FA9101-21-Q-2012_QnA.pdf
PDF 317 KB Posted
- Attached to
- Ka Band Amplifiers Federal contract opportunity
- Solicitation number
- FA9101-21-Q-2012
About this file
This document contains questions and answers regarding solicitation number FA9101-21-Q-2012 for Ka band amplifiers. The Air Force Test Center requires at least four amplifiers by the initial delivery date, with the remaining four units to be delivered no later than 90 days after. Acceptable terms outlined include delivery of half the order on the due date and the other half two months after. The document clarifies that PCA refers to Physical Configuration Audit and FCA to Functional Configuration Audit in the acceptance test terminology.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 1 FA9101-21-Q-2012_Combined Synopsis Solicitation.pdf | ||
| Atch 01 Rqmt Doc_Ka Band Amps.pdf | ||
| 1 FA9101-21-Q-2012_Combined Synopsis Solicitation.pdf | ||
| Atch 01 Rqmt Doc_Ka Band Amps.pdf | ||
| 1 FA9101-21-Q-2012_Combined Synopsis Solicitation.pdf | ||
| Atch 01 Rqmt Doc_Ka Band Amps.pdf | ||
| Atch 02 FAR DFARS AFFARS Prov and Clauses.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
HEADQUARTERS AIR FORCE TEST CENTER (AFMC)
EDWARDS AIR FORCE BASE CALIFORNIA
20 Apr 21
MEMORANDUM FOR WHOM IT MAY CONCERN
SUBJECT: FA9101-21-Q-2012, Ka Band Amplifiers, Questions and Answers
1. There is a 40 week delivery for all 8 units. Is there any flexibility on this?
Due to current test schedules, the Government requires at least 4 units by the required date. The remaining units shall be delivered no later than 90 days after the initial delivery of units.
2. We can deliver 4 systems on or before the said date and 4 two months after. Is this something the Government willing to consider at all?
This is acceptable.
3. What do PCA and FCA stand for in the "Acceptance Test (PCA/FCA)”?
PCA: Physical Configuration Audit
FCA: Functional Configuration Audit