Statement of Work
Wright-Patterson Air Force Base Security Forces Shoot House
28 June 18
OBJECTIVE:
Vendor shall install a three story shipping container shoot house/Military Operations on Urban Terrain (MOUT) facility capable of supporting the Shoot Move Communicate course and Active Shooter Response Training.
This training is conducted using simunitions and therefore the training cannot be conducted in an existing facility. The shoot house needs to have multiple rooms/doorways allowing for room clearing and will be three stories tall.
1.0 GENERAL:
The Contractor shall provide all supervision, labor, materials, equipment, and transportation to accomplish this project in accordance with this statement or work.
1.1 A power source is available on-site for Contractor use.
1.2 Shoot house shall not have/require installation of any utilities (water, sewer, electricity, etc.).
1.3 General Management: Contractor(s’) Project Lead shall demonstrate timely and superior communication skills, along with efficient time management skills in order to ensure the project is completed within the projected time constraints.
1.4 Concrete foundation is in place measureing approximately 30 feet by 86 feet.
1.5 Structure shall not be anchored to the ground.
2.0 TASKS:
Shoot house shall be built to the following standards:
2.1 Three story (not exceeding 32 ft high total) structure made from shipping containers modified for MOUT training using simunitions.
2.2 Three shipping containers shall be used per story, for a total of 9 shipping containers.
2.3 Contain at least 17 Defined Rooms no smaller than 8 feet by 9 feet.
2.4 Each room must have at least one exterior wall window with solid shutter which can be closed and have latches located on the interior.
2.5 Each room shall have a door separating the room from the hallway, or a door to an adjoining room that has a door to the hallway.
2.6 Each floor shall have at least one room that does not have a hallway door, but has a door to an adjoining room that has a door to the hallway.
2.7 The second floor shall have a room that does not have a hallway door, but has two doors that each connect to a different adjoining room, both of which must have hallway doors.
2.8 Have at least one interior stairwell per story which will open into a hallway.
2.9 At least two ground floor entrances with lockable doorhandles.
2.10 Structure footprint shall not exceed 26 feet by 42 feet.
2.11 Color shall be tan both inside and outside.
3.0 DELIVERY PROCEDURES COMMERCIAL VEHICLES:
3.1 Physical Security: All vehicles larger than a large pick-up truck are required to be inspected by the WPAFB CVDG prior to entering the installation. Vehicles to be inspected include, but are not limited to, the following.
3.1.1 Step van/panel truck
3.1.2 Tractor/trailor, box, and flatbed containing cargo
3.1.3 Tanker trucks
3.1.4 Box Trucks
3.1.5 Tour buses
3.1.6 Garbage/recycled waste trucks
3.1.7 Concrete trucks/mixers, dump trucks
3.1.8 Cranes, recreational vehicles, petroleum tanke.
3.2 This inspection will be conducted at Gate 16A located off State Route 444.
The following are exceptions to vehicles utilizing the CVDG:
3.2.1 If the vehicle has the product inside (concrete and asphalt trucks) and timely delivery is necessary due to product deterioration it does not need to enter the CVDG. To bypass the CVDG, the contractor shall submit a list containing drivers’ names, social security numbers and the state in which the driver's license is held for those drivers who will be entering the base. This shall be accomplished 24 hours prior to requested entry time. If entry is requested on Monday, this list must be submitted by Friday at 1630 hours. All lists shall be submitted to the 88th ABW/CE Directorate contract inspector. The only gates that may be used under this exemption shall be 15A, 26A, 38A, and gate 1B. If the driver's name is not on the list, he/she will not be allowed access to the installation through these gates and the base will not assume liability for denied access.
3.2.2 If a delivery vehicle must exit, and then re-enter the base to complete its route, the vehicle shall be resealed upon exiting the base. After initially passing through the commercial vehicle delivery gate, trucks shall be resealed at Gates 15A, 38A and 22B.
The resealing of the trucks will allow them to continue to any other area of the installation (Areas A, B, or Kittyhawk) without reprocessing through the CVDG. To receive resealing assistance, the drivers shall physically stop at one of the three authorized gates and request the installation entry controller to reseal their truck and provide the next location of their delivery. The controller will reseal the truck and give the delivery driver a pre-clearance form. The driver shall present the pre-clearance form to the entry controller at the next point of installation entry. This reentry can be through any base gate.
3.3 Wright Patterson Integrated Defense Plan, paragraph 3.10.12.9.2. All irregular deliveries will be sent to the CVDG for inspection. All visitors, which include contractors and commercial vendors without proper background checks and contractor passes, will not be allowed on WPAFB unless escorted by the receiving agency. This will take place after the individual(s) are issued a pre-clearance form at the CVDG. After successful completion of the vehicle inspection, the receiving agency will escort the individual to and from their destination on WPAFB. An inspector at the CVDG will contact the receiving agency, informing them to send an escort to the CVDG.
Escorts will remain with the vehicle at all times while it is on WPAFB.
3.4 Vehicles may be subject to an inspection at any of installation entry control points during a directed random antiterrorism measure (RAM). Any commercial vehicle, regardless of size, can be directed to the CVDG at the discretion of the installation entry controller.
4.0 PROJECT COMPLETION:
Project will be completed 120 days after award of the contract.
5.0 CONTRACTOR WORK SCHEDULE:
Contractor’s work hours shall be restricted to 0615hrs to 2100hrs Mon-Sun. Due to 2017 federal holidays and installation family days the contractor shall not work the following listed below:
23-26 November 25-26 December