Combine_Questions_and_Answers_Group_2_dated_10May2019.pdf
PDF 15 KB Posted
- Attached to
- Repair, Replace, Maintenance - Multiple HVAC Systems Federal contract opportunity
- Solicitation number
- FA667519RA012
About this file
Second group of answers to questions posed to the government.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation_Amendment_FA667519RA0120002_SF_30.pdf | ||
| Solicitation_Amendment_FA667519RA0120001_SF_30.pdf | ||
| FA667519RA012_Combined_Responses_to_Questions_2May2019.pdf | ||
| FA667519RA012_B1660_VRF_Design.pdf | ||
| FA667519RA012_B1651_Mechanical_Prints.pdf | ||
| FA667519RA012_B1643_Drawings.pdf | ||
| FA667519RA012_Site_Visit_Attendees.pdf | ||
| FA667519RA012_Multiple_HVAC_Repairs_Solicitation_12Apr2019.pdf | ||
| FA667519RA012_Multiple_HVAC_Repairs_Site_Wage_Determination_9April2019.pdf | ||
| FA667519RA012_Multiple_HVAC_Repairs_RFI_Form.pdf | ||
| FA667519RA012_Multiple_HVAC_Repairs_Statement_of_Work_11Apr2019.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA667519RA012 Multiple HVAC Repairs 10 May 2019
Combined Questions and Answers #2
Question 1: Section L of the solicitation includes instructions for the submission of (1) electronic & (1) physical proposal, but the SF1442 indicates a requirement for (2) physical proposals [1 original & 1 copy]. What is the required quantity of physical proposals?
Answer 1: (1) Electronic & (1) Physical proposal must be submitted.
Question 2: Is it sufficient to post mark the physical proposal(s) & email the electronic proposal by 1:00PM Monday 5/13/19 or do both need to be received by the specified date/time?
Answer 2: We must have the physical and electronic proposal in our possession by the closing date and time listed in the solicitation.
Question 3: Section B of the solicitation includes unit pricing for items (0001) Buildings with HVAC PM & (0002) Buildings with HVAC Repair/Replacement. However, Buildings 1643, 1651, & 1660 (VRFs) listed under Section C are not accounted for. Should pricing for Buildings 1643, 1651, & 1660 (VRFs) be included under item 17 of the SF1442 or not at all?
Answer 3: Buildings 1643, 1651, and 1660 are sustainment services per the SOW and should be included in the price of CLIN 0001. The total price you input into block 17 of the SF1442 should include the price to perform the entirety of the statement of work. The solicitation has been amended to reflect the 3 buildings in CLIN 0001.