Attachment_1_Statement_of_Work_(SOW).pdf

PDF 504 KB Posted

Attached to
Upgrade Force Protection, Tanner Hill Federal contract opportunity
Solicitation number
FA875119BA007
Issued by
Department of the Air Force Materiel Command Research Laboratory

About this file

Attachment 1 - Statement of Work

View the file

Other files for this federal contract opportunity

Other files attached to Upgrade Force Protection, Tanner Hill, newest first.
File Type Posted
QUESTIONS_&_ANSWERS_2.docx DOCX document
QUESTIONS_&_ANSWERS.docx DOCX document
Attachment_5_Wage_Decision_No_NY20190031.pdf PDF
Attachment_6_RRS_Visit_Authorization_Rqst.pdf PDF
Attachment_2_Project_Specifications.pdf PDF
Solicitation_-_FA875119BA007.pdf PDF
Attachment_4_AFRL_Supplemental_Requirements.pdf PDF
Attachment_3_Drawings.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

FOR

UPGRADE FORCE PROTECTION

TANNER HILL TEST SITE

PREPARED BY AFRL/RIOC

AIR FORCE RESEARCH LABORATORY

INFORMATION DIRECTORATE

ROME, NEW YORK

SOLICITATION FA8751-19-B-A007

ATTACHMENT 1

PROJECT NR: RTVW 19-0009

DATED: 18 JULY 2019

1. SCOPE

A. . The work covered under this Contract consists of furnishing all labor, equipment, and materials and performing all work required to repair existing perimeter fence at the Tanner Hill Test Site back to original condition. Included in this work is an approximate 4000’ clear and grubbed path and a powered M30/K4 rated drop arm gate at the site’s entrance with electrical and access controls conduit being installed into the gates foundations so power and access controls connectivity can be completed at a later date.

Government property warning signage will also be installed along the entire test site perimeter. All work shall be done in accordance with the contract specifications, this statement of work, and the drawings

B. Location: The work area is located at AFRL Rome Labs Tanner Hill Test Site, Newport, New York.

C. General Notes:

i. All dimensions and locations of project components shall be field verified and shall be installed following manufacturer’s recommended installation guidelines.

ii. Items provided by owner are to be coordinated with the owner for installation.

D. Security

i. All contractor materials including but not limited to; trash containers, vehicles, and equipment, are to be located 25 meters (80 feet) minimum from all Air Force and installation buildings.

E. Description: Currently our Tanner Hill test site force protection infrastructure does not meet the level required. To mitigate this, the existing perimeter fencing needs sections repaired due to overgrown conditions and fallen tree branches.

Along with the fencing repairs is approximately clearing 4000’ clear path along the perimeter fence line so that visual inspection of the fencing can be completed.

A M30/K4 rated drop arm barrier will be installed at the sites entrance. Power and access controls conduit will be installed into the gates foundations, but no power and access controls will be connected to the gates at this time.

2. ITEMS OF WORK

2.1 Contractor to verify all dimensions and field conditions prior to beginning construction and notify designer immediately of any discrepancies.

2.2 Clearing: Perform clearing or cutting of brush, trees, tree limbs and stumps in the areas shown on the drawing. Do not cut or clear any brush or trees on the adjacent property owners’ land. Do not access adjacent property, all work operations to remain on government property.

2.2.1 Remove all materials from site except smaller brush or tops which are to be chipped or shredded and spread out evenly in the adjacent wooded areas on government property. Remove all previous downed trees and limbs in the clearing area. Remove all stumps in the new clear path area. Other stumps, including saleable timber harvest by others, remaining in the clearing area to be cut as close to the ground surface as possible. Remove all foreign objects in the clearing area, old fence wire, old fence posts, etc. Existing fencing on adjacent property to remain.

2.3 Fence Repairs; Fence repairs are to match the existing fence. Fence posts to be heavy duty class 3 galvanized steel T-Posts, 6 ½’, 1.33 lb/ft, with anchor plates, 10’ on center. Bracing at corner, end, and intermediate locations to be installed as shown on the drawing. Bracing hardware to be Wedge-Loc or approved equal. T-Posts to have safety caps at top. Perform any clearing or cutting of brush or trees to install new fencing.

Debris from clearing and cutting can be left on site. Fence wire to be class 3 galvanized twisted barbless 12 ½ gauge two ply, four strands. T-post clips for fence wire to be class 3 galvanized.

2.3.1 New warning signs; If existing warning signage is damage, replace to match existing.

Aluminum sheeting, 6061-T6, 1’-3” x 1’-6”, .090” thick. Mount as shown in detail on drawing.

Attach sign panel to post with galvanized steel hardware. Sign post to be class 3 galvanized steel U-Chanel sign post, 2 pounds per foot, 8’ long. Sign location to be one foot inside fence line and spacing (200’) to be as shown on the drawing. Sign panel to be blank, government will attach adhesive back base warning sign.

2.4 Clear Path: New clear path to be located as shown on the drawing. Repair surface ruts and damage from clearing and grubbing operations. New clear path to be constructed on the surface 10 feet on the inside of the fence line. Path alignment can vary slightly to avoid obstacles but remain within the clearing area.

2.5 M30/K4 Drop Arm Barrier: Drop arm gate system to be B&B Armr Model 773E, or equal, M30/K4 certified. Clear roadway opening to be 24’. Provide complete installation and operation of vehicle barrier as specified. Work includes furnishing all items and accessories required or necessary for a complete operational vehicle barrier including as shown on the drawings and specified herein. Follow all manufacturer’s specifications and installation instructions.

2.7 Protection and Clean Up: Protect or restore all surfaces or items to remain. Remove all debris and excess materials from site. Restore storage and stockpile areas to original conditions.

3. SUBMITTALS

All submittals must be signed “approved” by designer, any submittals not seen by the designer shall not be considered approved or installed by the contractor.

A. Treated wood, manufacturer information B. Fence T-post, manufacturer information C. Fence wire, manufacturer information D. Sign post, manufacturer information E. M30/K4 Drop arm barrier, manufacturer information F. M30/K4 Drop arm barrier control system, manufacturer information