AirSpec.pdf

PDF 361 KB Posted

Attached to
Canopy Actuated Release Bolt Federal contract opportunity
Solicitation number
FA821319R3026
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

About this file

AirSpec

View the file

Other files for this federal contract opportunity

Other files attached to Canopy Actuated Release Bolt, newest first.
File Type Posted
FA821319R3026.pdf PDF
CDRLs.pdf PDF
PackReq.pdf PDF
CADPADIMI19Apr2016.pdf PDF
F010855974.pdf PDF
ES7034.pdf PDF
EDL.pdf PDF
REPSHIP.pdf PDF
QALI.pdf PDF
JQRS.pdf PDF
ID.pdf PDF
ADCSOW.doc DOC document
SOW.pdf PDF
BidSets.doc DOC document
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1/25/2019

AIRMUNITION SPECIFICATION

(version 15 Jun, 2016)

FD2020-19-50015 USAF, FD2020-19-50016 FMS

NSN: 1377-01-085-5974ES, alt. 1377-01-461-9131ES

1. The contractor shall provide an advanced Report of Shipment (REPSHIP) to the consignee no later than 24 hours prior to the shipment arrival, and for ammunition shipments no later than two hours after shipment departure. A (REPSHIP) shall include all the following data in accordance with Attached REPSHIP.

2. Contractor shall contact their nearest Defense Contract Management Agency (DCMA) Office for transportation guidance and assistance for all Foreign Military Sales (FMS) deliveries prior to shipment; and ensure that the DCMA provides one information copy of completed Notice of

Availability (NOA) including FMS case and requisition numbers by mail to:

AFLCMC/EBHMB Attn: FMS Transportation 6043 Elm Lane, Hill AFB, UT 84056-5819, or

Fax to: (801) 777-1089 or Email to ooalc.gacp.transportation@us.af.mil.

3. Department of Defense Identification Code (DODIC): SP87

4. Ammunition Data Cards (ADC) shall be filled out; input in accordance with Attachment 2, Statement of Work – Ammunition Data Cards; and state quantity/serial number of lot acceptance test units in the remarks block. One hard copy of the ADC shall accompany shipments to each shipping location. CDRL (DI-MISC-80043)

5. Items shall be marked in accordance with CAD/PAD Item Marking Instruction Version 1.3, 19

Apr 2016, reference attachment.

6. Shelf Life Code marking NOT required per MIL-STD-129.

7. Hazard Classification Information:

Hazard Class/Division: 1.4

Compatibility Group: S

DOT Marking/EX Number: EX1988080340, EX1988080340A

DOT Shipping Labels: EXPLOSIVE 1.4S

UN Serial No.: 0173

Proper Shipping Name: RELEASE DEVICES, EXPLOSIVE

Net Explosive Weight per item (NEW): 0.0017

NEW Unit of Measurement: pounds

NEW for all packaging/shipping documents shall reflect the NEW identified above per JHCS or

IHC. . If NEW is altered to adjust item performance and is greater than the weight listed, an

ECP shall be submitted to the government prior to manufacturing or at least 60 days prior to shipping and shall include the SDS (formerly MSDS) and applicable supporting documentation.

mailto:ooalc.gacp.transportation@us.af.mil

8. All Engineering Change Proposals (ECPs), Notice of Revisions (NORs), and Request For

Variances (RFVs formerly RFD/RFWs) affecting the approved product baseline configuration, acceptance test procedures, or manufacturing process of any item(s) on this contract shall be in accordance with EIA-649-B. Major ECPs with NORs and Critical/Major RFVs shall be submitted to the responsible Government Engineering Authority for review/disposition by CCB.

Minor/Administrative ECPs with NORs and Minor RFVs shall be processed by the:

COGNIZANT GOVERNMENT ENGINEER

ECPs -- CDRL (DI-SESS-80639D)

NORs – CDRL (DI-SESS-80642D)

RFVs – CDRL (DI-SESS-80640D)

Distribution Statement: B, Reason: Administrative or Operational (ref. DoD 5230.24)

9. The contractor shall provide the Lot Acceptance Test Plan (LATP/ATP) for this item(s) in accordance with the contractual data requirements. No changes to previously approved government Acceptance Test Plans shall be made without prior government approval. The Lot

Acceptance Test Plan provided must be approved by HAFB engineering at least 90 days prior to commencement of Lot Acceptance Testing allowing for 30 days approval time after submission.

CDRL (DI-QCIC-80553A)

10. Electronic Systems to encompass system, subsystem, pieces parts and assemblies shall not contain any substitutes for Tin-Lead solder and finishes. The use of any Tin-Lead solder substitutes requires approval through PCO and cognizant engineer, REFERENCE:

:Airworthiness Advisory (AA-08-02) Lead-Free Electronics: and GEIA-STD-0005-1 & 2.

11. Lot Acceptance Test Requirements are IAW latest Government approved ATP: Contractor.

12. The contractor shall furnish a Lot Acceptance Test/Inspection Report in the WAWF system.

CDRL: (DI-NDTI-80809B)

13. LOT ACCEPTANCE TEST: In the event of an end item failure, the contractor shall notify the

PCO/ACO and Air Force Engineering Organization within 1 business day.

Air Force Engineering Organization: AFLCMC/EBHJ

Organization E-mail: Quinn.Tidwell@us.af.mil

14. In the event of test failure(s), a Failure Analysis and Corrective Action Report with proposed corrective actions/recommendations is required. CDRL: (DI-SESS-80255A)

15. If Hexanitrostilbene (HNS) explosive material is used in the manufacture of this item, the HNS shall meet the requirements of Government Document WS5003F (or latest revision), Purchase

Description of HNS Explosive; and maximum particle size shall not exceed 250 microns.

16. The age of the energetic materials and components (i.e. ALL explosives, propellants, pyrotechnics, cartridges, and/or initiators) used in the manufacture of these items or sub-components shall not exceed 24 months based on the original manufacturing date. All energetic materials and components must be traceable to the original DoD qualified manufacturer and compliant with the ITAR part 120 and 121

(http://www.pmddtc.state.gov/regulations_laws/itar.html).

17. Raw (non-blended) ingredients & materials used in blended/mixed energetic materials such as, but not limited to: fuels, oxidizers, binders, curatives, sensitizers, plasticizers, stabilizers etc., shall not exceed 24 months since date of manufacture and comply with original manufacture’s

Specification or MIL-STD. The government may waive the energetic and constituent material requirements listed above or portions thereof, on a case-by-case basis (when acceptable to the government) provided the contractor furnishes all details of the reason for the waiver and the age, lot numbers, traceability, and other pertinent information/ test data and Certificate of

Analysis/ Conformance (COA/COC) of the subject materials or components. The waiver shall be submitted as a RFV and may be subject to, but not limited to, conditions such as sensitivity testing, stabilizer and analysis and/or dehumidification at vendor’s cost; therefore, vendor must plan accordingly. RFV not required provided vendor has approved energetic material and constituent management and recertification plan approved by HAFB technical authority for this specific contract and contract is executed with materials in compliance with said plan.

Recertification test data for materials shall be provided by vendor upon request at no additional charge to the government. All raw ingredients, materials and components must be traceable to the original DoD qualified manufacturer and compliant with the ITAR part 120 and 121.

18. This item is designated as a Critical Safety Item (CSI). Documentation for critical characteristics may be found in the contract, TDP, assembly/inspection procedures or QALI.

MRB approval authority shall be retained by government engineer.

19. Approval from government engineer is required prior to rework and repair of nonconforming material (see Attachment ES7034)

20. Vendor shall submit a bill of Materials (BOM) for Diminishing Manufacturing Sources and

Material Shortages (MDSMS) Management. CDRL (DI-PSSS-81656B)

21. Contracts involving ammunition and explosives (AE) will contain:

- DFARS Title 48 Part 252.223-7002, Safety Precautions for Ammunition and Explosives

- DFARS Title 48 Part 252.223-7003, Change in Place of Performance - Ammunition and

Explosives

Additionally, if the scope of work includes air shipment of explosives, the safety specification should require contractor compliance with:

- AFMAN 24-204(I), Preparing Hazardous Materials for Military Air Shipments http://www.pmddtc.state.gov/regulations_laws/itar.html

File details come from the government source that posted it.