Sheet1 Responses to Contractor Questions for Solicitation FA8601-14-R-0038
| Question | Reference | Response | ||
| 1 | Is this a new requirement, a replacement for someone | |||
| that has left, or a continuation/re-bid of a previous contract? | N/A | THIS REQUIREMENT IS A CONTINUATION OF A PREVIOUS |
CONTRACT THAT WAS A SOLE SOURCE.
| 2 | If a previous contractor existed, is there any reason for you to | |
| believe that this contractor would not be bidding this RFP? | N/A | THIS RFP IS FULL AND OPEN COMPETITION SO THE PREVIOUS |
CONTRACTOR CAN SUBMIT A BID.
| 3 | Cost Item 1002 states a “Base Period of Performance”. Should | |
| this be “Option 1 Period of Performance”, to coincide with Item 1001? | Attachment 1. | |
| Solicitation Document | YES. CLIN 1002 SHOULD BE “OPTION I PERIOD OF |
PERFORMANCE: 16 JUNE 2015 THROUGH 15 JUNE 2016” TO COINCIDE WITH CLIN 1001. AN AMENDMENT WILL BE ISSUED TO THE RFP ATTACHMENT 1. SOLICITATION DOCUMENT TO CORRECT THIS.
| 4 | You list Travel for MRA Expert (Items 0002 and 1002) as “12 | |
| each.” How is this possible, as travel costs will vary across suppliers (e.g., airlines, hotels) and the number of classes and trips may vary (section 3.3.2, 3rd paragraph “…actual dates, locations, and number of classes may change.”) over the next 24 months? Please explain what cost estimate you would like from us. | Attachment 1. | |
| Solicitation Document and DOD FMR, Volume 9 | GUIDANCE IS PROVIDED IN DOD FINANCIAL MANAGEMENT |
REGULATION, VOLUME 9. HISTORICALLY, THIS POSITION HAS AVERAGED ONE TRIP PER MONTH FOR ANNUAL AMOUNT OF 12. A SAMPLE SCHEDULE IS INCLUDED IN SOW 3.3.2, WHICH CAN BE USED TO CREATE A COST ESTIMATE USING CURRENT RATES. THE CONTRACTOR WILL SUBMIT TRAVEL RECEIPTS UPON CONCLUSION OF TRAVEL TO ENSURE DOD FMR 9 STANDARDS ARE BEING FOLLOWED. AN AMENDMENT WILL BE ISSUED FOR ATTACHMENT 1. SOLICITATION DOCUMENT TO CHANGE FROM “12 EACH” TO “1 LOT”
| 5 | Do cost Items 0001 and 1001 allow for vacation and/or sick time? | |
| If so, how much vacation and/or sick time have you budgeted for? | Attachment 2. | |
| SOW | SICK TIME AND VACATION DAYS ARE NOT WRITTEN INTO |
THE CONTRACT. AS A PERFORMANCE BASED-CONTRACT, THE CONTRACTOR IS REQUIRED TO IN ACCORDANCE WITH PERFORMANCE METRICS. IF THE CONTRACTOR IS TAKING VACATION OR SICK DAYS, THEY MUST STILL BE ABLE TO MEET THE PERFORMANCE METRICS. THIS CAN BE ACCOMPLISHED BY ACCOMPLISHING THE TASK BEFORE VACATIONS, COORDINATING VACATION TIME AROUND SCHEDULED EVENTS, MAKING UP LOST WORK DUE TO SICK TIME ON OTHER DAYS OR WEEKENDS, ETC. AN UPDATE WILL BE ISSUED TO THE SOW TO ADD PERFORMANCE METRICS
| 6 | You have checked 52.219-4, Notice of Price Evaluation | |
| Preference for HUBZone Small Business Concerns (Jan 2011). Is this procurement a HUBZone set-aside? Are you waiving the preference? | Attachment 1. | |
| Solicitation Document | THIS IS NOT A HUBZONE SET-ASIDE. POLICY REQUIRES THIS |
CLAUSE IS INSERTED FOR FULL AND OPEN COMPETITION
| 7 | Evaluation Factor 1, Subfactor 1, lists 8 Measures of Merits; | |
| however, the Statement of Work lists 11 factors in section 3.2. Which listing do we respond to? | Attachment 2. | |
| SOW and Attachment 3. Evaluation Factors | IN THE SOW, THE ADDITIONAL THREE QUALIFICATIONS ARE |
COVERED BY MEETING THE CIRTERIA OF OTHER QUALIFICATIONS. SOW 3.2.7 IS ALSO COVERED BY 3.2.5 and 3.2.6. SOW 3.2.9 IS ALSO COVERED BY 3.2.3, 3.2.4, AND 3.2.10. SOW 3.2.11 IS ALSO COVERED BY 3.2.2, 3.2.5, and 3.2.5.