Rework_and_repair_of_nonconforming_materials.pdf
PDF 184 KB Posted
- Attached to
- SMDC/GAS INITIATOR
- Solicitation number
- FA8213-20-R-3027
About this file
This solicitation seeks production and testing of initiators and associated data. Key requirements include the delivery of first article test plans within 30 days of award, completion of first article testing within 120 days of test plan approval, and delivery of 260 production articles to Tinker Air Force Base no later than May 31, 2021. The solicitation involves three line items for different initiator parts and includes provisions for first article testing and production quantities under the Department of the Air Force Materiel Command Lifecycle Management Center at Hill Air Force Base.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| JFQR_Justification_for_Qualification_Requirements.pdf | ||
| Quality_QALI.pdf | ||
| CDRL_DD1423.pdf | ||
| SPI_NSN_8510ES.pdf | ||
| SOW_Packaging.pdf | ||
| SPI_NSN_8061ES.pdf | ||
| SPI_NSN_9273ES.pdf | ||
| CADPAD_Item_Marking_Instruction.pdf | ||
| RFP FA821320R3027.pdf | ||
| SOW_Ammunition_Data_Cards.pdf | ||
| Item_Descriptions.pdf | ||
| Air_Munition_Specifications.pdf | ||
| REPSHIP.pdf | ||
| EDLs.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 5
(ES7034)
REWORK AND REPAIR OF NONCONFORMING MATERIAL
Jan 2012 (version)
(a) Rework and Repair are defined as follows:
(1) Rework - The reprocessing of nonconforming material to make it conform completely to the drawings, specifications or contract requirements.
(2) Repair - The reprocessing of nonconforming material in accordance with approved written procedures and operations to reduce, but not completely eliminate, the nonconformance. The purpose of repair is to bring nonconforming material into a usable condition. Repair is distinguished from rework in that the item after repair still does not completely conform to all of the applicable drawings, specifications or contract requirements.
(b) Rework procedures along with the associated inspection procedures shall be documented by the Contractor and submitted to the Government Quality Assurance Representative (QAR) for review prior to implementation. Rework procedures are subject to the QAR's disapproval.
(c) Repair procedures shall be documented by the Contractor and submitted on a Request for
Deviation/Waiver, DD Form 1694, to the Contracting Officer for review and written approval prior to implementation.
(d) Whenever the Contractor submits a repair or rework procedure for Government review, the submission shall also include a description of the cause for the nonconformances and a description of the action taken or to be taken to prevent recurrence.
(e) The rework or repair procedure shall also contain a provision for reinspection which will take precedence over the Technical Data Package requirements and shall, in addition, provide the
Government assurance that the reworked or repaired items have met reprocessing requirements.
(f) Rework and repair is a supply chain flow-down requirement that applies to contractors and their suppliers, vendors or subcontractors.