PreAward-RFIs_03.pdf

PDF 125 KB Posted

Attached to
Project 051863 - Remove Asbestos High Bay, Building 65 Federal contract opportunity
Solicitation number
FA8601-16-B-0001
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Wright Patterson Air Force Base

About this file

Pre Award RFIs 03 - responses.

View the file

Other files for this federal contract opportunity

Other files attached to Project 051863 - Remove Asbestos High Bay, Building 65, newest first.
File Type Posted
FA8601-16-B-0001_Conformed_Solicitation.pdf PDF
SIDING-REPLACEMENTexisting.pdf PDF
PreAward-RFIs_02.pdf PDF
Pic_01c.jpg JPG image
Pic_14.jpg JPG image
Pic_02.jpg JPG image
Pic_03a.jpg JPG image
Pic_10.jpg JPG image
Pic_06.jpg JPG image
Pic_11.jpg JPG image
Pic_04.jpg JPG image
Pic_07.jpg JPG image
Pic_05b.jpg JPG image
Pic_01b.jpg JPG image
Pic_03b.jpg JPG image
Pic_12.jpg JPG image
Pic_08.jpg JPG image
Pic_05a.jpg JPG image
Pic_13.jpg JPG image
Pic_01a.jpg JPG image
Pic_09.jpg JPG image
Pic_15.jpg JPG image
Pic_16.jpg JPG image
Addendum_2.pdf PDF
PreAward-RFIs.pdf PDF
FA8601-16-B-0001_Amendment_0001.pdf PDF
Specifications.pdf PDF
AsBuilt-Drawings.pdf PDF
Wage_Determination_OH160102_MOD__12.pdf PDF
Proj_051863_-_Site_Visit_Info.pdf PDF
Proj_051863_-_Site_Visit_Sign-in_Sheet.pdf PDF
FA8601-16-B-0001_Solicitation.pdf PDF
Attach_2_-_DRAWINGS.pdf PDF
Attach_5_-_Wage_Determination_OH160102.pdf PDF
Attach_4_-_Section_01_02_20_Addendum_1.pdf PDF
Attach_3_-_Addendum_1.pdf PDF
Attach_1_-_Specifications.pdf PDF
Draft_Drawings.pdf PDF
Draft_Specs.pdf PDF
Show all 39

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre Award RFIs 03 08 August 2016 Project 051863 – Remove Asbestos High Bay, Building 65 Solicitation # FA8601-16-B-0001

1. Amendment 1 added a line item to the bid form but did not re-issue the bid form. In addition, RFIs 17 and 27 / Amendment 1 indicated that a new bid form would be issued. Should we create our own bid form based on the information outlined in Amendment 1 or will you be re-issuing the bid form prior to the bid date?

REPLY: A new bid schedule / bid form will not be issued, nor do you need to create your own.

Follow the instructions in the original solicitation and amendment 0001, placing your bid for each of the 3 line items.

2. Amendment 1 indicates that there is a new CLIN 0002 being added. It appears that this new CLIN is to replace 4700 SF of wood framing and insulation. I have the following questions:

a. Why is insulation included in the unit price CLIN? Doesn’t all of the insulation need to be removed (and replaced) so that the framing can be inspected? It would seem that no insulation would be in the unit price CLIN (the insulation would be in the “base bid”), only wood framing replacement. Please clarify.

REPLY: The removal of existing insulation, which is between the framing, is not a requirement of the contract. The insulation is not known to be ACM. Note 004 on the demolition drawings referring to removal of ACM including panels and insulation applies only to insulation that has become contaminated from any of the severely deteriorated panels. It should be obvious upon removal of the panels alone if the framing is deteriorated and needs to be replaced.

b. Since the actual quantity of deteriorated framing is not known, it would make sense that the new unit price CLIN 0002 includes all of the wood framing replacement required for the job.

Does the new unit price CLIN 0002 include all of the wood framing replacement including the areas indicated by notes 015 on Drawings AD301, AD302, AD303, and AD 304 and by notes 017 on AD302 and AD304?

REPLY: The quantity of framing shown in the new CLIN 0002 is intended to include all framing required including the areas indicated on the drawings.

3. RFI 24 / Amendment 1 indicates that we are to cut the new panels above and below the existing horizontal framing members. This would require not only cutting the panels at these locations but would also require additional furring be installed above and below these members so this is an expensive item of interest for us. I looked through the as-built drawings provided in Amendment 1 but could not find anything that specifically shows the spacing of these members. I also looked for photos of the High Bay area which I thought were supposed to be included in Amendment 1 but could not find those. How far apart are these framing members? I saw a couple of dimensions on the as-built(s) which would lead me to believe these framing members run horizontally and are spaced about 5’ apart vertically. Is this the approximate spacing of these members?

REPLY: The as built drawing interior elevations show the horizontal exposed struts, girts and cross bracing for each elevation. The north wall section shows the horizontal girts are placed at 10’ 7 3/8” apart.