Wage_Determination_MN96.doc
DOC document 38 KB Posted
- Attached to
- Repair Perimeter Fence Federal contract opportunity
- Solicitation number
- FA6633-16-B0004
About this file
Wage Determination MN96
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Site_Visit_Minutes_18May16.pdf | ||
| Sign_in_2.pdf | ||
| FA6633-16-B0004 _0002_Amendment.docx | DOCX document | |
| QJKL_150037-Drawings-04May2016.pdf | ||
| 01_Technical_Specifications_-_27April2016.pdf | ||
| FA6633-16-B0004_0001_Repair_Perimeter_Fence.pdf | ||
| Sign_in_roster.pdf | ||
| Site_Visit_Minutes_21Apr16.pdf | ||
| SF_24_Bid_Bond_Form.pdf | ||
| Financial_Responsibility_Sheet.doc | DOC document | |
| Drawings_-_8March2016.pdf | ||
| Technical_Specifications-8March2016.pdf | ||
| FA6633-16-B0004 _Solicitation.docx | DOCX document |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
General Decision Number: MN160096 01/08/2016 MN96
Superseded General Decision Number: MN20150096
State: Minnesota
Construction Type: Heavy
Heavy including Water and Sewer Lines
County: Hennepin County in Minnesota.
HEAVY CONSTRUCTION PROJECTS (including sewer/water construction).
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.15 for calendar year 2016 applies to all contracts subject to the Davis-Bacon Act for which the solicitation was issued on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least
$10.15 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2016. The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date
0 01/08/2016
* CARP0548-002 05/01/2015
Rates Fringes
CARPENTER (Including Form
Work)............................$ 35.85 17.78
ELEC0292-024 05/01/2014
Rates Fringes
ELECTRICIAN......................$ 36.53 26.08
ENGI0049-064 05/01/2015
Rates Fringes
OPERATOR: Power Equipment
Group 2.....................$ 33.78 17.90
Group 3.....................$ 33.23 17.90
Group 4.....................$ 32.93 17.90
Group 5.....................$ 29.89 17.90
Group 6.....................$ 28.68 17.90
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 2: Crane with over 135' Boom, excluding jib; Dragline
& Hydraulic Backhoe with shovel-type controls, 3 cubic yards and over; Grader/Blade finishing earthwork and bituminous.
GROUP 3: Dragline & Hydraulic Backhoe with shovel-type controls up to 3 cubic yards; Loader 5 cu yd and over;
Mechanic; Tandem Scraper; Truck Crane; Crawler Crane
GROUP 4: Bituminous Roller 8 tons & over; Crusher/Crushing
Plant; Drill Rig; Elevating Grader; Loader over 1 cu yd;
Grader; Pump; Scraper up; to 32 cu yd; Farm Tractor with
Backhoe attachment; Skid Steer Loader over 1 cu yd with
Backhoe attachment; Bulldozer over 50 hp.
GROUP 5: Bituminous Roller under 8 tons; Bituminous Rubber
Tire Roller; Loader up to 1 cu yd; Bulldozer 50 hp or less.
GROUP 6: Oiler; Self-Propelled Vibrating Packer 35 hp and over.
CRANE OVER 135' BOOM, EXCLUDING JIB - $ .25 PREMIUM;
CRANE OVER 200' BOOM, EXCLUDING JIB - $ .50 PREMIUM
UNDERGROUND WORK:
UNNELS, SHAFTS, ETC. - $ .25 PREMIUM
UNDER AIR PRESSURE - $ .50 PREMIUM
HAZARDOUS WASTE PROJECTS (PPE Required):
LEVEL A - $1.25 PREMIUM
LEVEL B - $ .90 PREMIUM
LEVEL C - $ .60 PREMIUM
IRON0512-041 05/01/2015
Rates Fringes
IRONWORKER, STRUCTURAL AND
REINFORCING......................$ 35.50 23.45
LABO0563-026 05/01/2014
Rates Fringes
LABORERS
(1) Common or General
Laborer; Top Person.........$ 27.77 16.52
(2) Mason Tender
Cement/Concrete.............$ 27.97 16.52
(6) Pipe Layer..............$ 30.27 16.52
LABO0563-047 05/01/2012
Rates Fringes
LABORER (LANDSCAPE)..............$ 17.49 12.10
PLAS0633-004 05/09/2012
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 32.80 17.00
PLUM0015-023 05/01/2015
Rates Fringes
PLUMBER..........................$ 38.11 20.42
FOOTNOTE:
Paid Holiday: Labor Day
PLUM0539-017 05/01/2015
Rates Fringes
PIPEFITTER.......................$ 37.72 24.49
TEAM0160-016 05/01/2015
Rates Fringes
TRUCK DRIVER (DUMP)
(1) Articulated Dump Truck..$ 29.10 15.20
(2) 3 Axles/4 Axles; 5
Axles receive $0.30 additional per hour.........$ 28.55 15.20
(3) Tandem Axles; & Single
Axles.......................$ 28.45 15.20
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses
(29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate
(weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or
"UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010
08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour
Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the
Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the
Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator
(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative
Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
Wage Determination
FA6633-16-B0004
File details come from the government source that posted it. Updated .