FA8534-24-R-0008.pdf

PDF 817 KB Posted

Attached to
Tunner CLS Bridge Federal contract opportunity
Solicitation number
FA8534-24-R-0008
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Robins Air Force Base

About this file

This document is a solicitation for a 5-year, Fixed Price Incentive Firm Target (FPIF)/Firm Fixed Price (FFP) Indefinite Delivery/Requirements-type contract to provide support for the 60K Tunner Aircraft Cargo Loader. The required services include Material Management, Program Engineering Support, Unscheduled Depot Level Maintenance of the Tunner, and Contingency High Priority Mission Support Kits. The government intends to award this sole source bridge contract to Leonardo DRS in accordance with FAR 6.302-1. The solicitation has a one-year basic period of performance with four one-year options. It is set aside for U.S. firms only, with no foreign participation allowed. The solicitation is anticipated to be issued around May 6, 2024 through the Government Point of Entry. Interested offerors should register on the site to receive notifications.

View the file

Other files for this federal contract opportunity

Other files attached to Tunner CLS Bridge, newest first.
File Type Posted
FA8534-24-R-0008.pdf PDF
Tunner CLS Portfolio - updated.pdf PDF
Tunner_CDRL_Portfolio.pdf PDF
Atch_2-QASP.pdf PDF
Atch_4-Safety_Appendix.pdf PDF
Atch_5_Tunner_GFP_02Apr2024.xlsx XLSX spreadsheet
Atch_9-Cost_Proposal_Adequacy_Structure.pdf PDF
Atch_8-Tunner_Registration_Numbers.pdf PDF
Atch_3-TDP.pdf PDF
Atch_7-Provisions_for_SOFA_ROK.pdf PDF
Atch_6-Tunner_TSSA_Determination.pdf PDF
FA8534-24-R-0008.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 1447 (REV. 8/2016)

PREVIOUS EDITION NOT USABLE Prescribed by GSA - FAR (48 CFR) 53.214(d)

23. ACCOUNTING AND APPROPRIATION DATA

SEE SCHEDULE

24. TOTAL AWARD AMOUNT (For Government Use Only)

TELEPHONE NUMBER

UNIQUE ENTITY

IDENTIFIER

CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER

NO COLLECT CALLS

4. SOLICITATION NUMBER

FA8534-24-R-0008

6.SOLICITATION ISSUE DATE

8. THIS ACQUISITION IS UNRESTRICTED OR SET ASIDE: % FOR

SMALL BUSINESS WOMEN-OWNED SMALL BUSINESS (WOSB)

ELIGIBLE UNDER THE WOSB PROGRAM

HUBZONE SMALL

BUSINESS EDWOSB

SERVICE-DISABLED VETERAN-

OWNED SMALL BUSINESS NAICS: 333924

8(A) SIZE STANDARD: 900

DATE SIGNED

28. UNITED STATES OF AMERICA (Signature of Contracting Officer)

26. AWARD OF CONTRACT: YOUR OFFER ON SOLICITATION NUMBER

SHOWN IN BLOCK 4 INCLUDING ANY ADDITIONS OR CHANGES WHICH

ARE SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

ROUTINE

Subject to the terms and conditions stated herein, the Contractor agrees to hold its offered prices firm for 30 days.

SEE LINE ITEM SCHEDULE

22.

AMOUNT

16. AUTHORITY FOR USING OTHER THAN 10 USC 2304 41 USC 253

FULL AND OPEN COMPETITION (c) (1 ) (c) ( )

DATE SIGNED

27. SIGNATURE OF OFFEROR/CONTRACTOR

20.

UNIT

21.

UNIT PRICE

19.

QUANTITY

13. CONTRACTOR OFFEROR CODE FACILITY CODE

11. IF OFFER IS ACCEPTED BY THE GOVERNMENT WITHIN * ___ CALENDAR DAYS (60 CALENDAR

DAYS UNLESS OFFEROR INSERTS A DIFFERENT PERIOD) FROM THE DATE SET FORTH IN BLOCK 9

ABOVE, THE CONTRACTOR AGREES TO HOLD ITS OFFERED PRICES FIRM FOR THE ITEMS

SOLICITED HEREIN AND TO ACCEPT ANY RESULTING CONTRACT SUBJECT TO THE TERMS AND

CONDITIONS STATED HEREIN. *30

RATING

DO: A1

3. AWARD/EFFECTIVE DATE

FA8534

2. CONTRACT NUMBER

X

17.

ITEM NUMBER

12. ADMINISTERED BY CODE

Total

SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK: 14 EFT:T

SCD:B

NAME AND TITLE OF SIGNER (Type or Print) NAME OF CONTRACTING OFFICER

5. SOLICITATION TYPE

SEALED BIDS NEGOTIATED

(IFB) (RFP)

15. PROMPT PAYMENT DISCOUNT

25. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN 1

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER ALL ITEMS SETFORTH

OR OTHERWISE IDENTIFIED ABOVE AND ON ANY CONTINUATION SHEETS SUBJECT

THE TERMS AND CONDITIONS SPECIFIED HEREIN.

10. ITEMS TO BE PURCHASED (Brief Description)

SUPPLIES SERVICES Industrial Truck, Tractor, Trailer and Stacker Machinery Manufacturin

9. (Agency Use) Offers will be received at the issuing office until the date and time specified below. Late offers are subject to late proposal provisions incorporated herein. All offers are subject to provisions, representations, certifications, and specifications as are attached or incorporated by reference.

5-JUN-2024 4:00PM

X

18.

SCHEDULE OF SUPPLIES/SERVICES

14. PAYMENT WILL BE MADE BY CODE

(SEE ESP CLAUSE 252.232-7003.)

X

7. ISSUED BY CODE

MOBILITY SUPPORT, AFLCMC/WNKAC

235 BYRON ST BLDG 300 STE 19A

ROBINS AFB GA 31098-1670

BUYER: Christopher A. Greene/WNKC christopher.greene.37@us.af.mil

X

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)SOLICITATION/CONTRACT

BIDDER/OFFEROR TO COMPLETE BLOCKS 11, 13, 15, 21, 22, & 27.

JL

STANDARD FORM 1447 (REV. 8/2016) BACK

NO RESPONSE FOR REASONS CHECKED

TYPE OR PRINT NAME AND TITLE OF SIGNER

SIGNATURENAME AND ADDRESS OF FIRM (Include Zip Code)

WE DO NOT DESIRE TO BE RETAINED ON THE MAILING LIST FOR FUTURE PROCUREMENT OF THE TYPE OF

ITEMS INVOLVED

WE DO

OTHER (Specify)

UNABLE TO IDENTIFY THE ITEM(S)

CANNOT COMPLY WITH SPECIFICATIONS CANNOT MEET DELIVERY REQUIREMENT

DO NOT REGULARILY MANUFACTURE OR SELL THE TYPE

OF ITEMS INVOLVED

DATE AND LOCAL TIME 5 JUN 2024 4:00 PM

SOLICITATION NUMBER FA853424R0008

FROM: AFFIX

STAMP

HERE

TO:

ATTN: Christophe A Greene/WNKC

MOBILITY SUPPORT, AFLCMC/WNKAC

235 BYRON ST BLDG 300 STE 19A

ROBINS AFB GA 31098-1670

FA8534-24-R-0008

PART I - THE SCHEDULE

SECTION B

SUPPLIES OR SERVICES AND PRICES/COSTS

(A) GENERAL:

This is a FixedPrice Incentive (Firm) Target (FP(I)F)/FirmFixedPrice (FFP) Indefinite Delivery Requirements Type contract for the issuance of orders in support of the Tunner Aircraft Cargo Loaders.

The contractor shall provide all parts, tools, labor, and materials necessary for this effort. Work accomplished in support of Aircraft Cargo Loaders shall be accomplished in accordance with the PerformanceBased Work Statement (PWS) attached hereto.

(B) BEST ESTIMATED QUANTITIES/COSTS (BEQ/BEC):

The required quantity is not known at this time. The quantities identified are Best Estimated Quantities (BEQs) and Best Estimated Costs based on the actual history and projected requirements. Any single order may be issued for quantities in excess of or less than the BEQ. The failure of the Government to order the BEQ/BEC will not entitle the contractor to an equitable adjustment in price under the contract.

(C) OPTIONS:

Each option may be exercised on or before the last day of the previous basic contract period or option period. An option is considered to have been exercised at the time the Government provides contract modification to the contractor via email.

(D) PERIOD OF PERFORMANCE:

The period of performance for this effort is five (5) years, consisting of a 1year Basic, and four (4) 1year annual options.

The first digit of each line item identifies the applicable period. Each order issued under this contract will use the following lineitem numbering sequence.

Basic Contract Period (12 months from date of contract award)

000X Year 1

Option I (12 months following the end of the Basic Contract Period)

10XX Year 2

Option II (12 months following the end of Option I)

2XXX Year 3

Option III (12 months following the end of Option II)

3XXX Year 4

Option IV (12 months following the end of Option III)

4XXX Year 5

*Should an effort ordered under this contract cross contract years, the CLIN cited on the order shall reflect the contract year in which the order was originally awarded.

(E) CEILING PRICE:

As noted in Schedule B, the ceiling price shall be 120% of Total Target Cost.

(F) RIGHT TO CANCEL:

The Government reserves the right to cancel this solicitation, either before or after the closing date. In the event the Government cancels the solicitation, the Government has no obligation to reimburse the offeror for any costs.

BASIC CONTRACT PERIOD: Effective date of contract award to twelve (12) months

Material Management (MM) Infrastructure

Item No.

Incentive Firm Target Quantity U/I Target Cost Target Profit Target Price

MO

Material Management (MM) Infrastructure In accordance with (IAW) Performance Based Work Statement (PWS) paragraph 4.5.4.

Ceiling Price = 120% of Target Cost = $

Limitations of Liability: Other Than High Value Item

Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

Material Management (MM) - Parts

Item No.

Incentive Firm Target

Material Management (MM) - Parts

Best Estimated Qty

U/I Unit Target Cost Unit Target Profit Unit Target Price

85,000 HR

Material Management (MM) - Parts IAW the attached PWS, paragraph 4.5.3.

Ceiling Price = 120% of Target Cost = $

Limitations of Liability: Other Than High Value Item

Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001-2015 31DEC2015

Definition of U/I: The Unit of Issue denoted above, Hours (HR), is hereby further defined as Operating Hours.

The Total Target Price is calculated based on the following: 85,000 Operating Hours x ** ** Price per Operating Hour

Program Engineering Support (PES)

Item No.

Incentive Firm Target Best Estimated Qty

U/I Unit Target Cost Unit Target Profit Total Target Price

12 MO

Program Engineering Support (PES) IAW the attached PWS, paragraph 4.6.

Ceiling Price = 120% of Target Cost = $

Limitations of Liability: Other Than High Value Item

Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

NOTE FOR CLIN 0004:

The ‘Estimated Total Price’ represents best estimated costs only and is based on the projected quantity of UDLMs per year. There is no presumption on the part of the contractor that the 'Estimated Total Price’ represents the total payment for the CLIN under a task order.

EACH task order issued for UDLM will be separately negotiated utilizing the loaded labor rates and material burden factor/s incorporated into the contract; only labor categories/hours and base material are subject to negotiation.

Loaded labor rates and material burden rates shall be proposed for CLIN 0004.

Unscheduled Depot Level Maintenance (UDLM)

Item No.

Firm Fixed Price Quantity U/I Estimated Total Price

1 LO $662,000.00

UDLM IAW the attached PWS, paragraph 4.7 and the unique PWS to be provided with each individual task order.

This contract line item is to be negotiated as FirmFixedPrice.

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: TBD Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001-2015 31DEC2015

NOTE FOR CLIN 0005:

The ‘Estimated Total Price’ represents best estimated costs only and is based on the projected quantity of CHPMSKs per year. There is no presumption on the part of the contractor that the 'Estimated Total Price’ represents the total payment for the CLIN under a task order.

EACH task/delivery order issued for CHPMSK will be separately negotiated.

Contingency High Priority Mission Support Kits (CHPMSK)

Item No.

Contingency High Priority Mission Support Kits (CHPMSK) IAW attached PWS, paragraph 4.5.4.1.2.

Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

CHPMSK30 Day Kit Tunner

Item No.

0005AA

Firm Fixed Price Best Estimated Qty

U/I Estimated Total Price

1 LO $81,218.00

CHPMSK30 Day Kit Part # 200499892

CHPMSK90 Day Kit Tunner

Item No.

0005AB

Firm Fixed Price Best Estimated Qty

U/I Estimated Total Price

1 LO $71,622.00

CHPMSK90 Day Kit Part # 200499890

Data

Item No.

Incentive Firm Target Quantity U/I Target Price 1 LO Not Separately Priced

Data IAW attached DD 1423s, ELINs A001 A021

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

Data

ISO 90012015 31DEC2015

Option I: If exercised, the prices in Option I will be effective upon the expiration of the Basic Contract Period for a duration of twelve (12) months. Option I may be exercised on or before the last effective date of the Basic Contract Period.

Material Management (MM) Infrastructure

Item No.

Incentive Firm Target Best Estimated Qty

U/I Unit Target Cost Unit Target Profit Target Price

12 MO

Material Management (MM) Infrastructure In accordance with (IAW) Performance Based Work Statement (PWS) paragraph 4.5.4.

Ceiling Price = 120% of Target Cost = $

Limitations of Liability: Other Than High Value Item

Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

Material Management (MM) Parts

Item No.

Incentive Firm Target Best Estimated Qty

U/I Unit Target Cost Unit Target Profit Unit Target Price

90,000 HR

Material Management (MM) Parts IAW the attached PWS, paragraph 4.5.3.

Ceiling Price = 120% of Target Cost = $

Limitations of Liability: Other Than High Value Item

Material Management (MM) Parts

Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

Definition of U/I: The Unit of Issue denoted above, Hours (HR), is hereby further defined as Operating Hours.

The Total Target Price is calculated based on the following: 90,000 Operating Hours x ** ** Price per Operating Hour

Program Engineering Support (PES)

Item No.

Incentive Firm Target Best Estimated Qty

U/I Unit Target Cost Unit Target Profit Total Target Price

12 MO

Program Engineering Support (PES) IAW the attached PWS, paragraph 4.6.

Ceiling Price = 120% of Target Cost = $

Limitations of Liability: Other Than High Value Item

Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

NOTE FOR CLIN 0004:

The ‘Estimated Total Price’ represents best estimated costs only and is based on the projected quantity of UDLMs per year. There is no presumption on the part of the contractor that the 'Estimated Total Price’ represents the total payment for the CLIN under a task order.

EACH task order issued for UDLM will be separately negotiated utilizing the loaded labor rates and material burden factor/s incorporated into the contract; only labor categories/hours and base material are subject to negotiation.

Loaded labor rates and material burden rates shall be proposed for CLIN 0004.

Unscheduled Depot Level Maintenance (UDLM)

Item No.

Firm Fixed Price Quantity U/I Estimated Total Price

1 LO $681,860.00

UDLM IAW the attached PWS, paragraph 4.7 and the unique PWS to be provided with each individual task order.

This contract line item is to be negotiated as FirmFixedPrice.

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: TBD Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

NOTE FOR CLIN 0005:

The ‘Estimated Total Price’ represents best estimated costs only and is based on the projected quantity of CHPMSKs per year. There is no presumption on the part of the contractor that the 'Estimated Total Price’ represents the total payment for the CLIN under a task order.

EACH task/delivery order issued for CHPMSK will be separately negotiated.

Contingency High Priority Mission Support Kits (CHPMSK)

Item No.

Contingency High Priority Mission Support Kits (CHPMSK) IAW attached PWS, paragraph 4.5.4.1.2.

Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

CHPMSK30 Day Kit Tunner

Item No.

1005AA

Firm Fixed Price Best Estimated Qty

U/I Estimated Total Price

1 LO $83,655.00

CHPMSK30 Day Kit Part # 200499892

CHPMSK90 Day Kit Tunner

Item No.

1005AB

Firm Fixed Price Best Estimated Qty

U/I Estimated Total Price

1 LO $73,771.00

CHPMSK90 Day Kit Part # 200499890

Data

Item No.

Incentive Firm Target Quantity U/I Target Price 1 LO Not Separately Priced

Data IAW attached DD 1423s, ELINs B001 B021

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: B Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

Option II: If exercised, the prices in Option II will be effective upon the expiration of the Option Year I Period for a duration of twelve (12) months. Option II may be exercised on or before the last effective date of Option Year I.

Material Management (MM) Infrastructure

Item No.

Incentive Firm Target Best Estimated Qty

U/I Unit Target Cost Unit Target Profit Target Price

12 MO

Material Management (MM) Infrastructure In accordance with (IAW) Performance Based Work Statement (PWS) paragraph 4.5.4.

Ceiling Price = 120% of Target Cost = $

Limitations of Liability: Other Than High Value Item

Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

Material Management (MM) Parts

Item No.

Incentive Firm Target Best Estimated Qty

U/I Unit Target Cost Unit Target Profit Unit Target Price

90,000 HR

Material Management (MM) Parts IAW the attached PWS, paragraph 4.5.3.

Ceiling Price = 120% of Target Cost = $

Limitations of Liability: Other Than High Value Item

Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

Definition of U/I: The Unit of Issue denoted above, Hours (HR), is hereby further defined as Operating Hours.

The Total Target Price is calculated based on the following: 90,000 Operating Hours x ** ** Price per Operating Hour

Program Engineering Support (PES)

Item No.

Incentive Firm Target Best Estimated Qty

U/I Unit Target Cost Unit Target Profit Total Target Price

12 MO

Program Engineering Support (PES) IAW the attached PWS, paragraph 4.6.

Ceiling Price = 120% of Target Cost = $

Limitations of Liability: Other Than High Value Item

Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

NOTE FOR CLIN 0004:

The ‘Estimated Total Price’ represents best estimated costs only and is based on the projected quantity of UDLMs per year. There is no presumption on the part of the contractor that the 'Estimated Total Price’ represents the total payment for the CLIN under a task order.

EACH task order issued for UDLM will be separately negotiated utilizing the loaded labor rates and material burden factor/s incorporated into the contract; only labor categories/hours and base material are subject to negotiation.

Loaded labor rates and material burden rates shall be proposed for CLIN 0004.

Unscheduled Depot Level Maintenance (UDLM)

Item No.

Firm Fixed Price Quantity U/I Estimated Total Price

1 LO $702,315.80

UDLM IAW the attached PWS, paragraph 4.7 and the unique PWS to be provided with each individual task order.

This contract line item is to be negotiated as FirmFixedPrice.

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: TBD Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

NOTE FOR CLIN 0005:

The ‘Estimated Total Price’ represents best estimated costs only and is based on the projected quantity of CHPMSKs per year. There is no presumption on the part of the contractor that the 'Estimated Total Price’ represents the total payment for the CLIN under a task order.

EACH task/delivery order issued for CHPMSK will be separately negotiated.

Contingency High Priority Mission Support Kits (CHPMSK)

Item No.

Contingency High Priority Mission Support Kits (CHPMSK) IAW attached PWS, paragraph 4.5.4.1.2.

Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

CHPMSK30 Day Kit Tunner

Item No.

2005AA

Firm Fixed Price Best Estimated Qty

U/I Estimated Total Price

1 LO $86,164.65

CHPMSK30 Day Kit Part # 200499892

CHPMSK90 Day Kit Tunner

Item No.

2005AB

Firm Fixed Price Best Estimated Qty

U/I Estimated Total Price

1 LO $75,984.13

CHPMSK90 Day Kit Part # 200499890

Data

Item No.

Incentive Firm Target Quantity U/I Target Price 1 LO Not Separately Priced

Data IAW attached DD 1423s, ELINs C001 C021

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: C Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

Option III: If exercised, the prices in Option III will be effective upon the expiration of the Option Year II Contract Period for a duration of twelve (12) months. Option III may be exercised on or before the last effective date of the Option II Contract Period.

Material Management (MM) Infrastructure

Item No.

Incentive Firm Target Best Estimated Qty

U/I Unit Target Cost Unit Target Profit Target Price

12 MO

Material Management (MM) Infrastructure In accordance with (IAW) Performance Based Work Statement (PWS) paragraph 4.5.4.

Material Management (MM) Infrastructure

Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

Material Management (MM) Parts

Item No.

Incentive Firm Target Best Estimated Qty

U/I Unit Target Cost Unit Target Profit Unit Target Price

90,000 HR

Material Management (MM) Parts IAW the attached PWS, paragraph 4.5.3.

Ceiling Price = 120% of Target Cost = $

Limitations of Liability: Other Than High Value Item

Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

Definition of U/I: The Unit of Issue denoted above, Hours (HR), is hereby further defined as Operating Hours.

The Total Target Price is calculated based on the following: 90,000 Operating Hours x ** ** Price per Operating Hour

Program Engineering Support (PES)

Item No.

Incentive Firm Target

Program Engineering Support (PES)

Best Estimated Qty

U/I Unit Target Cost Unit Target Profit Total Target Price

12 MO

Program Engineering Support (PES) IAW the attached PWS, paragraph 4.6.

Ceiling Price = 120% of Target Cost = $

Limitations of Liability: Other Than High Value Item

Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

NOTE FOR CLIN 0004:

The ‘Estimated Total Price’ represents best estimated costs only and is based on the projected quantity of UDLMs per year. There is no presumption on the part of the contractor that the 'Estimated Total Price’ represents the total payment for the CLIN under a task order.

EACH task order issued for UDLM will be separately negotiated utilizing the loaded labor rates and material burden factor/s incorporated into the contract; only labor categories/hours and base material are subject to negotiation.

Loaded labor rates and material burden rates shall be proposed for CLIN 0004.

Unscheduled Depot Level Maintenance (UDLM)

Item No.

Firm Fixed Price Quantity U/I Estimated Total Price

1 LO $723,385.27

UDLM IAW the attached PWS, paragraph 4.7 and the unique PWS to be provided with each individual task order.

This contract line item is to be negotiated as FirmFixedPrice.

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: TBD Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

NOTE FOR CLIN 0005:

The ‘Estimated Total Price’ represents best estimated costs only and is based on the projected quantity of CHPMSKs per year. There is no presumption on the part of the contractor that the 'Estimated Total Price’ represents the total payment for the CLIN under a task order.

EACH task/delivery order issued for CHPMSK will be separately negotiated.

Contingency High Priority Mission Support Kits (CHPMSK)

Item No.

Contingency High Priority Mission Support Kits (CHPMSK) IAW attached PWS, paragraph 4.5.4.1.2.

Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

CHPMSK30 Day Kit Tunner

Item No.

3005AA

Firm Fixed Price Best Estimated Qty

U/I Estimated Total Price

1 LO $88,749.58

CHPMSK30 Day Kit Part # 200499892

CHPMSK90 Day Kit Tunner

Item No.

3005AB

Firm Fixed Price Best Estimated Qty

U/I Estimated Total Price

CHPMSK90 Day Kit Tunner

1 LO $78,263.65

CHPMSK90 Day Kit Part # 200499890

Data

Item No.

Incentive Firm Target Quantity U/I Target Price 1 LO Not Separately Priced

Data IAW attached DD 1423s, ELINs D001 D021

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: D Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

Option IV: If exercised, the prices in Option IV will be effective upon the expiration of the Option III Contract Period for a duration of twelve (12) months. Option IV may be exercised on or before the last effective date of the Option III Contract Period.

Material Management (MM) Infrastructure

Item No.

Incentive Firm Target Best Estimated Qty

U/I Unit Target Cost Unit Target Profit Target Price

12 MO

Material Management (MM) Infrastructure In accordance with (IAW) Performance Based Work Statement (PWS) paragraph 4.5.4.

Ceiling Price = 120% of Target Cost = $

Limitations of Liability: Other Than High Value Item

Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Material Management (MM) Infrastructure

Title Number Date Tailoring

ISO 90012015 31DEC2015

Material Management (MM) Parts

Item No.

Incentive Firm Target Best Estimated Qty

U/I Unit Target Cost Unit Target Profit Unit Target Price

90,000 HR

Material Management (MM) Parts IAW the attached PWS, paragraph 4.5.3.

Ceiling Price = 120% of Target Cost = $

Limitations of Liability: Other Than High Value Item

Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

Definition of U/I: The Unit of Issue denoted above, Hours (HR), is hereby further defined as Operating Hours.

The Total Target Price is calculated based on the following: 90,000 Operating Hours x ** ** Price per Operating Hour

Program Engineering Support (PES)

Item No.

Incentive Firm Target Best Estimated Qty

U/I Unit Target Cost Unit Target Profit Total Target Price

12 MO

Program Engineering Support (PES) IAW the attached PWS, paragraph 4.6.

Program Engineering Support (PES)

Limitations of Liability: Other Than High Value Item

Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

NOTE FOR CLIN 0004:

The ‘Estimated Total Price’ represents best estimated costs only and is based on the projected quantity of UDLMs per year. There is no presumption on the part of the contractor that the 'Estimated Total Price’ represents the total payment for the CLIN under a task order.

EACH task order issued for UDLM will be separately negotiated utilizing the loaded labor rates and material burden factor/s incorporated into the contract; only labor categories/hours and base material are subject to negotiation.

Loaded labor rates and material burden rates shall be proposed for CLIN 0004.

Unscheduled Depot Level Maintenance (UDLM)

Item No.

Firm Fixed Price Quantity U/I Estimated Total Price

1 LO $745,086.82

UDLM IAW the attached PWS, paragraph 4.7 and the unique PWS to be provided with each individual task order.

This contract line item is to be negotiated as FirmFixedPrice.

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: TBD Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

NOTE FOR CLIN 0005:

The ‘Estimated Total Price’ represents best estimated costs only and is based on the projected quantity of CHPMSKs per year. There is no presumption on the part of the contractor that the 'Estimated Total Price’ represents the total payment for the CLIN under a task order.

EACH task/delivery order issued for CHPMSK will be separately negotiated.

Contingency High Priority Mission Support Kits (CHPMSK)

Item No.

Contingency High Priority Mission Support Kits (CHPMSK) IAW attached PWS, paragraph 4.5.4.1.2.

Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

CHPMSK30 Day Kit Tunner

Item No.

4005AA

Firm Fixed Price Best Estimated Qty

U/I Estimated Total Price

1 LO $91,412.06

CHPMSK30 Day Kit Part # 200499892

CHPMSK90 Day Kit Tunner

Item No.

4005AB

Firm Fixed Price Best Estimated Qty

U/I Estimated Total Price

1 LO $80,611.56

CHPMSK90 Day Kit Part # 200499890

Data

Item No.

Incentive Firm Target Quantity U/I Target Price 1 LO Not Separately Priced

Data IAW attached DD 1423s, ELINs E001 E021

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: E Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 90012015 31DEC2015

DATA

Item No.

A001

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 0006

DATA

Conference Agenda

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

Proposed Delivery

DATA

+ IAW1423 1 LO

DATA

Item No.

A002

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 0006

DATA

Contract Work Breakdown Structure (CWBS)

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

Proposed Delivery

+ IAW1423 1 LO

DATA

Item No.

A003

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 0006

DATA

Integrated Program Managment Data and Analysis Report (IPMDAR)

DATA

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

Proposed Delivery

+ IAW1423 1 LO

DATA

Item No.

A004

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 0006

DATA

Contract Funds Status Report (CFSR)

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

DATA

+ IAW1423 1 LO

DATA

Item No.

A005

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 0006

DATA

Conference Minutes

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

Proposed Delivery

+ IAW1423 1 LO

DATA

Item No.

A006

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 0006

DATA

Configuration Audit Summary Report (CASR)

DATA

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

Proposed Delivery

+ IAW1423 1 LO

DATA

Item No.

A007

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 0006

DATA

Notice of Revision (NOR)

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

DATA

+ IAW1423 1 LO

DATA

Item No.

A008

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 0006

DATA

Engineering Change Proposal (ECP)

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

Proposed Delivery

+ IAW1423 1 LO

DATA

Item No.

A009

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 0006

DATA

Contract Summary Report (Finite Element Analysis)

DATA

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

Proposed Delivery

+ IAW1423 1 LO

DATA

Item No.

A010

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 0006

DATA

Technical Manual Contract Requirement (TMCR)

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

DATA

+ IAW1423 1 LO

DATA

Item No.

A011

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 0006

DATA

Product Drawings/Models and Associated Lists

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

Proposed Delivery

+ IAW1423 1 LO

DATA

Item No.

A012

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 0006

DATA

Systems Engineering Plan (SEP)

DATA

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

Proposed Delivery

+ IAW1423 1 LO

DATA

Item No.

A013

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 0006

DATA

Configuration Management Plan (CMP)

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

DATA

+ IAW1423 1 LO

DATA

Item No.

A014

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 0006

DATA

IUID Marking Plan

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

Proposed Delivery

+ IAW1423 1 LO

DATA

Item No.

A015

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 0006

DATA

Corrosion Prevention and Control Plan (CPCP)

DATA

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

Proposed Delivery

+ IAW1423 1 LO

DATA

Item No.

A016

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 0006

DATA

Accident/Incident Report

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

DATA

+ IAW1423 1 LO

DATA

Item No.

A017

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 0006

DATA

Quality Assurance Program Plan (QAPP)

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

Proposed Delivery

+ IAW1423 1 LO

DATA

Item No.

A018

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 0006

DATA

Safety Assessment Report (SAR)

DATA

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

Proposed Delivery

+ IAW1423 1 LO

DATA

Item No.

A019

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 0006

DATA

Technical Report/Study Services

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

DATA

+ IAW1423 1 LO

DATA

Item No.

A020

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 0006

DATA

Computer Program Identification Number (CPIN) Catalog Information

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

Proposed Delivery

+ IAW1423 1 LO

DATA

Item No.

A021

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 0006

DATA

Computer Software Product (CSP) End Items

DATA

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: A Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

Proposed Delivery

+ IAW1423 1 LO

DATA

Item No.

B001

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 1006

DATA

Conference Agenda

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: B Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

DATA

+ IAW1423 1 LO

DATA

Item No.

B002

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 1006

DATA

Contract Work Breakdown Structure (CWBS)

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: B Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

Proposed Delivery

+ IAW1423 1 LO

DATA

Item No.

B003

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 1006

DATA

DATA

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: B Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

Proposed Delivery

+ IAW1423 1 LO

DATA

Item No.

B004

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 1006

DATA

Contract Funds Status Report (CFSR)

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: B Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

DATA

+ IAW1423 1 LO

DATA

Item No.

B005

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 1006

DATA

Conference Minutes

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: B Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

Proposed Delivery

+ IAW1423 1 LO

DATA

Item No.

B006

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 1006

DATA

DATA

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: B Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

Proposed Delivery

+ IAW1423 1 LO

DATA

Item No.

B007

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 1006

DATA

Notice of Revision (NOR)

Limitations of Liability: Other Than High Value Item

Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Exhibit: B Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)

Title Number Date Tailoring

ISO 9001:2015 31DEC2015

Type / Ship To Quantity (U/I) *ARO IAW DD1423 _ Req No / Pri

Required Delivery

+ IAW1423 1 LO

DATA

+ IAW1423 1 LO

DATA

Item No.

B008

Not Separately Priced Quantity U/I Unit Price

1 LO NSP

DATA

Associated with LI: 1006

DATA

Engineering Change Proposal (ECP)

Limitations of Liability: Other Than High Value Item

Inspection: Destination…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .