Questions_and_Answers.docx
DOCX document 14 KB Posted
- Attached to
- Geotechnical Consultant Services Federal contract opportunity
- Solicitation number
- FERC13R0124
About this file
Questions and Answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Evaluation_Criteria.docx | DOCX document | |
| Attach_J-2 _Price_Model.xlsx | XLSX spreadsheet | |
| SOW.doc | DOC document | |
| Attach_J-1 _Past_Performance_Questionnaire.doc | DOC document | |
| Proposal_Instructions.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question #1: Can you explain how FERC will review for conflicts of interest if an engineering firm is working for the LNG company when asked to do a potential assignment?
Answer #1: The Government will make an OCI determination for each project in accordance with FAR 9.5.
Question #2: Can you let me know if this is a contractor that was with a prior firm or is it a new contract for the FERC?
Answer #2: This contract is a re-compete for existing services.
Question #3: The instructions call for submitting Attachment J-1 to references, and that offeror shall ensure that the questionnaires are submitted by the respondent to the Government by the proposal due date. Are we to ask respondents to complete these questionnaires and return directly to you the (in which case should it be e-mailed or sent via U.S. mail)? Or are we to collect these responses and submit them in our proposal package?
Answer #3: As stated in Proposal Instructions, Section IV. Past Performance, the offeror shall ensure that the questionnaires are submitted by the respondent to the Government by the proposal due date. Questionnaires shall be submitted via email by the submission due date.
Question #4: How much weight is given in terms of scoring for the prime small business to have all the capabilities referenced in the RFP.
Answer #4: At least 50% of all work performed under the resultant contract must be performed by the prime small business.