Specifications_Building_680_KRSM_152043.pdf
PDF 4 MB Posted
- Attached to
- Bldg. 680 Construct Classroom Addition Federal contract opportunity
- Solicitation number
- FA8201-16-B-0003
About this file
Specifications KRSM152043
View the file
Other files for this federal contract opportunity
Show all 41
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COVER SHEET
for
HILL AIR FORCE BASE
TRAINING CLASSROOM ADDITION
BUILDING 680
SPECIFICATIONS
Date: 26-February-2016
INSTALLATION: HILL AIR FORCE BASE, UTAH
JOB TITLE: TRAINING CLASSROOM ADDITION BUILDING 680
PROJECT NUMBER: KRSM 152043 WO#58149
GSBS PROJECT 2012.079.09
DOCUMENT SPECIFICATIONS
DESCRIPTION:
REMARKS: PROJECT MANAGER: ROBERT MILLER
KRSM 152043 (wo#58149) Training Classroom Addition HAFB, UT Building 680
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 GENERAL REQUIREMENTS
01 32 00 PROJECT SCHEDULE
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 57 20 ENVIRONMENTAL PROTECTION
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION AND DECONSTRUCTION
DIVISION 03 - CONCRETE
03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING
03 15 00.00 10 CONCRETE ACCESSORIES
03 20 00.00 10 CONCRETE REINFORCING
03 30 00.00 10 CAST-IN-PLACE CONCRETE
03 31 01.00 10 CAST-IN-PLACE CONCRETE FOR CIVIL WORKS
03 35 00.00 10 CONCRETE FINISHING
03 39 00.00 10 CONCRETE CURING
DIVISION 04 - MASONRY
04 20 00 MASONRY
DIVISION 05 - METALS
05 05 23.13 10 ULTRASONIC INSPECTION OF WELDMENTS
05 05 23.16 STRUCTURAL WELDING
05 12 00 STRUCTURAL STEEL
05 30 00 STEEL DECKS
05 40 00 COLD-FORMED METAL FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 60 00 FLASHING AND SHEET METAL
07 61 14.00 20 STEEL PANEL SOFFITS AND STANDING SEAM ROOFING
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 16 ALUMINUM DOORS AND FRAMES
08 14 00 WOOD DOORS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
DIVISION 09 - FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
PROJECT TABLE OF CONTENTS Page 1
09 30 00 CERAMIC TILE
09 51 00 ACOUSTICAL CEILINGS
09 65 00 RESILIENT FLOORING
09 90 00 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 14 02 INTERIOR SIGNAGE
10 22 26.13 ACCORDION FOLDING PARTITIONS
10 26 13 CORNER GUARDS
10 44 16 FIRE EXTINGUISHERS
DIVISION 12 - FURNISHINGS
12 24 13 ROLLER WINDOW SHADES
12 48 13.13 ENTRANCE FLOOR MATS
DIVISION 21 - FIRE SUPPRESSION
21 13 13 FIRE SPRINKLER SYSTEMS
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 48 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND
EQUIPMENT
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 11 25 FACILITY GAS PIPING
23 82 01.00 10 WARM AIR HEATING SYSTEMS
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL
26 20 00 INTERIOR DISTRIBUTION SYSTEM
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 FIRE ALARM SYSTEM
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 11 00 CLEARING AND GRUBBING
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS
PROJECT TABLE OF CONTENTS Page 2
DIVISION 33 - UTILITIES
33 40 00 STORM DRAINAGE UTILITIES
33 51 15 NATURAL-GAS DISTRIBUTION
APPENDIX A - AMERICAN WATER SPECIFICATIONS
03 48 20 VALVE BOXES AND METER VAULTS
22 11 16.11 WATER TAP AND SERVICE INSTALLATION
33 01 10.13 PRESSURE AND LEAKAGE TESTS
33 01 10.15 DISINFECTING PIPE
33 05 27 TRACER WIRE (GENERAL)
33 11 00 PIPING - GENERAL PROVISIONS
33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE
33 11 00.15 DUCTILE IRON PIPE & FITTINGS
33 11 00.17 POLYETHYLENE WRAP
33 11 00.19 ABANDONMENT OF WATER MAINS
33 12 16.11 GATE VALVES
33 12 19 FIRE HYDRANTS
33 31 00.15 SANITARY SEWER LATERALS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 3
Section 01 00 00 Page 1
SECTION 01 00 00
GENERAL REQUIREMENTS
4/13
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.3 SUBMITTALS
1.4 WORK COVERED BY CONTRACT DOCUMENTS
1.4.1 Materials and Workmanship
1.4.2 Weather Precautions
1.4.3 Project Description
1.4.4 Project Location
1.5 SITE VISITS
1.6 CONTRACT DRAWINGS
1.6.1 Project Drawings
1.6.2 Working Drawings
1.6.3 Shop Drawings
1.6.4 As-Built Record Drawings
1.7 WORK SCHEDULING
1.8 OCCUPANCY OF PREMISES
1.9 PROTECTION OF EXISTING GOVERNMENT PROPERTY AND EXISTING WORK
1.10 ON-SITE PERMITS
1.10.1 Excavation Permits
1.10.2 Utility Outage Requests.
1.10.3 Utility Connection Requests
1.10.4 Burning Permits
1.10.5 Welding, Cutting and Brazing Permits
1.10.6 Street Closures
1.11 SAFETY
1.12 ENVIRONMENTAL PROTECTION
1.13 SALVAGE MATERIAL AND WORKSITE CLEANUP
1.14 USE OF UTILITIES
1.15 CONTRACTOR BASE CREDENTIALS
1.16 STORAGE
1.17 CONSTRUCTION INSPECTION
1.18 WARRANTIES
1.19 TESTING
1.20 TRANSFER AND ACCEPTANCE OF MILITARY REAL PROPERTY
1.21 CONTRACT CLOSEOUT
PART 2 PRODUCTS
NOT USED
PART 3 EXECUTION
NOT USED
Section 01 00 00 Page 2
SECTION 01 00 00
04/11
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL
ASTM E 2114 Standard Terminology for Sustainability
Relative to the Performance of Buildings.
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
Energy Star Energy Star Energy Efficiency Labeling
System
U.S. GREEN BUILDING COUNCIL (USGBC)
LEED Leadership in Energy and Environmental
Design(tm) Green Building Rating System for
New Construction (LEED-NC)
1.2 DEFINITIONS
a. File Transfer Protocol (FTP): Communications protocol that enables transfer of files to and from another computer over a network and that serves as the basis for standard Internet protocols. An FTP site is a portion of a network located outside of network firewalls within which internal and external users are able to access files.
b. Portable Document Format (PDF): An open standard file format licensed by Adobe Systems used for representing documents in a device-independent and display resolution-independent fixed-layout document format.
Definitions pertaining to sustainable development are as defined in ASTM E
2114, and as specified below.
c. "Environmentally preferable products" have a lesser or reduced effect on the environment in comparison to conventional products and services. This comparison may consider raw materials acquisition, production, manufacturing, packaging, distribution, reuse, operation, maintenance, or disposal of the product.
d. "Indoor environmental quality" is the physical characteristics of the building interior that impact occupants, including air quality, illumination, acoustics, occupant control, thermal comfort, day-lighting, and views.
Section 01 00 00 Page 3
e. "Operational performance" is the functional behavior of the building as a whole or of the building components.
f. "Sustainability" is the balance of environmental, economic, and societal considerations.
1.3 SUBMITTALS
1.3.1 Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Submittals shall use Air Force Form 3000 and shall be provided as soon as possible. The progress schedule and submittal register shall be submitted within twenty-one (21) days of the
Notice to Proceed. The submittal register shall show projected dates to submit required material information.
1.3.2 Units of weights and measures used on all submittals are to be the same as those used in the contract drawings. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
1.3.3 Contractor's Quality Control (CQC) System Manager and the Designer of
Record, if applicable, shall check and approve all items prior to submittal and stamp, sign, and date.
1.3.4 Proposed deviations from the contract requirements must be submitted in writing in the form of a request for change. Government approval of submittals that deviate from contract requirements that were not marked as such and clearly identified in writing, shall not be construed to change or modify any contract requirements.
1.3.5 Design Reviews: The Government will review design submittals for conformance with the technical requirements of the solicitation. Government review is only for conformance with the contract requirements. Acceptance of design submittals is not be construed as a complete check, and indicates only that the general method appears to meet the requirements of the
Solicitation. The Designer of Record is responsible for the technical adequacy and functionality of the design.
1.3.6 Sample Reviews: Approval of a sample is only for the characteristics or use named in such approval and shall not be construed to change or modify any contract requirements. Before submitting samples, the Contractor to assure that the materials or equipment will be available in quantities required in the project. No change or substitution will be permitted after a sample has been approved.
1.3.7 Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby.
Include catalog cuts, diagrams, operating charts or curves and all other required documents necessary for determination of compliance with contract.
The Government will:
Section 01 00 00 Page 4
a. Note date on which submittal was received.
b. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
c. Identify returned submittals with one of the actions defined in paragraph 1.3.8 below of this section and with markings appropriate for action indicated.
d. Upon completion of review of submittals requiring Government approval, copies of the approved submittal will be retained by the Contracting
Officer and one copy of the submittal will be returned to the Contractor.
1.3.8 Review Notations. Government review will be completed within 14 calendar days after date of submission. Submittals will be returned to the
Contractor with the following notations:
a. Submittals marked "approved" or "accepted" authorize the Contractor to proceed with the work covered.
b. Submittals marked "approved as noted" "or approved except as noted, re-submittal not required," authorize the Contractor to proceed with the work covered provided he takes no exception to the corrections.
c. Submittals marked "not approved" or "disapproved," or "revise and resubmit," indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes. No work shall proceed for this item until re-submittal is approved.
1.3.9 Contractor shall make corrections required by the Contracting Officer.
If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the clause entitled, "Changes," is to be given to the Contracting Officer. Contractor is responsible for the dimensions and design of connection details and construction of work.
Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.
1.3.10 WITHHOLDING OF PAYMENT
Payment for materials incorporated in the work will not be made if required approvals have not been obtained. No payment for materials incorporated in the work will be made if all required Designer of Record or required
Government approvals have not been obtained. No payment will be made for any materials incorporated into the work for any conformance review submittals or information only submittals found to contain errors or deviations from the Solicitation or Accepted Proposal.
1.4 WORK COVERED BY CONTRACT DOCUMENTS
1.4.1 Materials and Workmanship:
1.4.1.1 All equipment, material, and articles incorporated into the work
Section 01 00 00 Page 5 covered by this contract shall be new and of the most suitable grade for the purpose intended, unless otherwise specifically provided in this contract.
References in the specifications to equipment, material, articles, or patented processes by trade name, make, or catalog number, shall be regarded as establishing a standard of quality and shall not be construed as limiting competition. The Contractor may, at its option, use any equipment, material, article, or process that, in the judgment of the Contracting Officer, is equal to that named in the specifications, unless otherwise specifically provided in this contract.
1.4.1.2 All work under this contract shall be performed in a skillful and workmanlike manner. The Contracting Officer may require, in writing, that the Contractor remove from the work any employee the Contracting Officer deems incompetent, careless, or otherwise objectionable.
1.4.1.3 In accordance with FAR 52.236-6 At all times during performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor.
1.4.2 Weather Precautions:
Contractor shall ensure that weather sensitive materials are placed within the conditions recommended by the material supplier. No pavements shall be placed on frozen ground. Concrete placed when weather temperatures can be expected to fall below 32 degrees F shall be covered with approved blankets.
1.4.3 Project Description:
Briefly and without force or effect upon the contract documents, the work of this contract can be summarized as follows:
a. Architectural: The project encompasses the addition of new classrooms and breakroom extension to the east side of Building
680. With this addition a new entry will be created and the corridor reconfigured. An equipment platform will be constructed above the new break room ceiling to accommodate new mechanical and electrical equipment to serve the addition.
b. Civil:
General
Minor demolition of existing sidewalks/concrete pavement adjacent to Building 680 to construct new classroom addition
Minor grading around new classroom addition
Utilities
Relocate existing 4” natural gas line around classroom addition and protect existing gas service to Building 680 in place.
Relocate existing 8” waterline around new classroom addition.
Work includes remove existing fire hydrant and install new fire hydrant with protective bollards; install new 2” water service to Building 680; install temporary water service to building 680 from the new 2” water service to the existing
Section 01 00 00 Page 6 water service line to be abandoned at the completion of construction. All work in accordance with American Water
Standards and Specifications.
Protect existing sanitary sewer lateral under new classroom addition footing(s) with flowable fill encasement and install new dual directional cleanout 5’ outside the building
Tie-in new roof drains into existing storm drain/roof drain system
c. Structural: Provide support and enclosure for new classroom area, break room, and mezzanine areas and positively attach to existing structure. Support to be comprised of masonry walls and structural steel framing with concrete footings. Mezzanine support to be comprised of metal stud joists and plywood sheathing. Support new openings in existing masonry walls for new mechanical ductwork.
d. Mechanical: Provide three (3) new DX cooled, natural gas fired furnace units to serve the new break room area and the two new classrooms. Condensing units will be placed outside on the ground. Ventilation air will be provided. Plumbing will be revised to accommodate new room additions.
e. Electrical: Project includes new lighting, power, telecom, access control and intrusion detection systems for an addition and remodel for two classrooms and a breakroom. New devices shall tie into existing building electrical infrastructure.
f. Fire Alarm: Replace existing fire alarm control panel (FACP) with new FACP. New FACP shall include emergency voice alarm capabilities and shall be compatible with all existing fire alarm initiating devices in building. Modify existing fire system protecting portions of Building 680 to be remodeled and expand fire alarm system to protect building addition.
g. Fire Sprinkler: Add and/or relocate existing fire sprinklers as required to accommodate building remodel. Install new fire sprinklers to protect building addition.
1.4.4 Project Location:
The work shall be located at Hill Air Force Base, Building 680, as indicated.
1.5 SITE VISITS:
1.5.1 The Contractor shall attend scheduled site visits and take steps reasonably necessary to ascertain the nature and location of the work, and investigate the general and local conditions which can affect the work or its cost in accordance with FAR 52.236-3. Such investigation shall include but is not limited to:
a. The conditions bearing upon transportation, disposal, handling, and storage of materials.
b. The availability of labor, and necessary utilities including water, gas, and electric power.
c. The availability and suitability of pavements and roadways.
d. Prevalent weather conditions or similar physical conditions at the site.
Section 01 00 00 Page 7
e. The conformation and existing conditions of the ground, pavements and soils.
f. The character and condition of equipment and facilities needed preliminary to and during work performance.
1.5.2 The Contractor shall examine and note the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as that information is reasonably ascertainable from an inspection of the site. The contractor shall note any exploratory work performed by the Government and provided in the drawings and specifications or made a part of this contract as attachments. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.
1.5.2.1 The Government assumes no responsibility for any conclusions or interpretations made by the Contractor based on the information made available by the Government. Nor does the Government assume responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of this contract, unless that understanding or representation is expressly stated in this contract.
1.6 CONTRACT DRAWINGS:
1.6.1 Project Drawings:
The following drawings accompany this specification and are a part thereof.
Sheets 1 through 61
1.6.2 Working Drawings
The Contractor shall keep on the work site a copy of the Project drawings and specifications and shall at all times give the Air Force Project manager access thereto in accordance with FAR 52.236-21. Anything mentioned in the specifications and not shown on the drawings, or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both. In case of a difference between drawings and specifications, the specifications shall govern. In case of discrepancy in the figures, in the drawings, or in the specifications, the matter shall be promptly submitted to the Contracting Officer, who shall promptly make a determination in writing. Any adjustment by the Contractor without such a determination shall be at its own risk and expense. The Contracting Officer shall furnish AutoCAD sets of contract drawings, maps, and MS Word Versions of the specifications for use in creating As-Built Record Drawings.
Contactor shall immediately check the furnished drawings and notify the
Government of any discrepancies.
a. Wherever in the specifications or upon the drawings the words
“directed”, “required”, “ordered”, “designated”, “prescribed”, or words of like import are used, it shall be understood that the “direction”, “requirement”, “order”, “designation”, or “prescription”, of the
Contracting Officer is intended and similarly the words “approved”, “acceptable”, “satisfactory”, or words of like import shall mean
Section 01 00 00 Page 8
“approved by,” or “acceptable to”, or “satisfactory to” the Contracting
Officer, unless otherwise expressly stated.
b. Where “as shown,” as indicated”, “as detailed”, or words of similar import are used, it shall be understood that the reference is made to the drawings accompanying this contract unless stated otherwise. The word “provided” as used herein shall be understood to mean “provide complete in place,” that is “furnished and installed”.
c. Wherever in the specifications or upon the drawings the words the terms
“As Built Record Drawings”, “marked up drawings”, “marked up prints”, “record drawings” and “red-lined drawings” are used, it shall be understood that “As-Built Record Drawings” as defined below is intended.
1.6.3 Shop Drawings:
1.6.3.1 The term Shop Drawings means drawings, submitted to the Government by the Contractor, subcontractor, or any lower tier subcontractor pursuant to a construction contract, showing in detail the following items.
a. The proposed fabrication and assembly of structural elements and the installation (i.e., fit, and attachment details) of materials or equipment.
b. Drawings, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance and test data, and similar materials furnished by the contractor to explain in detail specific portions of the work required by the contract. The Government may duplicate, use, and disclose in any manner and for any purpose shop drawings delivered under this contract.
1.6.3.2 If this contract requires shop drawings, the Contractor shall coordinate all such drawings, and review them for accuracy, completeness, and compliance with contract requirements and shall indicate its approval thereon as evidence of such coordination and review. Shop drawings submitted to the Contracting Officer without evidence of the Contractor’s approval may be returned for resubmission. The Contracting Officer will indicate an approval or disapproval of the shop drawings and if not approved as submitted shall indicate the Government’s reasons therefore.
Any work done before such approval shall be at the Contractor’s risk.
Approval by the Contracting Officer shall not relieve the Contractor from responsibility for any errors or omissions in such drawings, nor from responsibility for complying with the requirements of this contract, except with respect to variations described and approved in accordance with paragraph below.
a. If shop drawings show variations from the contract requirements, the
Contractor shall describe such variations in writing, separate from the drawings, at the time of submission. If the Contracting Officer approves any such variation, the Contracting Officer shall issue an appropriate contract modification, except that, if the variation is minor or does not involve a change in price or in time of performance, a modification need not be issued.
a. b. The Contractor shall submit to the Contracting
Officer for approval three copies (unless otherwise indicated) of all shop drawings as called for under the various headings of these specifications. The Contractor shall also submit a PDF electronic file. Two sets (unless otherwise indicated) of all shop drawings, will be retained
Section 01 00 00 Page 9 by the Contracting Officer and one set will be returned to the Contractor. Upon completing the work under this contract, the Contractor shall furnish a complete set of all shop drawings as finally approved. These drawings shall show all changes and revisions made up to the time the equipment is completed and accepted. The Contractor shall also provide a complete set of all shop drawings as finally approved in PRF electronic format.
1.6.4 As-Built Record Drawings:
1.6.4.1 Whenever changes occur the contractor shall immediately mark-up the working copy of the contract drawings in red to show both changes and the actual installation in sufficient detail including accurate dimensioning as necessary to form a complete record of work accomplished. Accuracy of changed elements may also be accomplished by surveying. Sign and date each mark-up redline as it occurs. The marked-up working drawings shall be on site, complete, legible, precise and understandable to a CAD operator who is unfamiliar with the project.
1.6.4.2 Upon completing the work under this contract, the Contractor shall use the marked-up working drawings and the approved shop drawings to produce the final As-Built Record Drawings. Furnish one complete set of bound AutoCAD As-Built Record Drawings including all shop drawings as finally approved. Provide digital (AutoCAD or pdf) as-built shop drawings, calculations and O&M Manuals. These drawings shall show changes and revisions made up to the time the contract is completed and accepted.
Include all unusual or uncharted obstructions that were encountered in the contract area during construction. All sheets shall be annotated as As-
Built Record Drawings in the revision section of the title block even if no changes occur during the contract.
a. Revisions made shall ensure related section and elevation views, details, legend, plans, profiles, schedules and notes are marked as needed to prevent conflicting data on differing sheets. Comments shall be complete without reference to change orders, letters, memos, etc.
The marked-up drawings shall be labeled to show project title and number.
b. Surveying data will be in Universal Transverse Mercator 1983 (UTM83) coordinate system, Transverse Mercator projection, Geodetic Reference
System 1980 (GRS80) spheroid, or World Geodetic System 1984 (WGS84) datum, and use metric coordinate units.
c. Particular attention should be given to work, which will be concealed and difficult to measure and record after construction, and work which may require servicing or replacement during the life of the facility.
The following are areas of concern that need special checking to ensure that the marked-up prints are complete and accurate:
1. Dimensions shall be clearly shown and accurately locate all changes in direction of utility lines. All surface or underground components such as valves, manholes, drain inlets, clean outs, meters, etc shall be indicated. The description utilities placed shall include the actual quantity, size, and type of materials used.
2. Actual location, size and type of interior plumbing and electrical lines installed below a concrete slab shall be clearly and accurately indicated.
Section 01 00 00 Page 10
3. Changes to layout and schematic drawings of electrical circuits and piping shall be clearly shown.
4. Correct dimensions and details shall be transferred from shop drawings.
5. Actual location of anchors, construction and control joints, in concrete must be shown.
6. Changes in location of equipment and architectural features must be shown.
7. Specific materials provided shall be indicated and words such as
“or equal” shall be removed.
1.6.4.3 The Air Force project managers will review the contractor’s marked-up drawings when verifying the performance shown by progress reports. If the drawings are not current, the progress report will be adjusted downward by the Civil Engineering project manager to reflect the contractor’s non-compliance. Marked-up drawings will be submitted within five working days after substantial completion. Final payment will not be authorized until complete and accurate digital and hard copy red-lined drawings are accepted by the Contracting Officer.
1.7 WORK SCHEDULING
1.7.1 Contractor shall allow in their planned work schedule for potential
Government caused delays as follows; Allow for 5 calendar days where the contractor’s construction activity is prohibited by Air Force Exercises or similar military events. Allow for 14 calendar days where excavation, utility outages, road closures, or other subsurface requested activities may be prevented. (Other construction activities will be permitted to continue.) Government will provide 24 hour notification each time the government caused delays mentioned above are invoked. No additional time will be granted for delays falling within those limits.
Normal duty hours for work shall be:
A. 0730 to 1600 Hours exclusive of Saturdays, Sundays, and holidays unless other times are approved by the Contracting Officer, or otherwise stated in the contract. Coordinate the work schedule with the Civil Engineering Project Manager.
1.7.2 Contract Progress Schedules AF Forms 3064 and 3065.
See Section 01 32 01 Project Schedule for information on this requirement.
1.8 OCCUPANCY OF PREMISES
1.8.1 Building Occupancy.
Adjacent building(s) will be occupied during performance of work under this
Contract unless expressly stated otherwise -in writing- from the
Contracting Officer.
Section 01 00 00 Page 11
1.8.1.1 Before work is started, the Contractor shall arrange with the
Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and the use of approaches, corridors, stairways, roads and truck gates.
1.8.1.2 Contractor shall make provisions to maintain occupied areas of any building under repair at no less than 65 degrees F and no warmer than 85 degrees F. Unoccupied areas shall be maintained above 40 degrees F to prevent freezing of water lines and fire protection systems.
1.8.1.3 Temporary heating, if required, shall be UL approved electric heaters and shall be physically monitored at least every 4 hours.
1.9 PROTECTION OF EXISTING GOVERNMENT PROPERTY AND EXISTING WORK
1.9.1 In addition to FAR 52.236-9 the Contractor shall conduct all operations in such a manner as to prevent injury or damage to government property and any portions of the existing work which are to remain. This requirement is not limited to just the project site but includes landscaping, curbs, pavements, and utilities adjacent to the site as well as along routes to and from the site. Where any ambiguity exists the contractor shall request clarification from the Contracting Officer before beginning work.
1.9.2 Contractor shall make repairs to or replace portions of existing work that is damaged or altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.9.3 In the event the contractor fails or refuses to make satisfactory repairs or replacements to property damaged by the contractor under this contract the government will have the repairs made and charge the cost to the contractor.
1.10 ON-SITE PERMITS
1.10.1 Excavation Permits
1.10.1.1 Notify the Contracting Officer prior to notice to proceed of anticipated excavation and intended routes and methods. At least 30 days prior to excavating, the contractor shall obtain a Base Civil Engineering
Excavation Permit. Permits are available from the Red Stake Office in
Building 593 South. Provide the filled out permit to the Civil Engineering
Project Manager no less than 21 days prior to starting excavation work.
The contractor shall field mark the alignment of all intended excavations with flags or non-permanent white paint. The project manager will notify the contractor when the permit is complete and excavation can begin. (for work at Utah Test and Training Range UTTR Civil Engineering Office permits can be obtained by calling 801-777-1577)
1.10.1.2 The Contractor shall protect from damage all existing improvements and utilities at or near the work site, and on adjacent property of a third party, the locations of which are made known to or should be known by the
Contractor.
1.10.1.3 The Contractor shall repair any damage to those facilities, Section 01 00 00 Page 12 including those that are the property of a third party, resulting from failure to obtain necessary permits and utility marking or failure to exercise reasonable care in performing the work. This includes irrigation lines and sprinkler components. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
1.10.1.4 The Contractor shall verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated or specified to be removed but indicated in locations to be crossed by piping, ducts, and other work to be installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
a. Hand digging shall be required to locate utilities shown on the contract drawings, Excavation Permit, or 3 feet on either side of locations identified by Base Maintenance Shops. For facilities that store munitions hand digging is required within 10 feet of the bldg to locate the existing grounding cable.
b. All excavation work within 15ft of a Questar high pressure natural gas distribution line will require Questar Gas technicians to be on-site during the excavation. Contractor shall coordinate this through Blue Stakes.
1.10.2 Utility Outage Requests.
1.10.2.1 Notify the Contracting Officer prior to notice to proceed of anticipated utility outages and closures of streets, parking lots, and pedestrian walkways. Work shall be scheduled to hold outages to a minimum.
Utility outages and connections required during the prosecution of work that affect existing systems shall be arranged for at the convenience of the Government and shall be scheduled on weekends unless otherwise approved by the Contracting Officer. Contractor shall not be entitled to additional payment for utility outages and connections required to be performed outside the regular work hours. All utility outages shall be of as short duration as possible and scheduled as far in advance as possible but in no case less than 24 calendar days prior to the outage or closure. Schedule with the Air Force Project Manager. The Contractor shall obtain in writing from the Project Manager a statement or schedule giving the permissible times for the outage or closure for particular installations and the maximum time allowed for such outage or closure. Permits shall be posted at a conspicuous location in the construction area.
1.10.3 Utility Connection Requests.
1.10.3.1 Utility connections required during the prosecution of work that affect existing systems regardless of necessity for a utility outage shall be arranged for at the convenience of the Government and shall be scheduled on weekends unless otherwise approved by the Contracting Officer. All newly installed underground utilities shall include tracer wire and marking strip and be surveyed by HAFB before the utilities are buried. Provide at least
7 day advance notice of utility connections when an outage is not required.
Comply with paragraph governing utility outages otherwise.
1.10.3.2 Provide 48 hours of advance notice to the Project Manager when new utility lines will be ready for inspection and surveying. The Contractor
Section 01 00 00 Page 13 shall uncover any utility lines buried prior to notification. Contractor shall not be entitled to additional payment for uncovering and reburying any utility lines that were covered prior to providing this 48 hour notice.
1.10.4 Burning Permits.
OPEN BURNING OF ANY SORT IS STRICTLY PROHIBITED.
1.10.5 Welding, Cutting and Brazing Permits.
Air Force (AF) Form 592 is required daily for all welding, cutting, brazing, soldering and similar hot work. The form shall be properly filled out and displayed while all hot work is underway. The Contractor will be required to attend the Welding, Cutting, Brazing certification class prior to construction startup. This class is conducted on the first Thursday of every month and the Base Fire Station Bldg 9.
1.10.6 Street Closures.
The contractor shall obtain approval in writing from the Project Manager before closing any street or parking lot. Submit requests at least 15 days in advance. Include the length to be closed and the length of time of the closure.
1.11 SAFETY.
1.11.1 Governmental Requirements for Construction Safety are given in section 01 35 26 GENERAL SAFETY REQUIREMENTS. In addition to the requirements listed in that section the contractor shall provide and maintain work environments and procedures which will;
a. Safeguard the public and Government personnel, property, materials, supplies, and equipment exposed to Contractor operations and activities.
b. Avoid interruptions of Government operations and delays in project completion dates.
c. Comply with all pertinent provisions of the latest version of U.S. Army
Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, in effect on the date of the solicitation.
d. Comply with the standards issued by the Secretary of Labor at 29 CFR
Part 1926 and 29 CFR Part 1910.
1.11.2 Whenever the Contracting Officer becomes aware of any noncompliance with these requirements or any condition which poses a serious or imminent danger to the health or safety of Contractor personnel, the public or
Government personnel, the Contracting Officer shall notify the Contractor orally, with written confirmation, and request immediate initiation of corrective action. This notice, when delivered to the Contractor or the
Contractor’s representative at the work site, shall be deemed sufficient notice of the noncompliance and that corrective action is required. After receiving the notice, the Contractor shall immediately take corrective action. If the Contractor fails or refuses to promptly take corrective action, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. The
Contractor shall not be entitled to any equitable adjustment of the contract price or extension of the performance schedule on any stop work
Section 01 00 00 Page 14 order so issued.
1.12. ENVIRONMENTAL PROTECTION
1.12.1 Requirements for environmental protection and hazardous materials are given in detail in section 01 57 20 ENVIRONMENTAL PROTECTION. In addition to the requirements listed in that section The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as well as any fines levied as a result of the Contractor’s fault or negligence. The Contractor shall be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract.
1.13. SALVAGE MATERIAL AND WORKSITE CLEANUP
1.13.1 The Contractor shall at all times keep the work area, including storage areas, free from accumulations of waste materials and obstructions.
At the end of each work day and at project final completion, the Contractor shall leave the work area in a clean, neat, and orderly condition satisfactory to the Contracting Officer. Before completing the work, the
Contractor shall remove from the work site any rubbish, tools, scaffolding, equipment, and materials that are not the property of the Government.
a. All excavated material (dirt, asphalt, concrete, etc.) and construction/demolition debris shall be managed in accordance with
Section 01 57 20 ENVIRONMENTAL PROTECTION.
b. All fire alarm control panels (FACP), Monaco Radio Fire Alarm
Transceivers (BT), Vindicator Intrusion Detection Panels (IDS) and
Vindicator Card Access Systems (ACSYS) to be removed under this contract shall remain property of the government and shall be delivered to the Civil Engineering Electronics Shop (Bldg 597). Cabinets will be delivered with all electronics and internal wiring intact. However, the batteries in the cabinets will be removed by the contractor and disposed of as hazardous waste as required under Section 01 57 19
ENVIRONMENTAL PROTECTION.
1.14. USE OF UTILITIES.
1.14.1 In general, the contractor will be allowed the use of electrical, and natural gas utilities without reimbursement while performing work under this contract, if available. In some cases the government will require reimbursement as when extensive temporary heating is required. In such cases, rates for utility costs will be established at the time of award.
a. Toilet facilities on the site may be used by the workmen subject to the regulation of the Government.
Section 01 00 00 Page 15
1.15. CONTRACTOR BASE CREDENTIALS.
1.15.1 To Obtain base identification passes for contractor personnel the prime Contractor shall submit a written request on company letterhead stationary, if available, to the Contracting Officer specifying the following:
a. Contract number.
b. Location of the work.
c. Date entry to the base required and contemplated termination date of entry.
d. Names of contractor and subcontractor employee requiring access to the base.
e. The name of the individual who will submit the Request of
Identification Credentials for each employee for whom identification credentials are needed.
1.15.2 The Contracting Officer will:
a. Endorse the request.
b. Attach a copy of the contract cover page and any other pages that provide performance information, such as the need for and duration of access to the work site.
c. Forward this request to the Security Forces, Pass and
Registration Office of the installation where the work is to be performed.
d. Provide blank Application For AFMC Identification Card, AFMC Form 496 and Unescorted Entry Authorization
Certificate, AF Form 2586 to the Prime Contractor.
1.15.3 The Prime Contractor shall be required to complete and submit AFMC
Form 496, for each of the firm's employees and for each subcontractor employee who must have access to the installation. For contracts, 90 days or less contractor employees will be issued an AF Form 75 unless the work is in a controlled or restricted area. For contracts in a controlled or restricted area or greater than 90 days an AFMC Form 387 will be issued.
1.15.4 The Prime Contractor is required to complete and submit AF Form 2586 for each of the firm’s employees and for each subcontractor employee who must have access to a controlled or restricted area at the installation.
The Prime Contractor shall ensure that all contractor personnel including subcontractors attend the Explosive Safety Briefing if applicable. See paragraph 1.14G. An Explosive Safety Awareness Statement signed by those requesting badges is required prior to processing AF Form 2586. The Weapon
Safety Monitor will provide the Contracting Officer copies of the awareness statements. The Security Forces, Pass and Registration Office, upon issuance of the appropriate badge for AF Form 2586, will provide the
Section 01 00 00 Page 16 original completed AF Form 2586 to the individual receiving the badge. The original form shall be given to the Contracting Officer for accountability.
The Prime Contractor shall also request AF Form 75, Visitor/Vehicle Pass or
DD Form 2220, DoD Registered Vehicle, for vehicle decals when the AFMC Form
496 is submitted. To obtain the vehicle decal from the Security Forces, Pass and Registration Office, the Contractor shall produce:
(1) A valid drivers license.
(2) Proof of financial responsibility or insurance, which meets the minimum requirements of the contract clause, entitled
"Required Insurance."
(3) Current vehicle registration.
(4) Proof of Davis County emissions certification if the vehicle is not registered in a county within the State of Utah, which requires emissions testing.
1.15.5 Follow the guidance in AFI 31-101, The Installation Security Program, when work under this contract requires entry to controlled areas. The
Contractor will request completion of an AF Form 2586, from the project manager for one prime contractor employee. That employee will act as escort for all other prime and subcontractor employees. Contractor employees with controlled area badges are required to escort contractor employees without badges, at all times, in and out of controlled areas. If it becomes necessary to establish a free zone for the Contractor, it must be approved in writing by the installation commander. The free zone must have clearly defined boundaries. It is recommended the free zone begin at some point in the boundary of the controlled area, which enables entry by the Contractor and other authorized personnel. The free zone must be closed during non-duty hours. The boundaries of the free zone must be under surveillance by the OPR for the area or designated responsible activity.
a. The contractor shall not permanently alter any surface in the controlled area when establishing a free zone such as drilling holes in pavements for temporary fencing or drilling holes in walls and floors for other barriers.
1.15.6 Contractors working inside buildings 680 F22 secure areas shall be escorted by 309 AMXG personnel. 309 AMXG will only provide one escort at any one time. Each escort will only oversee up to five Contractor personnel. Contractor personnel shall be in close proximity of and within sight of escort at all times. Contractor shall provide 309 AMXG seven days of notice for each piece of work requiring an escort. New addition is not located in F22 secure area of building 680. Hangar, Electrical Room and
South Toilet Rooms are part of F22 secure area of building 680.
1.15.7 All contractors working in building 680 shall be US citizens.
1.15.8 Contractor employees, at all times while on a military installation, shall wear visible contractor-provided identification either as a part of, or attached to, their outer clothing. The identification shall clearly identify the individual as being a contractor employee.
Section 01 00 00 Page 17
1.15.9 During performance of the contract, the Contractor shall be responsible for obtaining required identification for newly assigned personnel, and for prompt return of credentials and vehicle registration decals to the Security Forces, Pass and Registration Office, for any employee who no longer requires access to the work site.
1.15.10 At the termination or completion of the contract, or upon the expiration of credentials (if any such expirations are specified), the
Contractor must be sure that all base identification credentials and vehicle registration decals for all contractor and subcontractor employees are returned to the Contracting Officer.
1.15.11 Prior to submitting an invoice for final payment, the Prime
Contractor shall obtain a clearance certification from the contracting officer which states that all base identification credentials and vehicle decals have been returned or "accounted for." This certification shall be attached to the final invoice at the time of submittal for payment. Failure to comply with these requirements will result in withholding final payment.
1.15.12 If it becomes necessary for the Contractor to enter any unmanned base entry gate, they must first contact 75 SFS/SFO at 777-5531. If the
Contractor assumes custody or control of a particular gate they will insure:
1.Only cleared contractor personnel for that respective project gain access to the base through that gate.
2.Lock and Key Control will be established in such a manner as to clearly define an audit trail of who have keys to the gates and the times the gates are opened and closed, 24 hours a day.
1.16 STORAGE
1.16.1 In accordance with general provisions entitled Operations and Storage
Areas (FAR 52.236-10)the Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor’s performance.
1.16.2 Temporary buildings (construction trailers, storage sheds, shops, offices) are not permitted unless approved in advance by Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the
Contractor at its expense upon completion of the work.
1.16.3 The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any
Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
1.16.4 Store materials so as to avoid hindering the work of other
Contractors and to avoid damage or soiling of materials. All materials and
Section 01 00 00 Page 18 equipment shall be stored and handled to preclude the inclusion of foreign matter and damage by water or breakage. Store packaged materials in original containers until ready for use. Materials showing evidence of water or other damage shall be rejected and removed from the base. All materials shall be stored as recommended by the manufacturer, unless specifically noted otherwise in the contract documents.
1.16.5 When pipe and conduit are stored on the site, they shall be stored in racks or blocked to prevent rolling.
1.16.6 When combustible materials are stored on the site they shall be stored in an OSHA approved combustible materials locker at least 50 feet (15 meters) from all buildings unless otherwise specifically indicated by the