A-10 OBOGS A-Kits Federal contract opportunity
Solicitation number
FA8202-18-R-1003
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

About this file

Statement of Work

View the file

Other files for this federal contract opportunity

Other files attached to A-10 OBOGS A-Kits, newest first.
File Type Posted
FA820218R1003_______0002.pdf PDF
Question_and_Answers_OBOGS_A.docx DOCX document
FA820218R1003_______0001.pdf PDF
SECTION_L.pdf PDF
SECTION_M.pdf PDF
SECTION_L.pdf PDF
FA820218R1003.pdf PDF
SOW_Atch_1_OBOGS_A_Kits_Drawing_Parts_List.pdf PDF
SECTION_M.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AIR FORCE LIFE CYCLE MANAGEMENT CENTER

(AFLCMC)

A-10 DIVISION (WWA)

HILL AIR FORCE BASE, UTAH

STATEMENT OF WORK (SOW)

for

A-10 Onboard Oxygen Generating System

(OBOGS)

Group A Kit Assemblies

05 JUN 2018 REV 5.

Prepared by:

A-10 Division

Ogden Air Logistics Complex Hill Air Force Base, Utah, 84056

REVISION CONTROL

Revision Date Description Pages

11 July 2017 Initial Release 4 1 14 November 2017 Rev 1 4 2 19 April 2018 Rev 2 4

3 25 April 2018 Rev 3 4

4 23 May 2018 Rev 4 4

5 05 June 2018 Rev 5 4

Table of Contents

1. Scope

2. Applicability

3. Background

4. Program Objectives

5. Period of Performance ........................................ Error! Bookmark not defined.

6. Supply Point:

7. Packaging, Marking and Shipping

8. Definitions

9. Attachments

1. Scope

This Statement of Work (SOW) establishes the Contractor activities required to support efforts to integrate the Onboard Oxygen Generating System (OBOGS) on the A-10. The scope of this SOW is to deliver two hundred twenty eight (228) OBOGS Group A kit assemblies.

2. Applicability

A/OA-10C

3. Background

The purpose is to retrofit the A-10 aircraft by removing the present liquid oxygen system and installing the OBOGS. Due to its cryogenic nature, liquid oxygen systems require special handling precautions which adversely impact maintenance costs and increase downtime between sorties. The OBOGS mitigates the constraints of liquid oxygen by utilizing engine bleed air as the source of breathing oxygen and eliminates the maintenance costs and sortie delays the liquid oxygen system incurs.

4. Program Objectives

The primary objectives of the tasks provided within this SOW are:

a. Contractor shall deliver complete sets of Group A kits to the location specified in paragraph six (6) below.

b. Contractor shall manufacture OBOGS Group A kit per specifications contained in the following drawing package:

See Drawings provided on CD and the drawings parts list attached to this SOW. Requests for CD shall be submitted through contracting. To obtain the CD a valid form DD 2345 must be provided to contracting. If contractor does not have a valid form DD 2345, instructions on how to obtain a DD 2345 form are listed in the Section L and M.

5. Delivery Schedule

The contractor shall deliver the initial quantity of sixty four (64) OBOGS A kit assemblies no later than 12 months after receipt of (ARO) contract. All other deliveries shall be within 12 months of additional quantity award.

6. Supply Point:

All OBOGS A kit assemblies are to be shipped to:

FB2029

DDHU Hill Facility Central Receiving, Bldg 849 W 5851 F Ave Hill AFB UT 84056-5713

Mark For: Stock

(Make sure the Kit NSN is put on the packaging)

7. Packaging, Marking and Shipping

Each Group A kit must be shipped as a ship-set (A-10 OBOGS A-Kit). Each ship-set will be clearly marked with kit number 1560K0106065CFJ. See the attached parts lists for items to be in included in each kit.

The contractor shall package and ship using MIL-STD-2073-1E, Standard Practice for Military Packaging.

DoD documents:

A. MIL-STD-130N, 16 Nov 2012 Identification Marking of U.S. Military Property B. MIL-STD-2073-1E, 7 Jan 2011 Standard Practice for Military Packaging

Shipping shall be F.O.B. Destination. The contractor shall be responsible for all associated shipping costs for delivery to the government facility. Shipping costs are to be included in the price of each kit.

8. Definitions

Component. An item below the assembly level that may be repairable or non-repairable.

Data: Information generated for the requirements listed in the Data Item Description

(DID).

End Item: An item having all accessories and components comprising a piece of equipment and suitable for Government storage and issue.

Military Standard: used to help achieve standardization objectives by the U.S.

Department of Defense.

Ship-set: the full complement of what is needed to complete a kit assembly

NSL: not stock listed