PreAward-RFIs_02.pdf

PDF 137 KB Posted

Attached to
Project 051863 - Remove Asbestos High Bay, Building 65 Federal contract opportunity
Solicitation number
FA8601-16-B-0001
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Wright Patterson Air Force Base

About this file

Responses for a second round of pre-award questions.

View the file

Other files for this federal contract opportunity

Other files attached to Project 051863 - Remove Asbestos High Bay, Building 65, newest first.
File Type Posted
FA8601-16-B-0001_Conformed_Solicitation.pdf PDF
PreAward-RFIs_03.pdf PDF
SIDING-REPLACEMENTexisting.pdf PDF
Pic_01c.jpg JPG image
Pic_14.jpg JPG image
Pic_02.jpg JPG image
Pic_03a.jpg JPG image
Pic_10.jpg JPG image
Pic_06.jpg JPG image
Pic_11.jpg JPG image
Pic_04.jpg JPG image
Pic_07.jpg JPG image
Pic_05b.jpg JPG image
Pic_01b.jpg JPG image
Pic_08.jpg JPG image
Pic_05a.jpg JPG image
Pic_13.jpg JPG image
Pic_01a.jpg JPG image
Pic_09.jpg JPG image
Pic_15.jpg JPG image
Pic_16.jpg JPG image
Pic_03b.jpg JPG image
Pic_12.jpg JPG image
Addendum_2.pdf PDF
PreAward-RFIs.pdf PDF
AsBuilt-Drawings.pdf PDF
Wage_Determination_OH160102_MOD__12.pdf PDF
FA8601-16-B-0001_Amendment_0001.pdf PDF
Specifications.pdf PDF
Proj_051863_-_Site_Visit_Sign-in_Sheet.pdf PDF
Proj_051863_-_Site_Visit_Info.pdf PDF
FA8601-16-B-0001_Solicitation.pdf PDF
Attach_2_-_DRAWINGS.pdf PDF
Attach_5_-_Wage_Determination_OH160102.pdf PDF
Attach_4_-_Section_01_02_20_Addendum_1.pdf PDF
Attach_3_-_Addendum_1.pdf PDF
Attach_1_-_Specifications.pdf PDF
Draft_Drawings.pdf PDF
Draft_Specs.pdf PDF
Show all 39

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre Award RFIs 02 02 August 2016 Project 051863 – Remove Asbestos High Bay, Building 65 Solicitation # FA8601-16-B-0001

1. Key Note 010 (in drawings) indicates Conduits to be removed but they run off this wall and onto other walls. What extent is removal required? They Run up the middle of the wall half way up and then are mounted on wall shown on AD032 and then run to above Hangar doors.

REPLY: Conduits are electrical equipment; the Government response to RFI #37 of the previous Pre-AwardRFIs indicated that all equipment, including electrical shall be removed its entirety back to the service panel.

2. Who is responsible for moving components in front of transite panels?

REPLY: RFI #42 of the previous Pre-AwardRFIs has addressed this.

3. Response to previous RFI stated, photos would be forth coming, have not seen them.

REPLY: Pictures were posted to FBO on 02 August 2016. Additional as-built drawings were posted 08 August 2016.

4. Who is responsible for protecting equipment to remain?

REPLY: the Contractor will be responsible for protecting equipment that will remain during the contract operations.

File details come from the government source that posted it. Updated .