Attachment_1_-_Spec_-_Bldg_807.pdf

PDF 11 MB Posted

Attached to
Construct Addition to Command Post & Renovate Facility for Command Post Bldg. 807 Federal contract opportunity
Solicitation number
FA6670-15-B-0002
Issued by
Department of the Air Force Reserve Command

About this file

Attachment 1 - Spec - Bldg 807

View the file

Other files for this federal contract opportunity

Other files attached to Construct Addition to Command Post & Renovate Facility for Command Post Bldg. 807, newest first.
File Type Posted
807_-_Bid_Opening_Sign_in_Sheet.pdf PDF
807_-_Abstract_from_Bid_Opening.pdf PDF
Attachment_3_-_DB_Building_-_17_July_2015.pdf PDF
807_-_Qs_Set_1_22_July_2015.pdf PDF
807_-_Addendum__01_and_pg_A-200_rev_1.pdf PDF
807_-_Amendment_1.pdf PDF
807_-_Qs_Set_2_27_July_2015.pdf PDF
Attachment_4_-_Insurance_Cert.pdf PDF
807_-_FA6670-15-B-0002.pdf PDF
Attachment_2_-_Drawings_-_Bldg_807.pdf PDF
Attachment_3_-_DB_Building_-_5_June_2015.pdf PDF
Attachment_5_-_EAL_-_Ctr_template.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCT ADDITION TO COMMAND POST & RENOVATE

FACILITY FOR COMMAND POST BLDG. 807 RVKQ14-0607 A & B

PROJECT TABLE OF CONTENTS

DIVISION 01 – GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK 01 11 00-1 THRU 01 11 00-8

01 30 00 ADMINISTRATIVE REQUIREMENTS 01 30 00-1 THRU 01 30 00-4

01 33 00 SUBMITTAL PROCEDURES 01 33 00-1 THRU 01 33 00-7

SUBMITTAL LIST

AF-FORM 3000, MATERIAL APPROVAL SUBMITTAL

01 45 35 SPECIAL INSPECTIONS 01 45 35-1 THRU 01 45-4

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND

CONTROLS 01 50 00-1 THRU 01 50 00-4

01 57 20.00 10 ENVIRONMENTAL MANAGEMENT AND 01 57 20.00 10-1 THRU

PROTECTION 01 57 20.00 10-16

WASTE RECYCLED MATERIALS LOG FOR

CONTRACTORS A1-1

QUICK REFERENCE GUIDE FOR

OFF STATION CONTRACTORS AND SUPPLIERS A2-1 THRU A2-4

SWPPP STORM WATER PREVENTION & EROSION

& SEDIMENT CONTROL PLAN A-3-1 THRU A-3-7

STANDARD OPERATING PROCEDURE for

CONTRACTOR REMOVAL OF LAMPS/BALLASTS A4-1 THRU A4-3

01 62 35 RECYCLED/RECOVERED MATERIALS 01 62 35-1 THRU 01 62 35-1

01 74 19 CONSTRUCTION AND DEMOLITION WASTE

MANAGEMENT 01 74 19-1 THRU 01 74 19-5

01 78 00 CLOSEOUT SUBMITTALS 01 78 00-1 THRU 01 78 00-11

01 78 23 OPERATION AND MAINTENANCE DATA 01 78 23-1 THRU 01 78 23-9

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION 02 41 00-1 THRU 02 41 00-10

DIVISION 03 – CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE 03 30 00-1 THRU 03 30 00-36

DIVISION 04- MASONRY

04 20 00 MASONRY 04 20 00-1 THRU 04 20 00-22

DIVISION 05- METALS

05 12 00 STRUCTURAL STEEL 05 12 00-1 THRU 05 12 00-11

05 21 19 OPEN WEB STEEL JOIST FRAMING 05 12 19-1 THRU 05 12 19-3

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 ROUGH CARPENTRY 06 10 00-1 THRU 06 10 00-9

DIVISION 07- THERMAL AND MOISTURE PROTECTION

07 21 13 BOARD AND BLOCK INSULATION 07 21 13-1 THRU 07 21 13-5

07 22 00 ROOF AND DECK INSULATION 07 22 00-1 THRU 07 22-00-7

07 53 23 ETHYLENE-PROPYLENE-DIENE-MONOMER

ROOFING 07 53 23-1 THRU 0753 23 -14

FACILITY FOR COMMAND POST BLDG. 807 RVKQ14-0607 A & B

07 60 00 FLASHING AND SHEET METAL 07 60 00-1 THRU 07 60 00-6

07 84 00 FIRESTOPPING 07 84 00-1 THRU 07 84 00-6

07 92 00 JOINT SEALANTS 07 92 00-1 THRU 07 92 00-6

DIVISION 08 – OPENINGS

08 11 13 STEEL DOORS AND FRAMES 08 11 13-1 THRU 08 11 13-5

08 14 00 WOOD DOORS 08 14 00-1 THRU 08 14 00-4

08 71 00 DOOR HARDWARE 08 71 00-1 THRU 08 71 00-5

DIVISION 09 – FINISHES

09 29 00 GYPSUM BOARD 09 29 00-1 THRU 09 29 00-5

09 51 00 ACOUSTICAL CEILINGS 09 57 00-1 THRU 09 51 00-7

09 69 13 RIGID GRID ACCESS FLOORING 09 63 13-1 THRU 09 63 13--11

09 90 00 PAINTS AND COATINGS 09 90 00-1 THRU 09 90 00-14

DIVISION 11- EQUIPMENT

11 26 00 UNIT KITCHEN 11 26 00-1 THRU 11 26 00-5

DIVISION 13 – SPECIAL CONSTRUCTION

13 48 00 SEISMIC PROTECTION FOR MISCELLANEOUS EQUIP. 13 48 00-1 THRU 13 48 00-7

13 48 00.00 10 SEISMIC PROTECTION FOR MECHANICAL EQUIPMENT 13 48 00.00 10-1 THRU 13 48

00.00 10-6

DIVISION 21 – FIRE SUPPRESSION

21 13 00.00 40 FIRE-SUPPRESSION SPRINKLER SYSTEMS 21 13 00.00 40-1 THRU

21 13 00 00 40-10

DIVISION 22 – PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE 22 00 00-1 THRU 22 00 00-25

22 07 19.00 40 PLUMBING PIPING INSULATION 22 07 19.00 40-1 THRU

22 07 19.00 40-6

22 11 25 FACILITY GAS PIPING 22 11 25-1 THRU 22 11 25-12

DIVISION 23- HEATING, VENTILATION AND AIR CONDITIONING

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION 23 00 00-1 THRU 23 00 00-21

AND EXHAUST SYSTEMS

23 01 30.41 HVAC SYSTEM CLEANING 23 01 30.41-1 THRU 23 01 30.41-7

23 03 00.00 20 BASIC MECHANICAL MATERIALS 23 03 00.00 20-1 THRU 23 03

AND METHODS 00.00 20-4

23 05 15 COMMON PIPING FOR HVAC 23 05 15-1 THRU 23 05 15-11

23 05 48.00 40 VIBRATION AND SEISMIC CONTROLS 23 05 48.00 40-1 THRU

FOR HVAC PIPING AND EQUPIMENT 23 05 48.00 40-4

23 05 93 TESTING, ADJUSTING AND BALANCING 23 05 93-1 THRU 23 05 93-21

FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL 23 07 00-1 THRU 23 07 00-21

SYSTEMS

23 08 00.00 10 COMMISSIONING OF HVAC SYSTEMS 23 08 00.00 10-1 THRU

23 08 00.00 10-10

23 23 00 REFRIGERANT PIPING 23 23 00-1 THRU 23 23 00-13

23 31 13.00 40 METAL DUCTS 23 31 13.00 40-1 THRU

23 31 13.00 40-12

23 37 13.00 40 DIFFUSERS, REGISTERS AND GRILLS 23 37 13.00 40-1 THRU

23 37 13.00 40-3

FACILITY FOR COMMAND POST BLDG. 807 RVKQ14-0607 A & B

23 82 19.00 40 FAN COIL UNITS 23 82 19.00 40-1 THRU

23 82 19.00 40-5

DIVISION 26 – ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS 26 00 00.00 20-1 THRU

26 00 00.00 20-4

26 20 00 INTERIOR DISTRIBUTION SYSTEM 26 20 00-1 THRU 26 20 00-23

26 41 00 LIGHTNING PROTECTION SYSTEM 26 41 00-1 THRU 26 41 00-5

26 51 00 INTERIOR LIGHTING 26 51 00-1 THRU 26 51 00-10

DIVISION 27 – COMMUNICATIONS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING 27 10 00-1 THRU 27 10 00-16

SYSTEM

DIVISION 31 – EARTHWORK

31 00 00 EARTHWORK 31 00 00-1 THRU 31 00 00-15

31 23 00.00 20 EXCAVATION AND FILL 31 23 00.00 20-1 THRU

31 23 00.00 20-10

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 16 13 CONCRETE SIDEWALKS AND CURBS & GUTTERS 32 16 13-1 THRU 326 13-9

32 92 19 SEEDING 32 9219-1 THRU 32 9219-7

APPENDIX

Soil Borings Empire GEO Services Inc. dated November 2014

Refrigerant Accountability Report

SWPPP – Storm Water Pollution Prevention Plan

FACILITY FOR COMMAND POST BLDG. 807 RVKQ14-0607 A & B

SECTION 01 11 00 Page 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.1.1 PROJECT DESCRIPTION

The work to be performed under this contract consists of providing all plant, labor, material, and equipment necessary to complete the work described below and in the contract drawings and specifications at the 914th Airlift Wing, Niagara Falls Air Reserve Station.

1.1.2 Site Visit

The Contractor is solely responsible to attend the scheduled site visit and take measurements of existing conditions. Plans for the project are included as part of the bid package. Additional plans may be reviewed at the Office of the Base Civil Engineer located at Building 403.

1.1.3 Clean Work Site

The Contractor is solely responsible to clean the work site regularly during each work day as the work progresses, to prevent the accumulation of FOD (foreign object debris). All debris shall be placed in a dump truck and removed daily to prevent accumulation of debris at the demolition site and surrounding area.

1.1.4 Demolition Work Plan/Recycling/Salvaging/Waste Management Plans.

Contractor shall provide a work/demolition plan prior to starting any work indentifying universal and hazardous wastes and methods for handling and disposal. Work shall not proceed until the Contractor's work/demolition plan has been reviewed and approved by the Base Contracting Officer and/or his representatives. The work/demolition plan shall include the following:

a. The demolition plan shall be the following (where applicable): proposed method of demolition, recycling plan, engineering controls to reduce the amount of dust released to the air, disposal location, utilities capping plan, etc. The recycling plan shall also include documentation from each recycling center that the demolition Contractor will use for recycling. The recycling plan shall indicate which materials will be recycled at each center.

b. The recycling plan shall also include written certification (state, local, etc.) showing that the recycling center is approved to accept and has the capacity for each material listed to be recycled at their facility. The recycling plan shall indicate how the recycling facility/demolition Contractor will supply the net weights on each, material recycled. The documentation for each recycling center shall be on recycling center letterhead with original signature by the qualified recycling center representatives.

c. The salvaging plan shall list and identify all materials that are economically feasible to comply with the Air Force requirements for diversion of waste for construction projects. Fed diversion rates

1.1.5 Description of Work

The work to be accomplished by the Contractor shall include, but not be limited to the following items:

1.1.6 Demolition Work- General-A (Addition) and B (Renovations).

Remove existing 6” reinforced concrete slab and concrete retaining walls at the east entrance to the building.

SECTION 01 11 00 Page 2

Remove existing concrete barriers at East entrance.

Remove existing concrete sidewalks as noted on the drawings.

Remove and re-locate existing bike rack at East Entrance to building 807.

1.1.7 New Work – General

Replace existing 6” reinforced concrete slab and concrete retaining walls as noted on the drawings.

Provide new concrete sidewalk where noted on drawings.

Provide rigid insulated panels at the perimeter of the interior slab on grade.

Provide new insulated exterior hollow metal door, frame and hardware as noted on drawings.

Provide new painted interior metal and frames as noted shown on drawings.

Provide new 8” CMU with 4” face brick to match existing face brick.

Provide face brick “soldier” courses as noted on drawings.

Provide new metal furring and 5/8” gypsum wallboard at exterior walls with vinyl wall fabric as noted on drawings.

Provide new 3 5/8” metal stud and 5/8” gypsum wallboard with vinyl wall fabric partitions where noted on drawings.

Provide new 6” metal stud and 5/8” gypsum wallboard with vinyl wall fabric partitions where noted on drawings.

Provide 4” high resilient base as noted on drawings.

Provide new pre-finished solid core wood doors, hollow metal frames and finish hardware as noted on drawings.

Provide 2’ x 4’ suspended acoustical ceiling panels as noted on the drawings.

Provide, inspect, and maintain erosion and sediment control measures.

Provide new concrete sidewalks as noted on the drawings Relocate and reconnect existing site water and gas services.

Restore existing damaged lawn areas.

Provide earth berms as note on the drawings.

Provide temporary toilets.

Provide wood blocking and steel wall brackets for T.V wall monitors.

1.1.8 Demolition Work Fire Protection

Remove existing sprinklers in CAT 109 and associated piping for replacement.

1.1.9 New Work Fire Protection

Provide work indicated on drawings, in specifications, and as necessary for a complete and operational fire protection system.

Provide sprinklers, piping, and all associated accessories in the area of work. Extend existing piping as required.

1.1.10 Demolition Work Plumbing

Disconnect and remove existing non-freeze hose bib.

Disconnect and remove existing natural gas meter set.

Disconnect and remove existing underground natural gas piping below footprint of new addition for relocation.

1.1.11 New Work Plumbing

Provide work indicated on drawings, in specifications, and as necessary for a complete and operational plumbing system.

Provide new natural gas meter set (smart meter) in new location, including regulator. Provide piping to reconnect existing natural gas piping, including underground piping to generator.

Provide new vent, sanitary, domestic cold water, and domestic hot water piping for new sink, including all associated accessories. Provide domestic hot water recirculation piping to fixture. Tie into existing piping, including sanitary below slab.

SECTION 01 11 00 Page 3

Provide an under-counter lift pump for sink discharge for gravity drainage within ceiling space.

Provide vent through roof.

Provide new roof drain at addition. Provide piping to tie into existing storm leader.

Provide new non-freeze hose bibb at exterior. Extend piping as required.

Provide all disinfection, cleaning, testing, and adjusting as specified.

1.1.12 Demolition Work HVAC

Disconnect existing air-cooled condensing unit for relocation.

Disconnect and remove existing air handling unit and associated ductwork, piping, and refrigerant, including related louvers and dampers.

Disconnect existing emergency exhaust louver for relocation.

1.1.13 New Work HVAC

Provide work indicated on drawings, in specifications, and as necessary for a complete and operational HVAC systems.

Provide new mini-split system AC system for communications closet.

Re-install existing condensing unit onto roof.

Provide new fan-coil unit, including ductwork, hot water & refrigerant piping, etc, as well as related diffusers.

Reconnect existing ductwork to remain.

Provide new exhaust fan, ductwork, grilles, etc.

Provide new roof-mounted outdoor air intake.

Provide commissioning of HVAC systems.

1.1.14 Demolition Work Electrical

Remove existing lighting fixtures and lighting controls as noted on the drawings.

Remove existing receptacles and devices as noted on the drawings.

Remove and/or rework existing fire alarm system as noted on the drawings.

Remove existing equipment as noted on the drawings.

Remove conduit, wire, cabling, supports, etc. associated with the above.

1.1.15 New Work Electrical

Provide new electrical panelboard and feeder as noted on the drawings.

Provide new lighting fixtures as noted on the drawings.

Provide new lighting controls as noted on the drawings.

Provide new receptacles as noted on the drawings.

Provide new equipment disconnects/connections as noted on the drawings.

Provide new fire alarm/mass notification system components as noted on the drawings.

Provide new data/telcom devices and cabling as noted on the drawings.

Provide new lightning protection system components as noted on the drawings.

Provide new security and access control system components as noted on the drawings.

After construction, but before the contract is considered final, the Contractor shall supply an itemized list of materials recycled, including quantities, to the Base Contracting Officer (who in turn shall forward list to CEV).

The following items are an approximate list for items to be removed and inventoried for shipment to recycling centers.

a. Remove existing metal duct work in original building as noted on drawings and salvage for shipping to re-cycling center.

b. Remove existing roof top air handler in original building as noted on drawings and salvage for shipping to re-cycling center.

SECTION 01 11 00 Page 4

c. Remove existing copper refrigerant piping in original building as noted on drawings and salvage for shipping to re-cycling center.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes General Construction Work, Fire Suppression, Plumbing, HVAC (including controls), Electrical, Communications and Electronic, Lightning Protection, Safety and Security.

1.2.2 Location

The work will be performed at existing Building 807.

1.3 PROJECT ENVIRONMENTAL GOALS

Contractor shall distribute copies of the Environmental Goals to each subcontractor and the Contracting Officer. The overall goal for design, construction, and operation is to produce a building that meets the functional program needs and incorporate the principles of sustainability.

Specifically:

a. Preserve and restore the site ecosystem and biodiversity; avoid site degradation and erosion. Minimize offsite environmental impact.

b. Use the minimum amount of energy, water, and materials feasible to meet the design intent. Select energy and water efficient equipment and strategies.

c. Use environmentally preferable products and decrease toxicity level of materials used.

d. Use renewable energy and material resources.

e. Optimize operational performance (through commissioning efforts) in order to ensure Energy efficient equipment operates as intended. Consider the durability, maintainability, and flexibility of building systems.

f. Manage construction site and storage of materials to ensure no negative impact on the indoor environmental quality of the building.

g. Reduce construction waste through reuse, recycling, and supplier take-back.

1.4 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer.

At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.

SECTION 01 11 00 Page 5

1.5 LOCATION OF UNDERGROUND FACILITIES

Obtain digging permits prior to start of excavation by contacting the Contracting Officer ten (10) calendar days in advance. Scan the construction site with electromagnetic or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of underground or encased obstruction not indicated to be specified or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.5.1 Notification Prior to Excavation

Notify the Contracting Officer at least 10 days prior to starting excavation work. Contact “Dig Safe “ NY 48 hours prior to excavating. Contractor is responsible for marking all utilities not marked by “Dig Safe NY”.

1.6 CONTRACT DOCUMENTS

Dimensions on drawings shall be checked, for accuracy, by the Contractor. The Contractor shall determine exact dimensions for proper fit. Drawings shall not be construed as being detailed working drawings.

The following drawings accompany these specifications and is a part thereof:

T-01 Title Sheet, Location Map

C-1 Survey Existing Conditions C-2 Site Plan

S-01 Structural General Notes.

S-02 Abbreviations and Schedules.

S-03 Foundation Plan S-04 Roof Plan S-05 Foundation Details S-06 Foundation Details S-07 Roof Details S-08 Typical Masonry Details

A-100 Demolition Floor Plan and Elevations A-101 Construction Floor Plan A-102 Reflected Ceiling Plan A-103 Roof Plan and Details A-200 Wall Sections and Elevations A-300 Door and Finish Information

F-101 Fire Suppression Floor Plans

P-101 Plumbing Floor Plan

M-101 Mechanical Floor Plan

E-001 Electrical Symbol List, Details and Schedules Floor Plan E-101 Overall First Floor Plan-Electrical E-102 Electrical Plans E-103 Enlarged Electrical Plans E-601 One-Line Diagram, Details, and Schedules

SECTION 01 11 00 Page 6

One (1) set of contract drawings and specifications will be furnished to the Contractor in electronic or paper media without charge. Reference publications will not be furnished.

The Contractor shall immediately check furnished drawings and Specifications and notify the Government of any discrepancies.

1.7 WORK RESTRICTIONS

The Contractor shall not be allowed to work on Federal Holidays or when the Base is closed due to inclement weather.

1.7.1 Normal Duty Hours

Normal duty hours for work shall be 7:15 a.m. to 4:00 p.m., Monday through Friday. Requests for additional working hours, beyond the normal duty hours, shall be submitted by the Contractor to the Contracting Officer seven (7) days in advance of the proposed work period. This request for additional time shall require written approval from the Contracting Officer.

1.7.2 Notice to Commence Work

The Contractor shall give the Contracting Officer or his representative a 48 hour notice of the Contractor’s intent to commence work.

1.7.3 Daily Sign-In Sheet

Prior to starting the work each day, the Contractor and/or subcontractor must fill out the Sign-In sheet located at the 914th AW, Base Civil Engineering Office Building 403.

1.8 ON-SITE PERMITS

1.8.1 Utility Outages and Connections

Work shall be scheduled to hold outages to a minimum. The Contracting Officer may permit outages at his discretion.

Requests for utility outages and connections shall be made in writing to the Contracting Officer at least seven (7) working days in advance of the time required. Each request shall state the system involved, area involved, approximate duration of outage, and the nature of the work involved.

The Contractor and/or subcontractor shall coordinate any power shut downs with the Government. Any additional costs related to overtime, premium pay or impacts shall be paid by the Contractor at no increase to the contract.

1.8.2 Borrow, Digging, Welding, Burning Permits, and use of fire hydrants/water supply from outside a facility.

ACTIVITY SUBMISSION DATE SUBMISSION FORM

Borrow 10 days prior to work from Civil Engineering Dept. AF 103 Bldg. 403.

Digging 10 days prior to work from Civil Engineering Dept. AF 103 Bldg. 403.

Welding Each day prior to work from Base Fire Station Bldg. 821

SECTION 01 11 00 Page 7

Burning Each day prior to work from Base Fire Chief Bldg. 821

Permits shall be posed at a conspicuous location in the construction area.

Permits are the property of the Government and shall be returned to the Contracting Officer upon completion of permitted work.

The Contractor is responsible for hand excavation within 3’-0” from either side of all known utilities that have been either staked or marked from the scaled drawings.

Burning of trash is not permitted.

Use of explosives shall not be permitted.

1.9 REMOVAL OF WASTE MATERIAL

During the progress and at the completion of work, all refuse and waste material shall be removed from Government property and disposed according to Federal, State, and Local environmental regulations. If waste material is not removed daily, the Contractor shall provide a covered waste container at his expense. The 914 MSG/CEV will provide the contractor containers to collect hazardous and universal wastes

1.10 UTILITIES

Electricity and water shall be provided by the Government. Any extension of, or corrections to, the existing lines and their removal will be at the expense of the Contractor. All connections to existing utilities, if necessary, shall be coordinated with the Government. The Contractor is responsible for supplying his own temporary toilet facilities.

1.11 SPECIAL CONDITIONS

Upon initiation of construction work, the Contractor will replace all exterior door keys with construction cores.

One (1) additional key will be provided to the Base Civil Engineer representative.

1.12 REMOVAL OF WASTE MATERIAL

During the progress and at the completion of work, all refuse and waste material shall be removed from Government property and disposed of according to Federal, State and Local Environmental regulations.

1.13 WAYBILLS AND DELIVERY TICKETS

The Contractor shall submit, to the Contracting Officer, waybills and delivery tickets for all materials delivered to the job site.

1.14 CONTRACTORS SUBMITTALS

Itemized below is a list of materials requiring drawings, wiring diagrams, certifications, manufacturer’s literature, data brochures, technical data and samples as noted to be submitted to the Contracting Officer by the Contractor for approval using AF Form 3,000. Approval must be obtained from the Contracting Officer prior to operating instructions, as noted, shall be made no longer than 10 days after receipt by AF Form 3000. If submittals cannot be made within 10 days after Notice to Proceed, or as specified by the Contracting Officer, the Contracting Officer shall be advised of the difficulty and an extension of the time requested. Approval of submittals does not relieve the Contractor from performance in strict accordance with the contract specifications and drawings, not does such approval constitute “acceptance” under other provisions of this contract. Warranties and operating instructions shall be provided unless otherwise specified. Materials requiring submittals are as follows:

SECTION 01 11 00 Page 8

SPECIFICATIONS TYPE OF SUBMITTAL

DESCRIPTION

OF SECTION PARA SHOP OPER

SUBMITTALS NO. NO. LITERATURE SAMPLE DWG INST CERTIFICATE

PART 2 ENVIRONMENTAL PROTECTION REQUIREMENTS

2.1 Refer to specification Section 01 57 20.00 10 ENVIRONMENTAL MANAGEMENT AND PROTECTION for project requirements. Any questions concerning environmental conditions or problems shall be referred to 914th AW/CEV at 236-3125.

PART 3 SPECIAL CONDITIONS

3.1 The contractor shall supply the Base Contracting Officer with a list of quantities of materials used and removed prior to final acceptance of the project completion. The Contractor shall use the areas designated by the Contracting Officer for storage of materials and vehicles. The Contractor shall submit to the Contracting Officer, for approval, a sequence and schedule of work.

-- End of Section--

FACILITY FOR COMMAND POST BLDG. 807 RVKQ 14-0607 A & B

SECTION 01 30 00 Page 1

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

15 CFR 772 Definition of Terms

15 CFR 773 Special Licensing Procedures

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of contact personnel; G

View location map; G

Progress and completion pictures; G

1.3 MINIMUM INSURANCE REQUIREMENTS

Procure and maintain during the entire period of performance under this contract the following minimum insurance coverage as addressed in FAR 28.307-2 including by FAR Clause 52.228-5 “Insurance-Work on a Government Installation” and others as required by State Law.

1.4 CONTRACTOR PERSONNEL REQUIREMENTS

1.4.1 Subcontractors and Personnel

Furnish a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.4.2 Identification Badges

Identification badges, if required, will be furnished without charge. Application for and use of badges will be as directed. Immediately report instances of lost or stolen badges to the Contracting Officer.

1.4.3 Contractor Personnel Requirements

Failure to obtain entry approval will not affect the contract price or time of completion.

SECTION 01 30 00 Page 2

1.4.3.1 Personnel List

Submit for approval, at least 15 days prior to the desired date of entry, an original alphabetical list of personnel who require entry into Government property to perform work on the project. Furnish for each person:

a. Name

b. Date and place of birth

c. Citizenship

d. Home address

e. Social security number

The request for personnel passes shall be accompanied with the following certification:

"I hereby certify that all personnel on this list are either born U.S. citizens, naturalized U.S. citizens with the naturalization number shown."

Signature/Firm Name

1.4.3.2 Citizenship Requirements

Personnel will not be admitted to the work site without approval. Work under this contract is restricted to U.S.

citizens.

1.4.3.3 Documents Acceptable for Proof of Citizenship

a. Birth registration card

b. Certificate of live birth, birth certificate

c. Certificate of Naturalization

d. Certificate of registration

e. DD-214 (Must Cite Birthplace)

f. DD Form 4 (Contract for Enlistment and Must Cite Birthplace)

g. DD 1966 (Application for Enlistment)

h. Military discharge papers (must cite birthplace)

i. Delayed birth certificate

j. Hospital birth certificate

k. Marriage license certificate

l. Merchant marine certificate

m. Military officer ID card

n. Notification of birth registration

SECTION 01 30 00 Page 3

o. USA passport

1.4.3.4 Vehicle List

Submit an original list of vehicles to be utilized at the work site with the following information for each vehicle:

a. Make

b. Year

c. Model

d. License number

e. Registered owner

1.4.3.5 Passes

Submit request for personnel and vehicle passes together. Include the Certificate of Insurance for Contractor and Subcontractor(s) and the Statement of Acknowledgement Form SF 1413 with the submittal. Passes will normally be issued within 21 days.

1.4.3.6 Control

Maintain strict accountability over passes. Immediately report to the source of issue, passes missing or lost and the circumstances. If the Contractor has another active contract or one commencing immediately, employees' names may be transferred from one contract to the other. Final payment will not be effected until employees are transferred to another contract or the records are cleared. Furnish a signed letter, countersigned by the source of issue, stating that passes have been turned in.

1.5 SUPERVISION

Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, if a Quality Control (QC) representative is required on the contract, then that individual shall also have fluent English communication skills.

1.6 PRECONSTRUCTION CONFERENCE

After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule prices, shop drawings, and other submittals, scheduling programming, and prosecution of the work. Major subcontractors who will engage in the work shall also attend.

1.7 AVAILABILITY OF CADD DRAWING FILES

After award and upon request, the electronic "Computer-Aided Drafting and Design (CADD)" drawing files will only be made available to the Contractor for use in preparation of construction data related to the referenced contract subject to the following terms and conditions. Request specific drawing numbers of files required; the entire set of drawing files will not be provided.

Data contained on these electronic files shall not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor shall make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor shall, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.

SECTION 01 30 00 Page 4

These electronic CADD drawing files are not construction documents. Differences may exist between the CADD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CADD files, nor does it make representation to the compatibility of these files with the Contractors hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished CADD files, the signed and sealed construction documents shall govern. The Contractor is responsible for determining if any conflict exists. Use of these CADD files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.

If the Contractor uses, duplicates and/or modifies these electronic CADD files for use in producing construction data related to this contract, all previous indicia of ownership (seals, logos, signatures, initials and dates) shall be removed.

1.8 ELECTRONIC MAIL (E-MAIL) ADDRESS

The Contractor shall establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats. Within 10 days after contract award, the Contractor shall provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes, terrorist threats, etc. Multiple email address will not be allowed.

It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to this email address.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

-- End of Section --

FACILITY FOR COMMAND POST BLDG. 807 RVKQ14-0607 A & B

SECTION 01 33 00 Page 1

SECTION 01 33 00

SUBMITTAL PROCEDURES

1.1 SUMMARY

Requirements of this Section apply to, and are a component part of, each section of the specifications.

1.2 REFERENCES (NOT APPLICABLE)

1.3 SUBMITTALS

A standard transmittal form provided by the Government shall be used to transmit each submittal.

Submittal Description (SD): Drawings, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance and test data, and similar materials to be furnished by the Contractor explaining in detail specific portions of the work required by the contract.

The following items, SD-01 through SD-11, are descriptions of data to be submitted for the project. The requirements to actually furnish the applicable items will be called out in each specification.

SD-01 Preconstruction Submittals

Submittals which are required prior to a notice to proceed on a new contract. Submittals required prior to the start of the next major phase of the construction on a multi-phase contract. Schedules or tabular list of data or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work, submitted prior to contract notice to proceed or next major phase of construction.

SD-02 Shop Drawings

Submittals which graphically show relationship of various components of the work, schematic diagrams of systems, detail of fabrications, layout of particular elements, connections, and other relational aspects of the work.

SD-03 Product Data

Data composed of catalog cuts, brochures, circulars, specifications and product data, and printed information in sufficient detail and scope to verify compliance with requirements of the contract documents.

SD-04 Samples

Samples, including both fabricated and unfabricated physical examples of materials, products, and units of work as complete units or as portions of units of work.

SD-05 Design Data

Design calculations, mix design analyses, or other data, written in nature, and pertaining to a part of the work.

FACILITY FOR COMMAND POST BLDG. 807 RVKQ14-0607 A & B

SECTION 01 33 00 Page 2

SD-06 Test Reports

Written reports of a manufacturer's findings of his product during field inspections, attesting that the products are installed in accordance with the manufacturer's installation instructions, shop drawings, or other manufacturer's requirements. Written reports by a general Contractor or his subcontractors including daily logs reporting on the progress of daily activities or attesting that the work has been installed in accordance with the contract plans and specifications.

SD-07 Certificates

A document, required of the Contractor, or through the Contractor by way of a supplier, installer, manufacturer, or other Lower Tier Contractor, the purpose of which is to further the quality or orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel, qualifications, or other verification of quality.

Statements signed by responsible officials of a manufacturer of a product, system, or material attesting that the product, system or material meet specified requirements. Statements must be dated after the award of this contract, name the project, and list the specific requirements which it is intended to address.

SD-08 Manufacturer's Instructions

Preprinted material describing installation of a product, system, or material, including special notices and material safety data sheets, if any concerning impedances, hazards, and safety precautions.

SD-09 Manufacturer's Field Reports

A written report which includes the findings of a test made at the job site, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation. Report must be signed by an authorized official of a testing laboratory or agency and must state the test results; and indicate whether the material, product, or system has passed or failed the test.

SD-10 Operation and Maintenance Data

Data intended to be incorporated in an operations and maintenance manual.

SD-11 Closeout Submittals

Special requirements necessary to properly close out a construction contract. For example, as-built drawings, manufacturer's help and product lines necessary to maintain and install equipment. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.

1.4 PREPARATION

1.4.1 Marking

Permanent marking shall be provided on each submittal to identify it by contract number; transmittal date;

Contractor's, Subcontractor's, and supplier's name, address(es) and telephone number(s); submittal name;

specification or drawing reference; and similar information to distinguish it from other submittals. Submittal identification shall include space to receive the review action by the Contracting Officer.

1.4.2 Data Format

Required data submittals for each specific material, product, unit of work, or system shall be collected into a single submittal and marked for choices, options, and portions applicable to the submittal. Marking of each

FACILITY FOR COMMAND POST BLDG. 807 RVKQ14-0607 A & B

SECTION 01 33 00 Page 3 copy of product data submitted shall be identical. Partial submittals will not be accepted for expedition of construction effort.

1.4.3 Samples

Samples shall be physically identical with the proposed material or product to be incorporated in the work, fully fabricated and finished in the specified manner, and full scale. Where variations in color, finish, pattern, or texture are inherent in the material or product represented by the sample, multiple units of the sample, showing the near-limits of the variations and the "average" of the whole range (not less than 3 units), shall be submitted.

Each unit shall be marked to describe its relation to the range of the variation. Where samples are specified for selection of color, finish, pattern, or texture, the full set of available choices shall be submitted for the material or product specified. Sizes and quantities of samples shall represent their respective standard unit.

1.5 SUBMISSION REQUIREMENTS

1.5.1 Schedules

Within 10 days of notice to proceed, the Contractor shall provide, for approval by the Contracting Officer, the following schedule of submittals:

a. A schedule of shop drawings and technical submittals required by the specifications and drawings.

Schedule shall indicate the specification or drawing reference requiring the submittal; the material, item, or process for which the submittal is required; the "SD" number and identifying title of the submittal; the Contractor's anticipated submission date and the approval need date.

b. A separate schedule of other submittals required under the contract but not listed in the specifications or drawings. Schedule will indicate the contract requirement reference; the type or title of the submittal; the Contractor's anticipated submission date and the approved need date (if approval is required).

c. Submittals called for by the contract documents will be listed on one of the above schedules. If a submittal is called for but does not pertain to the contract work, the Contractor shall include it in the applicable schedule and annotate it "N/A" with a brief explanation. Approval of the schedules by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but which have been omitted from the schedules or marked "N/A".

d. Copies of both schedules shall be re-submitted monthly annotated by the Contractor with actual submission and approval dates. When all items on a schedule have been fully approved, no further re-submittal of the schedule is required.

1.5.2 Data Submittals

Four (4) complete sets of indexed and bound product data shall be submitted. One set, marked with review notations by the Contracting Officer, will be returned to the Contractor.

1.5.3 Samples

One set of identified samples shall be submitted. A copy of the transmittal form, marked with review notations including selections by the Contracting Officer, will be returned to the Contractor.

Samples that are intended or permitted to be returned and actually incorporated in the work are so indicated in the individual technical sections. These samples will be returned to the Contractor, at his expense, to be clearly labeled, with installation location recorded. Samples shall be in undamaged condition at the time of installation.

Where mockups and similar large samples are required by individual technical sections, it is recognized that these are a special type of sample which cannot be readily "transmitted" as specified for submittal of samples.

FACILITY FOR COMMAND POST BLDG. 807 RVKQ14-0607 A & B

SECTION 01 33 00 Page 4

Otherwise, and except as indicated in the individual technical sections, the requirements for samples shall be complied with and a transmittal form shall be processed for each mockup, to provide a record of the activity.

1.6 GOVERNMENT'S REVIEW

1.6.1 Review Notations

Contracting Officer will review submittals and provide pertinent notation within 10 calendar days after date of submission. Submittals will be returned to the Contractor with the following notations:

a. Submittals marked "approved" authorize the Contractor to proceed with the work covered.

b. Submittals marked "approved as noted" authorize the Contractor to proceed with the work covered provided he takes no exception to the corrections. Notes shall be incorporated prior to submission of the final submittal.

c. Submittals marked "return for correction" require the Contractor to make the necessary corrections and revisions and to re-submit them for approval in the same routine as before, prior to proceeding with any of the work depicted by the submittal.

d. Submittals marked "not approved" or "disapproved" indicate noncompliance with the contract requirements and shall be re-submitted with appropriate changes. No item requiring a submittal shall be accomplished until the submittals are approved or approved as noted.

e. Contractor shall make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the clause entitled, "Changes" shall be given to the Contracting Officer. Approval of the submittals by the Contracting Officer shall not be construed as a complete check, but will indicate only that the general method of construction and detailing is satisfactory. Contractor shall be responsible for the dimensions and design of connection details and construction of work. Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.

f. If changes are necessary to approved submittals, the Contractor shall make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change shall be accomplished until the changed submittals are approved.

1.6.2 Sample Approval

Contractor shall furnish, for the approval of the Contracting Officer, samples required by the specifications or by the Contracting Officer. Shipping charges shall be paid by the Contractor. Materials or equipment requiring sample approval shall not be delivered to the site or used in the work until approved in writing by the Contracting Officer.

Each sample shall have a label indicating:

a. Name of project

b. Name of Contractor

c. Material or equipment

d. Place of origin

e. Name of producer and brand

FACILITY FOR COMMAND POST BLDG. 807 RVKQ14-0607 A & B

SECTION 01 33 00 Page 5

f. Specification section to which samples applies

g. Samples of furnished material shall have additional markings that will identify them under the finished schedules.

Contractor shall submit to the Contracting Officer one sample of materials where samples are requested.

Contractor shall transmit with each sample a letter, original and two copies, containing the above information.

Approval of a sample shall be only for the characteristics or use named in such approval and shall not be construed to change or modify any contract requirements. Before submitting samples, the Contractor shall assure that the materials or equipment will be available in quantities required in the project. No change or substitution will be permitted after a sample has been approved.

Materials and equipment incorporated in the work shall match the approved samples. If requested, approved samples, including those which may be damaged in testing, will be returned to the Contractor, at his expense, upon completion of the contract. Samples not approved will also be returned to the Contractor at its expense, if so requested.

Failure of any materials to pass the specified tests will be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make of that material. Government reserves the right to disapprove any material or equipment which previously has proved unsatisfactory in service.

Variations from contract requirements shall be specifically pointed out in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.

Samples of various materials or equipment delivered on the site or in place may be taken by the Contracting Officer for testing. Samples failing to meet contract requirements will automatically void previous approvals.

Contractor shall replace such materials or equipment to meet contract requirements.

Approval of the Contractor's samples by the Contracting Officer shall not relieve the Contractor of his responsibilities under the contract.

3.1 GENERAL

The Contractor shall make submittals as required by the specifications. The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Units of weights and measures used on all submittals shall be the same as those used in the contract drawings. Each submittal shall be complete and in sufficient detail to allow ready determination of compliance with contract requirements. Proposed deviations from the contract requirements shall be clearly identified. Submittals shall include items such as: Contractor's, manufacturer's, or fabricator's drawings;

descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals. Submittals requiring Government approval shall be scheduled and made prior to the acquisition of the material or equipment covered thereby. Samples remaining upon completion of the work shall be picked up and disposed of in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.

FACILITY FOR COMMAND POST BLDG. 807 RVKQ14-0607 A & B

SECTION 01 33 00 Page 6

3.2 SUBMITTAL REGISTER REFER TO ATTACHED SUBMITTAL LIST

3.3 SCHEDULING

Submittals covering component items forming a system or items that are interrelated shall be scheduled to be coordinated and submitted concurrently. Certifications to be submitted with the pertinent drawings shall be so scheduled. Adequate time (a minimum of 14 calendar days exclusive of mailing time) shall be allowed and shown on the register for review and approval. No delay damages or time extensions will be allowed for time lost in late submittals.

3.4 TRANSMITTAL FORM (AF FORM 3000)

The sample transmittal form (AF Form 3000) attached to this section shall be used for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor. This form shall be properly completed by filling out all the heading blank spaces and identifying each item submitted. Special care shall be exercised to ensure proper listing of the specification paragraph and/or sheet number of the contract drawings pertinent to the data submitted for each item.

3.5 SUBMITTAL PROCEDURE

Submittals shall be made as follows:

3.5.1 Procedures

All submittals, except warranties and operating instructions, shall be made using AF Form 3000 no later than 10 days after receipt of the notice to Proceed, or as specified by the Contracting Officer. Four (4) copies of all submittals are required to be sent to the Contracting Officer. The Contracting Officer will return one (1) copy of the submittals approved or disapproved within 10 days working after receipt, using AF Form 3000. If submittals cannot be made within 10 days after Notice to Proceed, or as specified by the Contracting Officer, the Contracting Officer shall be advised of the difficulty and an extension of time required. The attached Submittal List is an itemized list of materials requiring drawings, wiring diagrams, certificates, manufacturers literature, data brochures, technical data and samples as noted to be submitted to the contracting Officer by the Contractor using AF Form 3000.