050212-statement of work24dec08.pdf
PDF 8 KB Posted
- Attached to
- Welding Shop Electrical Upgrade
- Solicitation number
- FA6670-09-B-0001
About this file
Statement of Work
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 09B1 Amend 0003.pdf | ||
| FA6670-09-B-0001, Site Visit Questions & Answers.pdf | ||
| 09B1 Amend 0002.pdf | ||
| 09B1 Addendum #1.pdf | ||
| af3000.pdf | ||
| weldshopTABLE OF CONTENTS | — | |
| Spec 16415A.pdf | ||
| Weldshopdwgs.pdf | ||
| Spec16375A.pdf | ||
| weldspeccover.pdf | ||
| Spec 01330.pdf | ||
| 01330 _SUBMITTAL LIST.pdf | ||
| Spec 16050N.pdf | ||
| spec 02220.pdf | ||
| FA6670-09-B-0001.pdf | ||
| 2008biddocs.lnk | LNK file | |
| 09B1 Amend 0001.pdf | ||
| DB Wage Decision 1-2-09.pdf |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
24 December 2008
STATEMENT OF WORK
RVKQ 05-0212
Welding Shop Electrical Upgrade
Building 847
DESCRIPTION OF PROPOSED CONSTRUCTION:
1.) Provide all material and labor to upgrade the existing electrical services from a 225 amp, 120/208 volt, three phase to a 120/208 volt, three phase, 600 amp. Existing primary electric and transformer concrete pad will be utilized. Remove existing 75 kVA transformer and secondary feeders. Contractor shall properly dispose of existing transformer. Provide a new 225 kVA transformer with new secondary service conduits, conductors, and distribution panel as shown on attached line diagram.
2.) Location of the new service panel will be on the inside north west corner of the building. This panel will support new equipment loads and will have a 225 amp sub feed breaker to feed the existing distribution panel located in the north east corner of the building.
3.) Conductors and conduit shall be run to locations of new equipment, final equipment location to be determined in the field.
4.) Remove 120V duplex receptacle and feeder to allow for panel installation. Provide unistrut and required mounting hardware to install panel. Panel shall be offset from wall with strut to clear compressed air line.
5.) Remove 100A disconnect for temporary trailer service tap at transformer and reconnect into new panel MDP. Provide feeders for new electrical equipment. Refer to panel schedules and one-line for conduit and cable sizes.
6.) All wiring shall meet the National Electrical Code, current edition.
7.) Project submittals shall be submitted in accordance with Section 01330.