Question_and_Answer_for_only_question_submitted_as_of_5-22-15.docx
DOCX document 14 KB Posted
- Attached to
- Repair Roof, Dining Hall, B213
- Solicitation number
- FA6712-15-B-0004
About this file
Question concerning tapered insulation with Government Response
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FA6712-15-B-0004-0001.pdf | ||
| FA6712-15-B-0004-0002.pdf | ||
| Site_Visit_Sign_in_Sheet_for_13_May_2015.pdf | ||
| WD_-_PA150001_dated_2-13-15.docx | DOCX document | |
| Repair_Roof_Plan_Drawings_A-2_A.pdf | ||
| Specs_-_11-0007_Repair_Roof_B213.pdf | ||
| FA6712-15-B-0004.pdf | ||
| Repair_Roof_Plan_Drawings_A-1_R.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question and Answer for only question submitted as of 5/26/2015:
QUESTION:
In studying the specifications and drawings I have come up with a question on the tapered insulation that I feel needs clarification. The drawings show a constant edge of 5". The specs specify 1-1/2" minimum and 1/4" per foot slope.
Based upon drain locations, I believe that the edge could be a constant 6" using 1/8" per foot slope and maintain the 1-1/2" minimum, or using 1/4" per foot slope. The edge would have to increase to about 10-1/2"; that thickness could cause more mechanical work.
GOVERNMENT ANSWER:
We have reviewed the below questions on site and determined that the option of using 1/8" per foot slope, maintaining the 1-1/2" minimum, and having a constant edge of 6" per below is preferred as this is likely closest to the current roof condition and would minimize impacts to the structure.