Program_Milestones.pdf

PDF 51 KB Posted

Attached to
WS3 Service Life Extension Program (SLEP) Federal contract opportunity
Solicitation number
FA9422-16-R-8036
Issued by
Department of the Air Force Materiel Command Nuclear Weapons Center

About this file

Attachment 8 - Program Milestones

View the file

Other files for this federal contract opportunity

Other files attached to WS3 Service Life Extension Program (SLEP), newest first.
File Type Posted
Atch_10-WS3_SLEP_Section_M-24Mar16.pdf PDF
Atch_8-Program_Milestones_16Mar16.pdf PDF
FA9422-16-R-8036_(Amend_0002-25Mar2016).pdf PDF
Atch_9-WS3_SLEP_Section_L-25Mar16.pdf PDF
WS3_Sample_Cost_Element_Summary_Table.xlsx XLSX spreadsheet
FA9422-16-R-8036_(RFP_Q A_18Mar2016).pdf PDF
WS3_SLEP_RFP_Amd_1.pdf PDF
Signed_SF30_-_RFP_Amd_1.pdf PDF
WS3_SLEP_RFP_Cover_Letter.pdf PDF
Attch_5_GFP_List_8_Jan_16.pdf PDF
SLEP_RFP_w_o_Atch_22Feb16.pdf PDF
SLEP_TMCR_17_Feb_16.pdf PDF
SLEP_CDRLs_Exhibit_A_17Feb16.pdf PDF
WS3_SLEP_Section_L-19Feb16.pdf PDF
WS3_SLEP_Section_M-19_Feb16.pdf PDF
SLEP_CDRLs_Exhibit_B_11Jan16.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Program Milestones

So that the Government can determine whether or not the Contractor is achieving satisfactory technical progress, certain milestones events during the performance of this contract (including Configuration Reviews and Audits) are established. These events are referred to as Program Milestones and are set forth below:

Program Milestones Completion Date Kickoff Meeting/Systems Requirements Review 09/27/2016

TO Guidance Conference 10/19/2016

Preliminary Design Review (PDR) 01/27/2017

Critical Design Review (CDR) 05/20/2017

Test Readiness Review (TRR) 09/29/2017

Contractor First PAS Test 10/27/2017

Government Developmental Test (DT) 03/02/2018

Government Operational Test (OT) 04/20/2018

Functional Configuration Audit (FCA) 05/04/2018

Physical Configuration Audit (PCA) 05/18/2018

Production Readiness Review (PRR) 06/01/2018

Phase I Completion 06/01/2018

Note: Assume 60 day approval cycle between Phase I and Phase II for the Government to obtain approval to enter production. No costs will be incurred prior to receiving written authorization to enter Phase II.

Program Milestones Completion Date Operational Training 03/29/2019

Phase II Installation at First Site 04/26/2019

Phase II Installation at Second Site 08/27/2019

Phase II Installation at Third Site 12/29/2020

Phase II Installation at Fourth Site 04/15/2020

Phase II Installation at Fifth Site 07/28/2020

Phase II Installation at Sixth Site 09/30/2020

Note: The completion dates for the Phase II Installations provided are notional. The contractor should propose new dates in an IMS. An accelerated schedule is favorable to the notional schedule above.