FA8552-17-R-0002-0001.pdf

PDF 25 KB Posted

Attached to
TH-1H Automatic Dependent Surveillance - Broadcast OUT Federal contract opportunity
Solicitation number
FA8552-17-R-0002
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Robins Air Force Base

About this file

Amendment 0001 to FA8552-17-R-0002

View the file

Other files for this federal contract opportunity

Other files attached to TH-1H Automatic Dependent Surveillance - Broadcast OUT, newest first.
File Type Posted
ADS-B_Out_Page_Count_chg1.pdf PDF
Questions_&_Answers_24_April_2017.pdf PDF
FA855217R0002_______0002.pdf PDF
ADS-B_Out_Page_Count.pdf PDF
Questions_&_Answers_6_April_2017.pdf PDF
Questions_&_Answers_30_March_2017.pdf PDF
PWS27Mar17.pdf PDF
DetailSpec.pdf PDF
Attachment1_PricingVolume.xlsx XLSX spreadsheet
Atch1-PricingVolume.xlsx XLSX spreadsheet
FullRFP.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

JS

2. AMENDMENT/MODIFICATION NO.

FA8552-17-R-0002-0001

3. EFFECTIVE DATE

4. REQUISITION/PURCHASE REQ. NO.

FD20601730434

5. PROJECT NO (If applicable)

6. ISSUED BY CODE

SOF/PR - ROTARY WING & AVIONICS, AFLCMC/WIUKB

235 BYRON ST STE 19A

BLDG 300 CML PHN 478 926 7227

ROBINS AFB GA 31098-1670

BUYER: Marcus R. Green/WIUK marcus.green.7@us.af.mil Phone: (478) 926- 7272 No Collect Calls

7. ADMINISTERED BY (If other than item 6) CODEFA8552

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

CODE

X

9A. AMENDMENT OF SOLICITATION NO.

FA855217R0002

9B. DATED (SEE ITEM 11)

20-MAR-2017

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods. ( a ) By completing Items 8 and 15, and returning copies of the amendment; ( b ) By acknowledging receipt of this amendment on each copy of the offer submitted; or ( c ) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified. 3-MAY-2017 4:00 PM

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return 1 copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

ROUTINE

15A. NAME AND TITLE OF SIGNER (Type or print)

15B. CONTRACTOR/OFFEROR

BY ________________________________________________________

(Signature of person authorized to sign)

15C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16B. UNITED STATES OF AMERICA

BY ____________________________________________________

(Signature of Contracting Officer)

16C. DATE SIGNED

FACILITY CODE

NSN 7540-01-152-8070

PREVIOUS EDITION UNUSABLE

30-105 STANDARD FORM 30 (REV. 10-83)

PRESCRIBED BY GSA

FAR (48 CFR) 53.243

X

X X

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

Continuation of block 14. DESCRIPTION OF AMENDMENT/MODIFICATION

The purpose of this amendment is to correct a typographical error on the production installation CLINS, incorporate the revised Performance Work Statement, incorporate the revised Attachment 1 (Pricing Volume), and incorporate the TH-1H Detail Specification as denoted within:

A. Correct the delivery quantity on the production CLIN 1010 as follows:

FROM: Quantity 26 LO TO: Quantity 1 LO

B. Correct the delivery quantity on the production CLIN 2010 as follows:

FROM: Quantity 13 LO TO: Quantity 1 LO

C.Incorporate the revised Performance Work Statement dated 27 March 2017, as attached in Section J. The following changes were incorporated as follows:

a. PWS paragraph 4.10.3 is hereby revised as follows:

FROM: 4.10.3 Interface Control Document: The Contractor shall submit a list of recommended changes to the TH-1H Avionics Interface Control Document.

(CDRL A00G; DI-SESS-81248B)

TO: 4.10.3 Interface Control Document: The Contractor shall develop a TH-1H Avionics Interface Control Document to supplement the TH-1H Detail Specification. (CDRL A00G; DI-SESS-81248B)

b. PWS paragraph 4.11.9 is hereby revised as follows:

FROM: 4.11.9 Preliminary Design Review (PDR): The Contractor shall conduct a

PDR after completion of all technical research and development of a preliminary design approach. The PDR shall be held before the Contractor begins the detailed engineering process and develops the preliminary TDP.

The Contractor shall present the design analysis and preliminary design for Government review and approval. The Contractor shall provide all preliminary technical design documents at the PDR. The PDR shall be hosted in conjunction with the IPR of the TDP. The Contractor shall prepare design review meeting agenda and minutes and for Government approval.

Proposed agenda shall be submitted at least 10 business days prior to the meeting. Meeting minutes shall be submitted within 10 business days after meeting. The minutes shall constitute the review report and shall require approval of the Government Program Manager prior to distribution. The meeting minutes shall be complete and accurate, so that the number of report rejections shall not exceed one per submittal. Once the document is received, the Government will have five business days to approve or reject

it. Rewritten documents shall be resubmitted to the Government within five business days. (CDRL A00L; DI-ADMN-81249B), (CDRL A00M;

DI-ADMN-81250B)

TO: 4.11.9 Preliminary Design Review (PDR): The Contractor shall conduct a PDR after completion of all technical research and development of a

Amendment/Modification FA8552-17-R-0002-0001 preliminary design approach. The PDR shall be held before the Contractor begins the detailed engineering process and develops the preliminary TDP.

The Contractor shall present the design analysis and preliminary design for Government review and approval. The Contractor shall provide all preliminary technical design documents at the PDR. The Contractor shall prepare design review meeting agenda and minutes and for Government approval. Proposed agenda shall be submitted at least 10 business days prior to the meeting. Meeting minutes shall be submitted within 10 business days after meeting. The minutes shall constitute the review report and shall require approval of the Government Program Manager prior to distribution. The meeting minutes shall be complete and accurate, so that the number of report rejections shall not exceed one per submittal. Once the document is received, the Government will have five business days to approve or reject it. Rewritten documents shall be resubmitted to the Government within five business days. (CDRL A00L; DI-ADMN-81249B), (CDRL A00M; DI-ADMN-81250B)

D. Incorporate the TH-1H Detail Specification, Revision B dated 11 March 2010, as attached in Section J.

E. As referenced in Block 11 on page 1 of this amendment, the solicitation period is hereby extended as follows:

FROM: 19 APRIL 2017 TO: 3 MAY 2017

F.All other terms and conditions remain the unchanged.

PART I - THE SCHEDULE

SECTION B

SUPPLIES OR SERVICES AND PRICES/COSTS

PRODUCTION INSTALLATION (LABOR)

Item No.

Firm Fixed Price Quantity U/I Unit Price Amount

1 LO

N016 Production Installation (Labor)

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001-2008 2008

Class I ODS Substance Application/Use Quantity none Place of Perf Quantity (U/I) *ARO Notice to

Proceed _ Req No / Pri

Required Period of Performance

A FB3034 1 LO *12 Months

Proposed Period of Performance

A FB3034 1 LO

PRODUCTION INSTALLATION (LABOR)

Item No.

Firm Fixed Price Quantity U/I Unit Price Amount

1 LO

N016 Production Installation (Labor)

PRODUCTION INSTALLATION (LABOR)

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001-2008 2008

Class I ODS Substance Application/Use Quantity none Place of Perf Quantity (U/I) *ARO Notice to

Proceed _ Req No / Pri

Required Period of Performance

A FB3034 1 LO *6 Months

Proposed Period of Performance

A FB3034 1 LO

SHIP TO / PLACE OF PERFORMANCE

TYPE/CODE: + IAW1423

MARK FOR: (See Individual Line Item) REQUISITION NUMBER: (See Individual Line Item) REQUISITION PRIORITY: (See Individual Line Item)

AWARD NUMBER:

TYPE/CODE: A FB3034

FB3034 23 FTS LGS USAF AF SUPPLY

BLDG 30800 CP 334 255 8844

CAIRNS ARMY AIR FIELD

FORT RUCKER AL 36362-5121

USA

MARK FOR: (See Individual Line Item) REQUISITION NUMBER: (See Individual Line Item) REQUISITION PRIORITY: (See Individual Line Item)

AWARD NUMBER:

TYPE/CODE: A SW3119

DLA DISTRIBUTION WARNER ROBINS

455 BYRON STREET BLDG 376

ROBINS AFB GA 31098-1887

UNITED STATES

MARK FOR: (See Individual Line Item) REQUISITION NUMBER: (See Individual Line Item) REQUISITION PRIORITY: (See Individual Line Item)

AWARD NUMBER:

PART III - LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J

LIST OF ATTACHMENTS

Form Number Description/File Name Date Number of Pages Performance Work Statement Revision 2

27MAR2017 27

TH-1H Detail Specification 11MAR2010 39

Attachment 1 - Pricing Volume UNDATED 1

File details come from the government source that posted it. Updated .