Questions_and_Answers_20_Jan_2016.docx

DOCX document 19 KB Posted

Attached to
Pest Control and Mechanical Cleaning Federal contract opportunity
Solicitation number
FA8224-16-R-0042
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

View the file

Other files for this federal contract opportunity

Other files attached to Pest Control and Mechanical Cleaning, newest first.
File Type Posted
Questions_and_Answers_01_Feb_2016.pdf PDF
RevQuestions_and_Answers_20_Jan_2016.pdf PDF
Performance_Work_Statement_Rev_1.pdf PDF
Working_Rodent_Control_PWS_20_Jan_2016_redline_version.docx DOCX document
FA8224-16-R-0042_0001.pdf PDF
CDRL_A001_A002.pdf PDF
CDRL_A003_A004.pdf PDF
FA8224-16-R-0042.pdf PDF
Performance_Work_Statment.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions on PWS dated 10 Sept 2015 from Solicitation Number FA8224-16-R-0042.

1. Paragraph 1.1 requires spaying for spiders. A pesticide is required to perform this requirement. Pesticide reporting is not outlined in the PWS paragraphs 1.1.2.1, 1.1.2.2, and 1.1.2.3 Reporting requirements for rodenticides are covered but not pesticides.

· Answer – Remove spray and replace with manually remove insect etc.

2. Paragraph 2. Service Summary SS#2 requires the reporting of pesticides but not rodenticides. SS#3 requires furnishing rodenticide labeling but not pesticide labeling.

· Answer – By removing spray in PWS no need for pesticides.

3. Appendix E. has no list for DOD approved pesticides, only rodenticides.

· Answer – No need for pesticides.

4. Paragraph 1.1.1 states cleaning requirements. Is there a cleaning requirement for walls if so how high will this cleaning go?

· Answer – Nothing over 10 feet in accordance with IAW PWS para. 1.2.2.

5. Paragraph 1.1.1 requires the cleaning on the inside of compressors, Heating, Ventilation and Air Conditioning (HVAC) systems, etc. However, Paragraph 1.1.5 states the Contractor shall not open any electric panel boxes, air handling units (AHUs), compressors, air conditioners A/C and heating units within any facility. I see this as a conflict as to what to clean.

· Answer – Just the areas outside of these units.

6. Paragraph 1.1.2 states, The Contractor shall replace the poison, reset traps, remove carcasses and perform mechanical cleaning every three months (once a quarter). Appendix B: Historical Workload Data page 21 outlines Cleaning on the 1st and 3rd quarters and rodent control every quarter. Is facility cleaning every quarter or 1st and 3rd quarter?

· Answer – Only 1st and 3rd quarter’s facilities will be clean.

7. Paragraph 4.7 Hours of Operation. Does Missile Transportation work every other Friday? If so can that Friday be used as a work day?

· Answer – Missile Transportation still working 5-4-9 shifts, 0630 to 1600 hrs. Only work every other Friday.

8. In your HISTORICAL WORKLOAD Service chart, the Quantity list is the number of building visited/cleaned during the quarter?

· Answer – Yes

9. Does the contractor have to develop a schedule as to which buildings are going to be visited and when as part of the proposal?

· Answer – No

10. What is the current contractor's price?

· Answer – the Air Force is currently completing this work internally

11. Do you remember how high the highest interior is?

· Answer – Nothing over 10 feet in accordance with IAW PWS para. 1.2.2.