Question_and_Answers_OBOGS_A.docx

DOCX document 12 KB Posted

Attached to
A-10 OBOGS A-Kits Federal contract opportunity
Solicitation number
FA8202-18-R-1003
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

About this file

Q&A

View the file

Other files for this federal contract opportunity

Other files attached to A-10 OBOGS A-Kits, newest first.
File Type Posted
FA820218R1003_______0002.pdf PDF
SECTION_M.pdf PDF
FA820218R1003_______0001.pdf PDF
SECTION_L.pdf PDF
SOW_OBOGS_Group_A_kits.pdf PDF
SECTION_L.pdf PDF
FA820218R1003.pdf PDF
SOW_Atch_1_OBOGS_A_Kits_Drawing_Parts_List.pdf PDF
SECTION_M.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question and Answers OBOGS A-Kits

1. Is there a schedule or plan by year for the remaining quantity beyond the initial 64?

- There is no schedule on the remaining qty after the initial 64. The intent is to issue a task order if and when there is funding available for additional OBOGS kits.

2. Page 3 of 27 references a minimum order of 64 units however FAR 52.216-19 states a minimum order of "quantity of 1"

- The minimum order guarantee will be 64 units for the entire IDIQ contract which will be placed with the first task order. The minimum order under FAR52.216-19 is the minimum order (1 ea) we will place under each additional task order.

3. There is no Best Estimated Quantity (BEQ) identified in the solicitation for evaluation purposes. Does the Government intend to identify a BEQ? - There is not a BEQ for additional orders for OBOGS kits beyond the minimum order guarantee of 64 kits.

4. Section M, Factor 2 - Price Proposal states "Cost/Price Evaluation: The offeror's cost/price proposal, Section B, will be evaluated for award purposes by adding the total price for the basic requirements (basic award)". Can you explain what that means? Is that referring to a quantity of 64 as that is the minimum and first order?

- This section needs to be clarified. The intent is to obtain a total evaluated price for the total possible quantity (228).

5. There is only one CLIN in the solicitation but the ordering period spans 5 years. Will a CLIN per year be accommodated to account for unit pricing fluctuation by year?

- Yes, this was an oversight and an RFP amendment will be forthcoming which includes CLINs for each of the 5 year ordering period.

Additionally we will extend the RFP out until 31 July, which is the longest we can extend this RFP in order to allow sufficient time for evaluations and award prior to end of the fiscal year.