About this file
Estimated Quantities
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Q&A.pdf | ||
| Attachment_I_-_Section_L_070119_Final.pdf | ||
| FA812819R0005_______0001.pdf | ||
| Attachment_II-Section_M_070119_Final.pdf | ||
| Attachment_VI_-_DDForm254-Draft-_Final.pdf | ||
| CDRLA001_-_Final.pdf | ||
| CDRLA004_-_Final.pdf | ||
| FA812819R0005_-_Final.pdf | ||
| CDRLA003_-_Final.pdf | ||
| Attachment_IV_-_MSD_Technical_Order_Pricing_Matrix_070119_Final.xlsx | XLSX spreadsheet | |
| Attachment_III_-_PWS_-_Final.pdf | ||
| Attachment_I_-_Section_L_070119_Final.pdf | ||
| CDRLA002_-_Final.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
JS
2. AMENDMENT/MODIFICATION NO.
FA8128-19-R-0005-0002
3. EFFECTIVE DATE
16 JUL 2019
4. REQUISITION/PURCHASE REQ. NO.
FD20301930634
5. PROJECT NO (If applicable)
6. ISSUED BY CODE FA8128 7. ADMINISTERED BY (If other than item 6) CODE
DEPARTMENT OF THE AIR FORCE, AFNWC PZN
7330 SENTRY BLVD BLDG 469
TINKER AFB OK 73145-9093
BUYER: Erin Crabtree/AFNWC/PZNT erin.crabtree.1@us.af.mil Phone: (000) 000- 0000 No Collect Calls
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
X
9A. AMENDMENT OF SOLICITATION NO.
FA812819R0005
9B. DATED (SEE ITEM 11)
27-JUN-2019
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers X is extended, is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods. ( a ) By completing Items 8 and 15, and returning copies of the amendment; ( b ) By acknowledging receipt of this amendment on each copy of the offer submitted; or ( c ) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED
MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified. 22-JUL-2019 3:00
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
BY
(Signature of person authorized to sign)
NSN 7540-01-152-8070
15C. DATE SIGNED
30-
16B. UNITED STATES OF AMERICA
BY
(Signature of Contracting Officer)
105 STANDARD FORM 30 (REV.
16C. DATE SIGNED
10-83)
PREVIOUS EDITION UNUSABLE PRESCRIBED BY GSA
FAR (48 CFR) 53.243
mailto:erin.crabtree.1@us.af.mil
FA8128-19-R-0005-0002
Continuation of block 14. DESCRIPTION OF AMENDMENT/MODIFICATION
The purpose of this amendment is to extend the proposal due date, revise Section L and revise estimated quantities.
FIRST: The proposal submission date for solicitation FA8128-19-R-0005 is hereby extended as follows:
FROM: 17 July 2019 at 3:00 p.m.
TO: 22 July 2019 at 3:00 p.m.
SECOND: Section L has been revised to delete a reference to section 6.4.1, in regards to cost/price volume.
THIRD: Estimated quantities have been revised for all applicable CLINs in Section B, Part 1 (See
Below).
CLIN FROM: TO: Total QTY (Base + 4 Option Years)
X001 1 1 1 X002 1 2518 12,950
X003 1 351 1,755 X004 1 1 1
X005 1 325 1,625
X006 1 225 1,125
X007 1 6,350 31,750
X008 1 1 1
X009 1 67 335
X010 1 1,800 9,000
X011 1 1 1
X012 1 1 1 X013 1 1 1 X014 1 1 1
X015 1 3,650 18,250 X016 1 1 1 X017 1 1 1
X018 1 1 1 X019 1 1 1
X020 1 1 1
X021 1 1 1
X022 1 107 535
X023 1 1 1
X024 1 1 1
SECOND: All other terms and conditions remain unchanged and in full force and effect.
SUPPLIES OR SERVICES AND PRICES/COSTS
DO NOT TRANSMIT CLASSIFIED INFORMATION OVER UNSECURED TELECOMMUNICATIONS SYSTEMS.
OFFICIAL DOD TELECOMMUNICATIONS SYSTEMS ARE SUBJECT TO MONITORING. USE OF DOD
TELECOMMUNICATIONS SYSTEMS CONSTITUTES CONSENT TO MONITORING.
Item No.
Required Period of Performance
Proposed Period of Performance
Firm Fixed Price Quantity U/I Unit Price Amount 1 LO To be Determined
Phase In/Transition
In accordance with the Performance Work Statement Class I ODS Substance Application/Use Quantity None Place of Perf Quantity (U/I) *ARO Contract _ Req No / Pri
1 LO *45 Calendar Days
1 LO
Phase In/Transition
Estimated Quantity
U/I Unit Price Estimated Total Price
2,518 ZP To be Determined
ZP equals Firm Fixed Price Per Page Text Change In accordance with the Performance Work Statement.
Limitations of Liability: Other Than High Value Item
Inspection: Destination Acceptance: Destination
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection Class I ODS Substance Application/Use Quantity
351 ZP To be Determined
Text Change to Illustration In accordance with the Performance Work Statement.
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
ZP To be Determined
Technical Page Development from Source Data In accordance with the Performance Work Statement.
Technical Page Development from Source Data - Basic Year
Text Change to Illustration - Basic Year
Text Change - Basic Year
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
325 ZP To be Determined
Revised Illustration In accordance with the Performance Work Statement.
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
225 ZP To be Determined
New Illustration In accordance with the Performance Work Statement.
Inspection/Acceptance Report: Receiving Report Required
Quality Assurance: Commercial Item Inspection
Firm Fixed Price
New Illustration - Basic Year
Revised Illustration - Basic Year
Pre-Publication Review Copy - Basic Year
6,350 ZP To be Determined
Pre-Publication Review Copy In accordance with the Performance Work Statement.
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
PK To be Determined
PK equals Firm Fixed Price Per Package Printing Package from Form Sets In accordance with the Performance Work Statement.
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
67 PK To be Determined
History Package Development in accordance with the Performance Work Statement.
History Package Development - Basic Year
Printing Package from Form Sets - Basic Year
Pre-Publication Review Copy - Basic Year
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
1,800 ZP To be Determined
Reprints in accordance with the Performance Work Statement.
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
DC To be Determined
DC equals Firm Fixed Price Per C/D (Computer Disc) Digitized Delivery of Change/Revision Page in accordance with the Performance Work Statement.
Inspection/Acceptance Report: Receiving Report Required
Quality Assurance: Commercial Item Inspection
Firm Fixed Price
Digitized Delivery of Change/Revision Page - Basic Year
Reprints - Basic Year
Standard General Mark-up Language (SGML) Sustainment - Basic Year
SGML Sustainment in accordance with the Performance Work Statement.
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
EA To be Determined
EA equals Firm Fixed Price Per Manual Maintenance and Storage of Technical Manuals in accordance with the Performance Work Statement.
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Convert Tech Order from Digital in accordance with the Performance Work Statement.
Convert Tech Order from Digital - Basic Year
Maintenance and Storage of Technical Manuals - Basic Year
Standard General Mark-up Language (SGML) Sustainment - Basic Year
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
3,650 ZP To be Determined
Update Tech Manual Indexed Portable Doc File (IPDF) in accordance with the Performance Work Statement.
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Firm Fixed Price Per Page Enhance Poor Quality IPDF File in accordance with the Performance Work Statement.
Inspection/Acceptance Report: Receiving Report Required
Quality Assurance: Commercial Item Inspection
Firm Fixed Price
Enhance Poor Quality IPDF File - Basic Year
Update Tech Manual Indexed Portable Doc File (IPDF) - Basic Year
Convert Paper Tech Manuals to IPDF Files - Basic Year
Convert Paper to IPDF in accordance with the Performance Work Statement.
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Convert Digital to IPDF in accordance with the Performance Work Statement.
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Convert Paper to Digital Editable File in accordance with the Performance Work Statement.
Convert Paper Document to Digital Editable File - Basic Year
Convert Technical Orders in Digital Form to IPDF - Basic Year
Convert Paper Tech Manuals to IPDF Files - Basic Year
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Convert Paper to Standard General Mark-Up Language (SGML) in accordance with the Performance Work Statement.
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
General Data Conversion to SGML in accordance with the Performance Work Statement.
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Firm Fixed Price
Digital Data Conversion to SGML - Base Year
Convert Paper to Standard General Mark-Up Language (SGML) - Base Year
Stock, Store, and Issue TO's - Base Year
107 EA To be Determined
Stock, Store, and Issue TO's
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
1 LO Not Separately Priced Not Separately Priced
DATA
IN ACCORDANCE WITH THE REQUIREMENTS SET FORTH ON THE DD FORM 1423 (EXHIBITS A) ATTACHED AND MADE A PART
HEREOF.
Exhibit: A
A001 Contractor Held Conferences/Meetings – Official Minutes
A002 Contract Funds Status Report
A003 Technical Reports/Services
A004 Inventory/Utilization Data Report
Cost Reimbursement - No Fee
Quantity U/I Estimated Unit Price Amount
Travel Cost Reimbursement
Travel Cost Reimbursement - Basic Year
CDRLs - Base Year
Stock, Store, and Issue TO's - Base Year
This CLIN is to support Government directed travel. The contractor shall provide travel in accordance with (IAW) the PWS.
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
The Contractor may be required to travel in support of task order (TO) requirements. Travel requirements will be reimbursed by separate voucher and must be coordinated in advance with the
Contracting Officer representative (COR) and approved by the Procuring Contracting Officer. Travel requirements will be identified, proposed, and negotiated in individual task orders on a cost-reimbursement basis as the requirement for travel upon occurrence
In accordance with FAR 31.205-46(a)(2), costs incurred by the contractor for authorized travel shall be reimbursed to the extent that they do not exceed, on a daily basis, per diem rates set forth in the Joint
Travel Regulations (JTR). Travel expenses such as air fare, ground transportation, and per diem costs in direct support of this TO will be issued under the applicable travel CLIN.
For purposes of this contract, the Government under no circumstances will pay per diem for a contractor who is not on Government directed official travel IAW the provisions of this clause.
Option Year I
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection Class I ODS Substance Application/Use Quantity None
Text Change - Option I
Travel Cost Reimbursement - Basic Year
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Revised Illustration - Option I
Technical Page Development from Source Data - Option I
Text Change to Illustration- Option I
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Inspection/Acceptance Report: Receiving Report Required
Quality Assurance: Commercial Item Inspection
Firm Fixed Price
Pre-Publication Review Copy - Option I
New Illustration - Option 1
Printing Package from Form Sets - Option I
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Reprints - Option I
History Package Development Option I
Printing Package from Form Sets - Option I
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Firm Fixed Price
Standard General Mark-up Language (SGML) Sustainment - Option I
Digitized Delivery of Change/Revision Page - Option I
Maintenance and Storage of Technical Manuals - Option I
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Update Tech Manual Indexed Portable Doc File (IPDF) in accordance with the Performance Work Statement.
Update Tech Manual Indexed Portable Doc File (IPDF) - Option I
Convert Tech Order from Digital - Option I
Maintenance and Storage of Technical Manuals - Option I
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Firm Fixed Price
Convert Paper Tech Manuals to IPDF Files - Option I
Enhance Poor Quality IPDF File - Option I
Convert Technical Orders in Digital Form to IPDF - Option I
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Convert Paper to Standard General Mark-Up Language (SGML) in accordance with the Performance Work Statement.
Convert Paper to Standard General Mark-Up Language (SGML) - Option i
Convert Paper Document to Digital Editable File - Option I
Convert Technical Orders in Digital Form to IPDF - Option I
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Inspection/Acceptance Report: Receiving Report Required
Quality Assurance: Commercial Item Inspection
Firm Fixed Price
Stock, Store, and Issue TO's - Option I
Digital Data Conversion to SGML - Option I
CDRLs - Option I
IN ACCORDANCE WITH THE REQUIREMENTS SET FORTH ON THE DD FORM 1423 (EXHIBITS A) ATTACHED AND MADE A PART
This CLIN is to support Government directed travel. The contractor shall provide travel in accordance with (IAW) the PWS.
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Contracting Officer representative (COR) and approved by the Procuring Contracting Officer. Travel requirements will be identified, proposed, and negotiated in individual task orders on a cost-reimbursement basis as the requirement for travel upon occurrence
In accordance with FAR 31.205-46(a)(2), costs incurred by the contractor for authorized travel shall be reimbursed to the extent that they do not exceed, on a daily basis, per diem rates set forth in the Joint
Travel Cost Reimbursement - Option I
CDRLs - Option I
Travel Regulations (JTR). Travel expenses such as air fare, ground transportation, and per diem costs in direct support of this TO will be issued under the applicable travel CLIN.
Option Year II
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection Class I ODS Substance Application/Use Quantity None
Text Change to Illustration - Option II
Text Change - Option II
Quantity
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
New Illustration - Option II
Revised Illustration - Option II
Technical Page Development from Source Data - Option II
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required
Quality Assurance: Commercial Item Inspection
Firm Fixed Price
Printing Package from Form Sets - Option II
Pre-Publication Review Copy - Option II
History Package Development - Option II
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Digitized Delivery of Change/Revision Page - Option II
Reprints - Option II
History Package Development - Option II
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Firm Fixed Price
Maintenance and Storage of Technical Manuals - Option II
Standard General Mark-up Language (SGML) Sustainment - Option II
Convert Tech Order from Digital - Option II
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Update Tech Manual Indexed Portable Doc File (IPDF) in accordance with the Performance Work Statement.
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Enhance Poor Quality IPDF File - Option II
Update Tech Manual Indexed Portable Doc File (IPDF) - Option II
Convert Tech Order from Digital - Option II
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Firm Fixed Price
Convert Technical Orders in Digital Form to IPDF - Option II
Convert Paper Tech Manuals to IPDF Files - Option II
Convert Paper Document to Digital Editable File - Option II
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Convert Paper to Standard General Mark-Up Language (SGML) in accordance with the Performance Work Statement.
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Digital Data Conversion to SGML - Option II
Convert Paper to Standard General Mark-Up Language (SGML) - Option II
Convert Paper Document to Digital Editable File - Option II
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
IN ACCORDANCE WITH THE REQUIREMENTS SET FORTH ON THE DD FORM 1423 (EXHIBITS A) ATTACHED AND MADE A PART
A003 Technical Reports/Services
A004 Inventory/Utilization Data Report
CDRLs - Option II
Stock, Store, and Issue TO's - Option II
This CLIN is to support Government directed travel. The contractor shall provide travel in accordance with (IAW) the PWS.
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Contracting Officer representative (COR) and approved by the Procuring Contracting Officer. Travel requirements will be identified, proposed, and negotiated in individual task orders on a cost-reimbursement basis as the requirement for travel upon occurrence
In accordance with FAR 31.205-46(a)(2), costs incurred by the contractor for authorized travel shall be reimbursed to the extent that they do not exceed, on a daily basis, per diem rates set forth in the Joint
Travel Regulations (JTR). Travel expenses such as air fare, ground transportation, and per diem costs in direct support of this TO will be issued under the applicable travel CLIN.
Option Year III
Text Change - Option III
Travel Cost Reimbursement - Option II
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required
Quality Assurance: Commercial Item Inspection
Firm Fixed Price
Technical Page Development from Source Data - Option III
Text Change to Illustration - Option III
Revised Illustration - Option III
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Pre-Publication Review Copy - Option III
New Illustration - Option III
Revised Illustration - Option III
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Inspection/Acceptance Report: Receiving Report Required
Quality Assurance: Commercial Item Inspection
Firm Fixed Price
History Package Development - Option III
Printing Package from Form Sets - Option III
Reprints - Option III
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Standard General Mark-up Language (SGML) Sustainment - Option III
Digitized Delivery of Change/Revision Page - Option III
Reprints - Option III
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Firm Fixed Price
Convert Tech Order from Digital - Option III
Maintenance and Storage of Technical Manuals - Option III
Update Tech Manual Indexed Portable Doc File (IPDF) - Option IV
R499 Update Tech Manual Indexed Portable Doc File (IPDF) in accordance with the Performance Work Statement.
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Convert Paper Tech Manuals to IPDF Files - Option III
Enhance Poor Quality IPDF File - Option III
Update Tech Manual Indexed Portable Doc File (IPDF) - Option IV
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Firm Fixed Price
Convert Paper Document to Digital Editable File - Option III
Convert Technical Orders in Digital Form to IPDF - Option III
Convert Paper to Standard General Mark-Up Language (SGML) - Option III
Convert Paper to Standard General Mark-Up Language (SGML) in accordance with the Performance Work Statement.
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Stock, Store, and Issue TO's - Option III
Digital Data Conversion to SGML Option III
Convert Paper to Standard General Mark-Up Language (SGML) - Option III
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
IN ACCORDANCE WITH THE REQUIREMENTS SET FORTH ON THE DD FORM 1423 (EXHIBITS A) ATTACHED AND MADE A PART
This CLIN is to support Government directed travel. The contractor shall provide travel in accordance with (IAW) the PWS.
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection Class I ODS Substance Application/Use Quantity None
Travel Cost Reimbursement - Option III
CDRLs - Option III
Contracting Officer representative (COR) and approved by the Procuring Contracting Officer. Travel requirements will be identified, proposed, and negotiated in individual task orders on a cost-reimbursement basis as the requirement for travel upon occurrence
In accordance with FAR 31.205-46(a)(2), costs incurred by the contractor for authorized travel shall be reimbursed to the extent that they do not exceed, on a daily basis, per diem rates set forth in the Joint
Travel Regulations (JTR). Travel expenses such as air fare, ground transportation, and per diem costs in direct support of this TO will be issued under the applicable travel CLIN.
Option Year IV
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Text Change to Illustration IV
Text Change - Option IV
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Inspection/Acceptance Report: Receiving Report Required
Quality Assurance: Commercial Item Inspection
Firm Fixed Price
Revised Illustration - Option IV
Technical Page Development from Source Data - Option IV
New Illustration - Option IV
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Printing Package from Form Sets - Option IV
Pre-Publication Review Copy - Option IV
New Illustration - Option IV
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Inspection/Acceptance Report: Receiving Report Required
Quality Assurance: Commercial Item Inspection
Firm Fixed Price
Reprints - Option IV
History Package Development - Option IV
Digitized Delivery of Change/Revision Page - Option IV
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Quantity
Maintenance and Storage of Technical Manuals - Option IV
Standard General Mark-up Language (SGML) Sustainment - Option IV
Digitized Delivery of Change/Revision Page - Option IV
Inspection: Destination Acceptance: Destination
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection Class I ODS Substance Application/Use Quantity None
Item No.
Firm Fixed Price
Estimated Quantity
U/I Unit Price Estimated Total Price
ZP To be Determined
ZP equals Firm Fixed Price Per Page Convert Tech Order from Digital in accordance with the Performance Work Statement.
Limitations of Liability: Other Than High Value Item
Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection Class I ODS Substance Application/Use Quantity None
Item No.
Firm Fixed Price
Estimated Quantity
U/I Unit Price Estimated Total Price
3,650 ZP To be Determined
ZP equals Firm Fixed Price Per Page R499 Update Tech Manual Indexed Portable Doc File (IPDF) in accordance with the Performance Work Statement.
Limitations of Liability: Other Than High Value Item
Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection Class I ODS Substance Application/Use Quantity None
Item No.
Update Tech Manual Indexed Portable Doc File (IPDF) - Option IV
Convert Tech Order from Digital - Option IV
Enhance Poor Quality IPDF File - Option IV
Firm Fixed Price Estimated Quantity
U/I Unit Price Estimated Total Price
ZP To be Determined
Firm Fixed Price Per Page Enhance Poor Quality IPDF File in accordance with the Performance Work Statement.
Limitations of Liability: Other Than High Value Item
Inspection: Destination
Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection Class I ODS Substance Application/Use Quantity None
Item No.
Firm Fixed Price
Estimated Quantity
U/I Unit Price Estimated Total Price
ZP To be Determined
ZP equals Firm Fixed Price Per Page Convert Paper to IPDF in accordance with the Performance Work Statement.
Limitations of Liability: Other Than High Value Item
Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection Class I ODS Substance Application/Use Quantity None
Item No.
Firm Fixed Price
Estimated Quantity
U/I Unit Price Estimated Total Price
ZP To be Determined
ZP equals Firm Fixed Price Per Page Convert Digital to IPDF in accordance with the Performance Work Statement.
Limitations of Liability: Other Than High Value Item
Convert Technical Orders in Digital Form to IPDF - Option IV
Convert Paper Tech Manuals to IPDF Files - Option IV
Enhance Poor Quality IPDF File - Option IV
Inspection: Destination Acceptance: Destination
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection Class I ODS Substance Application/Use Quantity None
Item No.
Firm Fixed Price
Estimated Quantity
U/I Unit Price Estimated Total Price
ZP To be Determined
ZP equals Firm Fixed Price Per Page Convert Paper to Digital Editable File in accordance with the Performance Work Statement.
Limitations of Liability: Other Than High Value Item
Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection Class I ODS Substance Application/Use Quantity None
Item No.
Firm Fixed Price
Estimated Quantity
U/I Unit Price Estimated Total Price
ZP To be Determined
ZP equals Firm Fixed Price Per Page Convert Paper to Standard General Mark-Up Language (SGML) in accordance with the Performance Work Statement.
Limitations of Liability: Other Than High Value Item
Inspection: Destination
Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection Class I ODS Substance Application/Use Quantity None
Item No.
Firm Fixed Price
Convert Paper to Standard General Mark-Up Language (SGML) - Option IV
Convert Paper Document to Digital Editable File Option IV
Digital Data Conversion to SGML - Option IV
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
IN ACCORDANCE WITH THE REQUIREMENTS SET FORTH ON THE DD FORM 1423 (EXHIBITS A) ATTACHED AND MADE A PART
CDRLs - Option IV
Stock, Store, and Issue TO's - Option IV
Digital Data Conversion to SGML - Option IV
A001 Contractor Held Conferences/Meetings – Official Minutes
A002 Contract Funds Status Report
A003 Technical Reports/Services
A004 Inventory/Utilization Data Report
Item No.
Cost Reimbursement - No Fee
Quantity U/I Estimated Unit Price Amount 1 LO To be Determined
Travel Cost Reimbursement This CLIN is to support Government directed travel. The contractor shall provide travel in accordance with (IAW) the PWS.
Limitations of Liability: Other Than High Value Item
Inspection: Destination
Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Commercial Item Inspection
Class I ODS Substance Application/Use Quantity None
The Contractor may be required to travel in support of task order (TO) requirements. Travel requirements will be reimbursed by separate voucher and must be coordinated in advance with the
Contracting Officer representative (COR) and approved by the Procuring Contracting Officer. Travel requirements will be identified, proposed, and negotiated in individual task orders on a cost-reimbursement basis as the requirement for travel upon occurrence
In accordance with FAR 31.205-46(a)(2), costs incurred by the contractor for authorized travel shall be reimbursed to the extent that they do not exceed, on a daily basis, per diem rates set forth in the Joint
Travel Regulations (JTR). Travel expenses such as air fare, ground transportation, and per diem costs in direct support of this TO will be issued under the applicable travel CLIN.
For purposes of this contract, the Government under no circumstances will pay per diem for a
Travel Cost Reimbursement - Option IV
File details come from the government source that posted it.