Fire Department
Department Head:
James Walters
Fire Chief / Department Director
2.4. Timeline
Release Project Date May 16, 2025
Question Submission Deadline June 13, 2025, 12:00pm
Bid Submission Deadline June 20, 2025, 1:00pm mailto:fpuccini@schaumburg.com tel:(847)923-6749
3. Instruction to Proposers
3.1. Intent
The intent of this Request for Proposal is to enable the Village of Schaumburg's Department of Fire
Department to establish relationships with vendors for Fire Station Location and Space Analysis.
This Request for Proposal is open to all vendors actively engaged in supplying goods/services as specified herein. A detailed description of each item/service request is listed in this solicitation.
3.2. Contract Documents
Any drawings, plans, standard conditions, special conditions, supplemental additional conditions, specifications, proposal notice, proposal sheet, and addendum, if any, as specified herein shall form the
“Contract Documents.” For the purpose of this proposal, the word “Village” shall refer to the Village of
Schaumburg, and the word “Firm” shall refer to any person, company, or entity submitting a proposal.
Any work shown or described in one of the documents shall be construed as if described in all the documents.
3.3. Interpretation of Contract Documents
Each request for interpretation of the Contract Documents shall be made in writing through the
OpenGov Question/Answer Tab via the District's e-Procurement portal, on or before, Friday, June 13, 2025 by 12:00 pm. Interpretations and supplemental instructions will be electronically distributed to firms following this solicitation on the Village’s e-Procurement Portal.
3.4. Electronic Proposal Documents
Firms intending to respond to this opportunity must create a FREE account with OpenGov by signing up at https://procurement.opengov.com/signup. This step is necessary to establish a communication link with the Village. The firm, not the Village, is responsible for obtaining any addenda to the original specification. Addenda and other relevant information will be posted on the Village’s e-Procurement
Portal. Addenda notifications will be emailed to all persons on record as following this Proposal. Failure of any firm to receive any such addenda or interpretation shall not relieve such firm from any obligation under their proposal as submitted. All addenda so issued shall become part of the contract documents.
Paper submissions will not be accepted.
3.5. Withdrawal of Proposal
Proposals may be withdrawn through the Village's e-Procurement Portal, the responding firm may
“unsubmit” their proposal in OpenGov. After withdrawing a previously submitted proposal, the responding firm may submit another proposal at any time up to the deadline for submitting proposals prior to the opening. Firms may withdraw or cancel their proposal, in written form, at any time prior to the advertised proposal opening time.
3.6. Firm Qualifications
No award will be made to any proposal or firm who cannot satisfy to the Village that they have sufficient ability and experience in this class of work, as well as sufficient capital and equipment to do the job and https://procurement.opengov.com/signup complete the work successfully within the time named (i.e. responsible). The Village’s decision or judgment on these matters shall be final, conclusive, and binding. The Village may make such investigations as it deems necessary. The proposal shall furnish to the Village, under oath if so required, all information and data the Village may request for the purpose of investigation.
3.7. Preparation of Proposal
The Proposal submittal shall include all required Documents and any further specified documentation as pertaining to this solicitation. The Village will strictly hold the firm to the terms of the proposal.
4. Scope of Work
4.1. Scope of Service
The consultant shall conduct a Community Risk Analysis/Standards of Cover (SOC) analysis to formulate recommendations for appropriate staffing and deployment of firefighting and emergency medical service resources consistent with state and national best practices. The study will be generally in keeping with recommendations of the Center for Public Safety Excellence and Insurance Service
Organization. The SOC shall also include analysis and recommendations for the future improvement of services to the community. The comprehensive deployment study shall be based on relevant data analysis and benchmarking to National Standards as well as the Department established performance benchmarks. The study shall include analysis of fire incidents, emergency medical incidents, hazardous materials incidents, false and other alarms, incident patterns, unit hour utilization (UHU) workload, station location analysis, and response times.
It is expected that the selected consultant will understand existing deployment strategies and performance measures. The Consultant shall analyze Fire Risk Assessment data and the most recent deployment of fire companies and apparatus to develop a comprehensive assessment of the
Department’s station locations, and deployment models.
4.2. Assessment
A. Gather pertinent data and information. the consultant is responsible for all costs associated with obtaining third-party data, such as GIS. (Village Staff will be able to provide: Schaumburg Village
Boundaries, Schaumburg Fire Protection Boundaries, Current Fire Station Locations, Fire
Hydrant Locations)
B. Collaborate with the Village and SFD staff to gather information and to evaluate current and future needs as it pertains to fire stations and personnel/apparatus deployment
C. Conduct an operations efficiency evaluation and analysis of existing conditions of the buildings to form recommendations for a remodel or construction of a new facility or facilities.
D. Identify recommended future fire station locations and phasing plan for station development/construction based on but not limited to:
1. Land use
2. Population
3. Density
4. Physical or other barriers
5. Future residential and commercial development
6. Transportation infrastructure
7. Apparatus and equipment deployment
8. Proper bay space for future needs
9. Relocation of Police Station planned for late 2028
10. Evaluation of existing stations current physical condition
E. Response Times:
1. Document and evaluate current call processing time, turnout time, travel time and overall response time
2. Evaluate the time currently required to deliver the full effective response force
3. Evaluation of incident and unit response concurrency to determine how multiple calls are affecting performance.
F. Evaluation of current administrative space and future needs
G. Evaluation of formal training space and future needs
H. Work closely with other affected Village Departments, such as Finance, Public Works, and
Transportation.
4.3. Deliverables
A. Assessment report, including:
1. Executive Summary
2. Documentation of process
3. Physical findings
4. Operational findings
5. Explanations of closures and new facilities
6. Description of of community services/benefits.
7. Inclusion of supporting data and rationale for all recommendations
8. Modeled response times
B. Meetings
1. Biweekly meetings
2. All meetings are to take place in person. Virtual meetings may be allowed at the discretion of SFD leadership
3. Project kick-off meeting with SFD staff to review scope of work
4. Facility inspection/evaluation
5. Meeting with village stakeholders and SFD leadership to review preliminary results and to make adjustments before drafting the final report
6. Formal presentation to convey findings and results to SFD leadership and village administrators.
C. Project Completion
1. Proposal of expected project completion shall be included
2. Project shall be completed within six (6) months of awarding of contract.
4.4. Proposer Information
A. An outline of the proposer's background and five references
B. Five (5) similar studies, including contact information, completed in past five years
C. Name of lead consultant/project manager
D. Timeline of project completion
5. Evaluation Criteria
No. Evaluation Criteria Scoring Method Weight (Points)
1. Firm's Project History
Firm's ability to provide similar project work in the past five (5) years.
0-10 Points 33 (33% of Total)
2. Demonstration of Project Understanding
Provide cover letter clearly stating the understanding of the project and full scope.
0-10 Points 33 (33% of Total)
3. Fee Schedule
Lump sum fee as provided in the pricing table
0-10 Points 34 (34% of Total)
6. Insurance Requirements
6.1. Insurance
The proposal will provide certificates of insurance evidencing the following types and limits of insurance.
The certificates of insurance will specifically address each of the requirements noted below. Each insurance company shall be acceptable to the Village. The General Liability coverage shall name the
Village of Schaumburg as additional insured. All insurance noted below is primary and in no event will be considered contributory to any insurance purchased by the Village. All insurance noted below will not be canceled, reduced, or materially changed without providing the Village thirty (30) days advance notice, via certified mail.
The Proposal will provide written Proof of Endorsement, with the General Liability policy number on the endorsement.
A. Comprehensive General Liability including Products Liability/Completed Operations insurance, in an amount not less than $1,000,000/occurrence, $2,000,000/policy limit, including Broad Form
Contractual Liability insurance, in an amount not less than $1,000,000/occurrence, $2,000,000/policy limit, subject to the terms and conditions of the policy. A copy of the policy may be required.
B. Automobile Liability insurance, in an amount not less than $1,000,000 combined single limit.
Said insurance is to be extended to cover hired and non-owned vehicles.
C. Umbrella or Excess Liability coverage, the Contractor shall provide evidence of Umbrella or
Excess Liability coverage of $2,000,000.
D. Workers’ Compensation is to be provided as required by statute, by an insurance company licensed to write worker’s compensation in the State of Illinois. Employer’s Liability, in an amount not less than $500,000 each accident, $500,000 disease – policy limit, and $500,000 disease – each employee.
E. Insurance Rating – All insurance policies required by this contract shall be underwritten by insurance companies with a minimum A. M. Best rating of A:VII.
F. A certificate of insurance is required as evidence of coverage, with the Village of Schaumburg named as an additional insured. The certificate will include an “Additional Insured
Endorsement”. The same full insurance coverage provided to the named insured, whether it is the contractor or a sub-contractor, shall be provided to the Village without any limitations or endorsements that might limit or exclude coverage. If insurance is canceled for any reason whatsoever the Village will be given not less than thirty (30) days prior written notice.
Any and all deductibles or other forms of retention are the responsibility of the Contractor. All deductibles or other forms of retention are subject to the approval of the Village. Contractor will disclose to the Village in writing the amounts of any deductible or self-insured retentions on the insurance required under this contract.
Contractor waives any right of subrogation it may have or later acquire against the Village.
The firm shall not commence work under this contract until they have obtained all insurance required under this section and such insurance has been approved by the Village, nor shall firm allow any subcontractor to commence work on their subcontract until the same insurance has been obtained by the subcontractor. The firm and their subcontractor(s) shall maintain all insurance required under paragraphs A through D of this Section for not less than one (1) year after completion of this contract.
7. Pricing Sheet(s)
NOTICE TO VENDORS: Failure to complete the following Pricing Sheet(s) may be cause for rejection of your submittal. If you are not bidding on an entire group, please provide $0.00 as the cost for such items.
NOTE: Unit prices shall include the cost of delivery (if applicable).
PRICING SHEET
Lump sum price for required services.
Line Item Description Unit of Measure Unit Cost
1 Lump sum price for complete fire station location study and space analysis Lump Sum
8. Terms and Conditions
8.1. Compliance with Laws
The proposer shall at all times observe and conform to all laws, ordinances, and regulations of the
Federal, State, and local governments, which may in any manner affect the preparation of proposals or the performance of the contract.
8.2. Alternate
Any reference in these specifications to manufacturer’s name, trade name, or catalog number (unless otherwise specified) is intended as a standard only. The Village’s written decision of approval or disapproval of a proposed substitution shall be final.
Alternate proposals will be considered only if received at the time stated for receipt of the proposal.
Proposers are cautioned that, if an alternate proposal(s) involves an increase in the proposal Sum, the proposal Deposit, if required, shall be ample or be increased to cover the alternate proposal Sum or the entire proposal may be rejected.
8.3. Freedom of Information Act (FOIA)
The Village is required by 5 ILCS 140 - Freedom of Information Act to comply with freedom of information requests (FOIA) within five (5) business days of a record request. All contractors used by the
Village may be in possession of records covered by this act and therefore will be required to provide the
Village with those records upon request and within the time frame of the Act.
8.4. Confidentiality
As a public agency, the Village is required to adhere to Freedom of Information Act. If a responding firm intends to request confidentiality on any portion of a proposal, the submittal shall also include a redacted copy of the proposal. Limited redactions will be considered. However, entire full redaction of proposal submittals will not be considered for award. If a redacted copy is not provided, the original submittal may be released by the Village as received.
8.5. Proposal Review
The Village reserves the right to reject any or all proposals and/or to waive any irregularities or disregard any informality in the proposal when, in its opinion, the best interest of the Village will be served by such action. Furthermore, the Village reserves the right to award each item to a different proposer, or all items to a single proposer unless otherwise noted on in this solicitation. The Village may determine as follows: 1) an equal or alternative is a satisfactory substitute; 2) an early delivery date is entitled to more consideration than price; 3) an early delivery date is to be disregarded because of the reputation of the proposer for not meeting delivery dates; 4) a Proposer is not a responsible Proposer; and 5) what exceptions or deviations from written specifications will be accepted.
No proposals will be accepted from or contract awarded to any person, firm, or corporation that is in arrears or is in default to the Village upon any debt or contract, or that is a defaulter, as surety or otherwise, upon any obligation to the Village, or had failed to perform faithfully any previous contract with the Village.
8.6. Form of Contract
The form of contract between the Village and the successful Proposer will be a purchase order referencing the proposal specification, the proposal submitted by the successful Proposer, and the resulting purchasing order.
8.7. Proposal Results
Following the proposal opening, bid tabulations will be posted on the Village’s e-Procurement Portal. Bid tabulations posted on-line represent “as read” submittals at time of the proposal opening. They do not represent contract award. Final awards will be posted when approved.
8.8. Delivery
Where applicable, all materials shipped to the Village must be shipped F.O.B. delivered, designated location, Schaumburg, Illinois. If the delivery is made by truck, arrangements must be made in advance by the Proposer, with concurrence by the Village, for receipt of the materials. The materials must be delivered where directed. Truck deliveries will be accepted at the Public Works Facility between 7:00 a.m. and 3:30 p.m. and at all other Village locations 8:00 a.m. and 4:00 p.m., weekdays only.
NOTE: The Public Works Facility does have a raised loading dock. All other Village locations do not have access to a raised loading dock. Deliveries requiring removal from the delivery truck via a forklift provided by the Village must be arranged with the Village twenty-four (24) hours in advance of the expected delivery date.
8.9. Inspections
The Village shall have the right to inspect any materials, components, equipment, supplies, services, or completed work specified herein. Any of said items not complying with these specifications are subject to rejection at the option of the Village. Any items rejected shall be removed from the premises of the
Village and/or replaced at the entire expense of the successful Proposer.
8.10. Payment
Payment shall be made within 30 days of invoice receipt and approval, unless otherwise specified in the agreed upon contract. All invoices must include the PO number associated with the order and shall be submitted to the Village of Schaumburg, Accounts Payable Division, 101 Schaumburg Court, Schaumburg, IL 60193. If prevailing wage is a requirement of the contract, the invoice must include IDOL filing certificate and waivers. Failure to submit all documentation as specified may result in delay of invoice payment.
8.11. Period of Unemployment
30 ILCS 570 - Employment of Illinois Workers on Public Works Act must be adhered to in entirety by the awarded contractor. This act requires the use of Illinois workers on Public Works projects during periods of excess unemployment, which means any month immediately following 2 consecutive calendar months during which the level of unemployment in the State of Illinois has exceeded 5% as measured by the United States Bureau of Labor Statistics in its monthly publication of employment and unemployment figures.
8.12. Toxic Substance
Prior to delivery of any material which is caustic, corrosive, flammable, or dangerous to handle, the supplier will provide written directions as to methods of handling such products, as well as the antidote or neutralizing material required for its first aid. (Materials Safety Data Sheet).
8.13. Guarantees and Warranties
All guarantees and warranties required shall be furnished by the Proposer and shall be delivered to the
Village before final payment on the contract is issued.
8.14. Termination of Contract
The Village reserves the right to terminate in whole or any part of this contract, upon written notice to the Proposer, in the event of default by the Proposer. Default is defined as failure of the Proposer to perform any of the provisions of this contract or failure to make sufficient progress so as to endanger performance of this contract in accordance with its terms. In the event of default and termination, the
Village may procure, upon such terms and in such a manner as the Village may deem appropriate, supplies, or services similar to those terminated.
The Proposer shall be liable for any excess costs for such similar supplies or service unless evidence is submitted to the Village that, in the sole opinion of the Village, clearly proves that failure to perform the contract was due to causes beyond the control and without the fault or negligence of the Proposer .
9. Supplemental Conditions
10. Vendor Questionnaire
10.1. Authorized Person(s)*
Please provide the following information for each person(s) authorized to submit a response on behalf of your organization:
Name
Title
Phone Number
Email Address
*Response required
10.2. Equal Employment Opportunity Clause*
EQUAL EMPLOYMENT OPPORTUNITY CLAUSE required by the Illinois Fair Employment Practices
Commission as a material term of all public contracts.
During the performance of this contract, the contractor agrees as follows:
A. That it will not discriminate against any employee or applicant for employment because of race, color, religion, sex, national origin, or ancestry; and further, that it will examine all job classifications to determine if minority persons or women are underutilized and will take appropriate affirmative action to rectify any such under utilization.
B. That, if it hires additional employees in order to perform this contract, or any portion hereof, it will determine the availability (in accordance with the Commission’s Rules and Regulations for
Public Contracts) of minorities and women in the area(s) from which it may reasonably recruit and it will hire for each job classification for which employees are hired in such a way that minorities and women are not underutilized.
C. That, in all solicitations or advertisements for employees placed by it or on its behalf, it will state that all applicants will be afforded equal opportunity without discrimination because of race, color, religion, sex, national origin, or ancestry.
D. That it will send to each labor organization or representative of workers with which it has or is bound by a collective bargaining or other agreement or understanding, a notice advising such labor organization or representative of the contractor’s obligations under the Illinois Fair
Employment Practices Act and the Commission's Rules and Regulations for Public Contracts. If any such labor organization or representative fails or refuses to cooperate with the contractor in its efforts to comply with such Act and Rules and Regulations the contractor will promptly so notify the Illinois Fair Employment Practices Commission and the contracting agency and will recruit employees from other sources when necessary to fulfill its obligations there under.
E. That it will submit reports as required by the Illinois Fair Employment Practices Commission’s
Rules and Regulations for Public Contracts, furnish all relevant information as may from time to time be requested by the Commission or the contracting agency, and in all respects comply with the Illinois Fair Employment Practices Act and the Commission’s Rules and Regulations for Public
Contracts.
F. That it will permit access to all relevant books, records, accounts, and work sites by personnel of the contracting agency and the Illinois Fair Employment Practices Commission for purposes of investigation to ascertain compliance with the Illinois Fair Employment Practices Act and the
Commission’s Rules and Regulations for Public Contracts.
G. That it will include verbatim or by reference the provisions of paragraphs 1 through 7 of this clause in every performance subcontract as defined in Section 2.10 (b) of the Commission's
Rules and Regulations for Public Contracts so that such provision will be binding upon every such subcontractor; and that it will also include the provisions of paragraphs 1,5, 6, and 7 in every supply subcontract as defined in Section 2.10(a) of the Commission’s Rules and
Regulations for Public Contracts so that such provisions will be binding upon every such subcontractor. In the same manner as with other provisions of this contract, the contractor will be liable for compliance with applicable provisions of this clause by all its subcontractors; and further it will promptly notify the contracting agency and the Illinois Fair Employment Practices
Commission in the event any subcontractor fails or refuses to comply therewith. In addition, no contractor will utilize any subcontractor declared by the Commission to be non-responsible and therefore ineligible for contracts or subcontracts with the State of Illinois or any of its political subdivisions or municipal corporations.
The Village of Schaumburg does not discriminate on the basis of disability status in admission or access to, or treatment or employment in, its programs and activities.
☐ Please confirm
*Response required
10.3. Bid Sheet*
By submitting a response to this solicitation, the authorized person(s), confirms having examined the specifications and all conditions affecting the specified project, offer to furnish all services, labor, and incidentals specified for the price as provided with their response.
The Proposer certifies that they are not barred from bidding on this contract as a result of a conviction for the violation of state laws prohibiting bid rigging or bid rotating, (720ILCS 5/33E-1, et seq.) and is not delinquent in any taxes to the Illinois Department of Revenue. (65ILCS 5/11-42.1-1)
It is understood that the Village reserves the right to reject any and all Proposals and to waive any irregularities and that the prices contained herein will remain valid for a period of not less than sixty (60) days.
The Proposer proposes to complete the following project as more fully described in the specifications for the following: in this solicitation document.
☐ Please confirm
*Response required
10.4. Subcontractor Utilization*
If it is the Contractor’s intention to utilize a subcontractor(s) to fulfill the requirements of this contract, the Village must be advised of the subcontractor’s company name, address, telephone and fax numbers, and a contact person’s name at the time of Proposal submittal.
☐ Please confirm
*Response required
10.5. Subcontractor*
Will you be utilizing a subcontractor?
☐ Yes
☐ No
*Response required
10.6. Subcontractor Information*
Please provide the following information for each subcontractor that will be utilized on this project:
Subcontractor's Company Name
Address
Telephone
Email Address
Contact Person's Name at the time of Proposal Submittal
If no subcontractor will be utilized, please type "N/A".
*Response required
10.7. Indemnification*
The Proposer hereby agrees to protect, defend, indemnify, and save harmless the Village against loss, damage, or expense from any suit, claim, demand, judgment, cause of action, or shortage initiated by any person whatsoever, arising or alleged to have arisen out of work described herein, except that in no instance shall the Proposer be held responsible for any liability, claim, demand, or cause of action attributable solely to the negligence of the Village.
☐ Please confirm
*Response required
10.8. Not Barred by Law*
By submitting a response to this solicitation, the Proposer hereby certifies that the item(s) proposed is/are in accordance with the specifications as noted and that the prices quoted are not subject to change; and that on behalf of the organization, is not barred by law from submitting a Proposal to the
Village for the project contemplated herein because of a conviction for prior violations of either Illinois
Compiled Statutes, 720 ILCS 5/33E-3 (Proposal Rigging) or 720 ILCS 5/33-4 (Proposal Rotating).
☐ Please confirm
10.9. Not Delinquent in Payment*
By submitting a response to this solicitation, the Proposer hereby certifies that the item(s) proposed is/are in accordance with the specifications as noted and that the prices quoted are not subject to change; and that on behalf of the organization, is not delinquent in payment of any taxes to the Illinois
Department of Revenue in accordance with 65 ILCS 5/11-42.1.
☐ Please confirm
*Response required
10.10. Drug-Free Workplace*
By submitting a response to this solicitation, the Proposer hereby certifies that the item(s) proposed is/are in accordance with the specifications as noted and that the prices quoted are not subject to change; and that on behalf of the organization, provides a drug free workplace pursuant 30 ILCS 580/1, et seq.
☐ Please confirm
*Response required
10.11. Substance-Abuse Program*
By submitting a response to this solicitation, the Proposer hereby certifies that the item(s) proposed is/are in accordance with the specifications as noted and that the prices quoted are not subject to change; and that on behalf of the organization, certifies they have a substance-abuse program and provide drug testing in accordance with 820 ILCS 265/1 et. seq., Public Act 095-0635
☐ Please confirm
*Response required
10.12. Illinois Human Rights Act*
By submitting a response to this solicitation, the Proposer hereby certifies that the item(s) proposed is/are in accordance with the specifications as noted and that the prices quoted are not subject to change; and that on behalf of the organization, is in compliance with the Illinois Human Rights Act 775
ILCS 5/1.101, et seq. including establishment and maintenance of sexual harassment policies and program.
☐ Please confirm
*Response required
10.13. Detail Exceptions Sheet*
Any exceptions must be clearly noted on the Detail Exceptions Sheet(s). Failure to do so may be reason for rejection of the bid. It is not our intention to prohibit any potential Bidder from bidding by virtue of the specifications, but to describe the material and services actually required. The Village reserves the right to accept or reject any or all exceptions.
DETAIL EXCEPTIONS SHEET MUST BE SUBMITTED WITH THE BID RESPONSE.
Please download the below documents, complete, and upload.
• Detail_Exceptions_Sheet.pdf
*Response required
10.14. Provide 3 Municipal Government References*
Project Name: _______________________
Year Completed: _____________________
Location and Agency: _________________
Contact Person Name and Number: _____
10.15. Upload any Proposal Documents *
https://government-project.s3.us-west-2.amazonaws.com/10427/41581636-990c-405d-86c2-46b736061482_Detail_Exceptions_Sheet.pdf?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=ASIA47RIURE4MYORD4ZD%2F20250516%2Fus-west-2%2Fs3%2Faws4_request&X-Amz-Date=20250516T163000Z&X-Amz-Expires=72000&X-Amz-Security-Token=IQoJb3JpZ2luX2VjEJD%2F%2F%2F%2F%2F%2F%2F%2F%2F%2FwEaCXVzLXdlc3QtMiJIMEYCIQD8tbDnhVDTgmRH87kVBj88gzCaVdOhVhbs7hBELhP8WAIhAKY1MrJVxlVhsWzP6cPhXXNfvwf%2BUQojPtbDDzePW7jmKoMFCEkQAhoMODkyMzY0Njg3NjcyIgy3zdSo7WNFib4aKCIq4ARywSSkmm41Ay1ig4hHRHFfvj16F9jrovDYcj8pqshDBsoeSegzumCaTGlGVXnu1msPfNYYeEXrjHu2NrWNAKG9YryMue2%2FR0j80Lr8BFeKup%2F95UUhG61MEw%2Fq1WAePrJdQS5ZaaWdH7y%2F%2F8ZgWISZyrJ%2BjJ7k9DDb0mzuxCb4XjXWJCkd9LIpa50n%2F0SgiYLFIo6sWw1JPGYx8gSB5vg%2FfDgj5IXWhOK9pjPGu3WrLaRemYNH1%2B7K33KYUwVi5Vg6d%2FJ3m5iH9hJJZtwUX1unUE66qCNMnqYPlouruAHpPO1CaI7x9Syg1SodOjkiuEUqGGqmVJOK6l7LaiHar0qPlIVKS7dpamg%2FAZl5jh%2BUPFhRQqWSaQ2iHyov4Cyh9FKJwQg3CGn0egkq1XFPbwEKaDVvHZyMgfbCs97hcP256I9kMUJFZJWesu0Yfdv1%2FWC0DhxoOsGW%2Bpjox%2B0sxIdq0iAyaxE3pO833nFmJXZFeze6beiBnU0LWuhIt79WYgkZokl5ofKZUddTUzXaVnTSblIvsLMbQ8hosILrMs8ut3AQh3lxPUPJTfji%2FRLhVBBaPP5CawWlTUBaqvegU8B3Vvfu5PKPtYL2o9PEl8IsqQDW9ykHTxzCkeNvc31nZud926UCieh6JCBCyWL1mjkY7zq%2BtIVJ%2FrfI%2BUZX%2BVKev9kfRf7FN9bxol%2BsZ%2Bciqml%2BrQtzHBoZT5W%2FHC31FkCQcjUu%2F8C3gaFwBeCI9m%2Fw8JOLR%2FCAuP2uO554MhX2s2mwjWIHLjkP5g3VH48M50O4au0k5iglBgso%2FBgYKkn5njDpxp3BBjqaAaZ1T5EogWOO13%2BYn0OH9xSvIruu9%2BYRRvP0vW7XEQCfLto8M%2BkoyoMMLV7PIZ3hqMw4y6XWXdIxw0YvotIryRoDrgKZM4E2B1cXnfHjhGgXpYvqLHmWSREsjBe8CqkFZJ7E3rIVNQlV0QzJTfA%2FM0lf5TcLY9FmFRMO0Lma72H0i1Zc119r7GdDQH894sitILhOzR5ifCLeGgQ%3D&X-Amz-Signature=2e9c9bce1b26e0b4666f8a1c4e3aa275ab6cfbf80ad9350babf379db265cf4bc&X-Amz-SignedHeaders=host&response-content-disposition=attachment%3B%20filename%3D%22Detail_Exceptions_Sheet.pdf%22&x-id=GetObject