Statement of Work

Requirements for Road Base at Indian Crossing Parking Lot

Introduction The Utah BLM, Green River District is soliciting bids for the purchase and delivery of road base for a parking lot expansion project at the Indian Crossing Boat Ramp parking lot. The project will include enlarging the existing parking lot. The road base will be used to provide a stable driving surface at the parking lot. Contract price shall include material and transportation costs.

This solicitation will include a Base Bid for 660 tons of road base delivered to the site and Option 1 for additional road base material up to 200 tons to be delivered to the same location. Option 1 bid shall be a per ton unit cost to allow for any amount of road base between 60 and 210 tons.

Project Logistics The project location is approximately 30 miles east of Dutch John, Utah in the Browns Park area of Daggett County. See attached map (Attachment 1). Contractor shall coordinate delivery of materials with BLM to facilitate spreading of material by BLM personnel.

Requirements

1. Material – Road base shall be sound, durable material and be free of clay lumps, vegetation, construction debris and other deleterious material.

2. Gradation – The road base shall be well graded and meet one of the following gradations.

Screen Size Percent Passing Percent Passing Percent Passing

1½” 100 100

1” 100 90-100

¾” 60-90 70-100 70-90

½” 65-80

3/8” 55-75

#4 30-55 36-60 40-65

#8 22-43 24-47

#16 25-45

#30 11-27 12-31

#200 6-15 6-15 7-15

3. Submittal - Bidder shall provide laboratory test results from an independent testing firm for gradation and Atterberg Limits. Contractor shall submit physical samples if requested by the contracting Officer’s Representative.

4. Delivery – Road base material shall be delivered to the Indian Crossing Boat Ramp parking lot located approximately 30 miles east of Dutch John, Utah. Road base materials shall be dumped in cleared and graded area as directed by Contracting Officer’s Representative or a designated inspector. Contractor shall coordinate delivery to facilitate spreading and grading by BLM personnel.

5. Schedule – Contractor shall notify the BLM of delivery schedule for the road base material at least 10 business days prior to beginning the contract delivery. Delivery of materials shall take place between October 01, 2022 and December 28, 2022. Contractor shall make delivery of entire contract amount within a 2-week window between these dates.