Question_Answer_1.pdf

PDF 326 KB Posted

Attached to
Materials Handling System at Spangdahlem AFB, Germany Federal contract opportunity
Solicitation number
FA8604-18-R-8106
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Wright Patterson Air Force Base

View the file

Other files for this federal contract opportunity

Other files attached to Materials Handling System at Spangdahlem AFB, Germany, newest first.
File Type Posted
Question_Answer_2.pdf PDF
Amendment_001.pdf PDF
Proposal_Checklist.Pricing_Summary_Sheet.pdf PDF
USP701-01_dwg.dwg DWG drawing
8984.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question: Para 3.2.8 of Appendix A asks for FR plywood flooring but does not call for any kind of covering over the plywood. Is this correct or is there something going on top of the FR plywood like tile or rubber matting?

Answer: A covering shall be provided; Appendix A has been updated with this revision.

Question: For the mobile aisle there are no dimensions on the drawings or the appendix. A rough estimate can be established based on the size of the weapons racks, however a min/max size would be helpful.

Answer: The footprint of the entire mobile aisle system is approximately 31’ x 35’.

Question: For the mobile aisle, do you want the ramp on 1 side, 2 sides, or all sides? The appendix does not specify other than 1 should be provided.

Answer: Ramps shall be provided on both the North and South sides of the mobile aisle as shown on AF Drawing USP701-01.

Question: For the removal of the existing weapons racks it states that “Approximately 75 existing weapons cabinets will be removed and disposed of at the recycling facility at Ramstein AB which is roughly 115 km southeast of Spangdahlem AB.”

What is the method to which the cabinets will get there? Does the base have scrap bins that can be delivered to the job site and hauled off to the recycling center or will the contractor be required to rent equipment, fill it, and drive the 115 kms?

Answer: The contractor will be required to obtain their own equipment to dispose of the existing cabinets.